Date: xxx
Ref. xxx
Kind Attn: Mr. xxx
Project: 2B + G + 14+ Lower Roof Hotels Building
Plot No.: xxx at Al Barsha 1st, Dubai
Subject: Regarding MP Coordination layout
Dear Tahir,
With ref. to above, we need impact analysis, kindly provide us the following
- If we are implementing the change of wiring diagram for Room management system as per AP/269/CC/96 dt.03.07.16 what all changes will happen in our scope.
- By comparing change of wiring diagram for Room management system, kindly give us your opinion whether there will be any change in the cost impact.
- Is there any impact in the project schedule from the changed ID drawing to execution?
Regards,
For xxx Contracting L.L.C
xxx
General Manager