Variation Order Request

Final Submission of Variation Order No. 6A R1

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Final Submission of Variation Order No. 6A R1 – Change in Stag Bar Door Location after complying with comments in document ref: xxx Dear Sir, With […]

Final Submission of Variation Order No. 6A R1 Read Post »

Claim rejected

Rejection of Lift Lobby Shop Drawing for Tile at Typical Floor

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding rejection of Lift Lobby Shop Drawing for Tile at Typical Floor and Additional Instruction by ID Dear Sir, With reference to our submission ref. xxx

Rejection of Lift Lobby Shop Drawing for Tile at Typical Floor Read Post »

Supply of swimming pool deck tiles

Improper tile ratio supplied for pool deck area

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding improper tile ratio supplied for pool deck area( shortage of NEOSTONE AVORIO GRIPM 333X333) Dear Sir, With reference to above there is shortage of the

Improper tile ratio supplied for pool deck area Read Post »

Variation notification

Reminder for BOH Threshold and Vanity Counter Nomination

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Reminder for BOH Threshold and Vanity Counter Nomination for Remaining Area Dear Sir, With reference above subject, we would like to inform you that we are

Reminder for BOH Threshold and Vanity Counter Nomination Read Post »

Letter Sample

Reply – renewal of CAR insurance, your ref no. xxx dated xxx

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding your letter renewal of CAR insurance, your ref no. xxx dated xxx Dear Sir, With reference above, we would like to inform you that CAR

Reply – renewal of CAR insurance, your ref no. xxx dated xxx Read Post »

Variation Order Request

Variation for additional column and block wall at main entrance area in Ground Floor.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Variation for additional column and block wall at main entrance area in Ground Floor. Dear Sir, With reference to above subject we would like to submit

Variation for additional column and block wall at main entrance area in Ground Floor. Read Post »

Bituminous-Membrane-Waterproofing

NCR for roof water proofing system and approved materials

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding NCR for roof water proofing system and approved materials                       And re-confirmation / undertaking Dear Sir, With reference to the above mentioned subject, we

NCR for roof water proofing system and approved materials Read Post »

fixing the floor tile

14th floor toilet and ablution tile

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject       : 14th floor toilet and ablution tile Dear Sir, With reference to the above, we would like to inform you that we followed continuously to provide tile

14th floor toilet and ablution tile Read Post »

Approval

Delay in approval of Steel Structure and additional cost

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject       : Regarding the delay in approval of Steel Structure and additional cost of                       Mobile crane since we are removing the tower crane Dear Sir, With

Delay in approval of Steel Structure and additional cost Read Post »

Slow Progress

Reply – slow progress Of work and resources issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject       : Regarding your mail dated xxx, regarding slow progress                   Of work and resources issue Dear Sir,                With reference to your above mail (copy attached)