Issue of MEP  (Formal reminder)

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject    :     Issue of MEP  (Formal reminder) Dear Mr.Tahir, With reference to the above mentioned subject please find the followings. Revised Corridor coordination drawing not yet submitted. We have issue of time extension […]

Opening Size and  location

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject           : Opening Size and  location Dear Sir, With reference to the above, we  would like to inform you that, we already finished the block work and plaster work  up to 6th floor […]

Regarding RMU room drawing

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject           : Regarding RMU room drawing Dear Sir, As we received the RMU room drawing from  you , and note the following instructions which you have been delivered to us : The DEWA […]

Regarding minutes of meeting held on dated xxx and the pending MEP work which are awaited to address

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          :  Regarding minutes of meeting held on dated xxx and the pending MEP work which are awaited to address Dear Sir , With reference to the above, we would like to inform […]

Regarding Submission of variation for GRAMS and for other items

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          : Regarding Submission of variation for GRAMS and for other items Dear Mr Tahir, With reference to above we would like to inform you that we are waiting all MEP variation for the […]

Very serious concern and need senior foreman from MEP dept

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          :  Very serious concern and need senior foreman from MEP dept Dear Mr.Tahir, With reference to the above, we would like to inform you as we notice that your engineers are busy […]

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          :  Instruction to review the swimming pool  drawings and claim for the variation. Dear MEP team, With reference to the above, we would like to inform you that the variation for kitchen […]

REQUEST FOR THE FEEDBACK OF ID DRAWINGS

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          :  REQUEST FOR THE FEEDBACK OF ID DRAWINGS Dear MEP team, With reference to the above, we would like to inform you that we have submitted ID drawings for first floor and […]

Protocol for Permission from QA/QC Division and Time for Approval

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject          :  Protocol for Permission from QA/QC Division and Time for Approval Dear Mr. Teja, The protocol of cutting/changing/ core cutting /breaking of wall at any part of the project, you must provide […]

Regarding follow up of pending work

Date: xxx Ref. xxx Kind Attn:     Mr. xxx Project:            2B + G + 14+ Lower Roof Hotels Building Plot No.:          xxx at Al Barsha 1st, Dubai Subject:         Regarding follow up of pending work Dear Tahir, With ref. to above, the following are to be submitted to consultant. Inclusion/ exclusion items to be submitted Long lead item must be submitted […]