METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION Material to be used:  NEPRO / PIPES: Approved (Trans # M-088) NAMAT-PVC FITTINGS: Approved (Trans # M-076) Summary:   This Method of Statement includes all the underground sewer                               pipe installation. 1. Procedure Excavate trenches to provide a clearance 300mm on each of the pipe. Bedding to be compacted in layers not exceeding […]

METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION

METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION Summary:   This Method of Statement includes all the underground sewer                               pipe installation. 1. Procedure Excavate trenches to provide a clearance 200mm on each of the pipe. Bedding to be compacted in layers not exceeding 150mm to give uniform bed. Lay the pipe directly on the bedding. The pipes must be installed […]