HAZARD / WORK: Casting Blinding Concrete and Installation of Precast Box Culvert Units LOCATION:______________________________________________ H=High M=Medium L=Low Significant Risks H M L Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries X 2 Dehydration, heat exhaustion. Heat stroke … Continue reading ACTIVITY HAZARD ANALYSIS Casting Blinding Concrete and Installation of Precast Box Culvert Units
Category: Risk Assessment
ACTIVITY HAZARD ANALYSIS PLACING OF SELECT FILL
HAZARD / WORK: PLACING OF SELECT FILL LOCATION:______________________________________________ H=High M=Medium L=Low Significant Risks H M L Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries. X 2 Dehydration, heat exhaustion. Heat stroke X Employees…………………… X 3 Cuts,… Continue reading ACTIVITY HAZARD ANALYSIS PLACING OF SELECT FILL
JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS Manual Handling COSHH Excavations NOISE
Toolbox talks:-Manual HandlingCOSHHExcavationsNOISE Manual Handling We lift, manoeuvre and handle goods every day of our lives in one way or another, not just whilst at work but also during social activities such as gardening, DIY, shopping and sport. A bad back or injury today, could, and regularly does, turn into a painful back problem for… Continue reading JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS Manual Handling COSHH Excavations NOISE
JOB HAZARD ANALYSIS Construction of AGL Ducts & installation of precast AGL Lighting Pits
The responsible person is to ensure all the controls below are in place before the activity takes place TASK: Construction of AGL Ducts & installation of precast AGL Lighting Pits Date: 04 November 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey… Continue reading JOB HAZARD ANALYSIS Construction of AGL Ducts & installation of precast AGL Lighting Pits
CTIVITY HAZARD ANALYSIS – Construction of AGL Ducts & installation of precast AGL Lighting Pits
HAZARD / WORK: AHA Construction of AGL Ducts & installation of precast AGL Lighting Pits LOCATION:______________________________________________ H=High M=Medium L=Low Significant Risks H M L Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries X 2 Dehydration, heat exhaustion. Heat stroke… Continue reading CTIVITY HAZARD ANALYSIS – Construction of AGL Ducts & installation of precast AGL Lighting Pits
JOB HAZARD ANALYSIS Method Statement for Excavation and Foundation Preparation of Box Culvert
TASK: Excavation and foundation preparation of Box culvert Date:15th July 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use of equipment to reduce need… Continue reading JOB HAZARD ANALYSIS Method Statement for Excavation and Foundation Preparation of Box Culvert
ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation of Box Culvert
HAZARD / WORK: Excavation and Foundation preparation of Box Culvert LOCATION:______________________________________________ H=High M=Medium L=Low Significant Risks H M L Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries X 2 Dehydration, heat exhaustion. Heat stroke X Employees……………………… Continue reading ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation of Box Culvert
JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS
Toolbox talks:-Manual HandlingCOSHHNOISE Manual Handling We lift, maneuver and handle goods every day of our lives in one way or another, not just whilst at work but also during social activities such as gardening, DIY, shopping and sport. A bad back or injury today, could, and regularly does, turn into a painful back problem for… Continue reading JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS
The responsible person is to ensure the control measures below are in place before the activity takes place
The responsible person is to ensure the control measures below are in place before the activity takes place
ACTIVITY HAZARD ANALYSIS – Placing of Bituminous pavement
ACTIVITY HAZARD ANALYSIS – Placing of Bituminous pavement