Delay by nominated subcontractor and serious concern at site for pending work.

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject   : Delay by nominated subcontractor and serious concern at site for pending work. Dear Sir, With reference to above, we would like to inform you that we did all our close […]

interlock drawing proposed by your office And feedback from the interlock subcontractor

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        :  Regarding road side interlock drawing proposed by your office                        And feedback from the interlock subcontractor Dear Sir, With reference of above we would like to inform you that we send […]

Request to release the ramp  drawing for physically challenge people

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        :  Regarding Issue related  entrance area flooring and request to release the ramp  drawing for physically challenge people as well as interlock stamp drawing from the RTA Dear Sir, With reference to […]

External stone cladding and flooring stone quality issue

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding external stone cladding and flooring stone quality issue (stone supplied by RBM, nominated supplier by client) Dear Sir, With reference to above we would like to inform you that flooring […]

Requirement of core cutting for steel structure erection

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Requirement of core cutting for steel structure erection at gas tank area due to Re-bar obstruction Dear Sir, With respect above our sub contractor have completed the drilling whereas it is […]

Reply – to provide signage quantity and our submission

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Reply – to provide signage quantity and our submission Dear Sir, With respect and refer to above, we are hereby attaching the total signage quantity calculated from signage drawing and kindly […]

Rejection of the mock up shower partition

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Rejection of the mock up shower partition request ref: 56R4 dated xxx Dear Sir, With reference to above, we are hereby intimating that our glass partition sample was rejected as per […]

invoice issued from Smart monitoring system (24×7) and request for cheque payment

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Submission of the fee estimate invoice issued from Smart monitoring system (24×7) and request for cheque payment Dear Sir, With reference to above, we are hereby submitting the required fee estimate […]

shaft closing approval from 2nd floor to 13th floor and issue future access

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding the closing of shaft from 2nd floor to 13th floor approval and issue access door/panels for future maintenance Dear Sir, With reference to above, are hereby informing you that we […]

Variation order for shower partition due to change in the tender drawing

Date:               xxx Ref:                  xxx Kind Attn         :Mr. xxx Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai Subject        : Regarding variation order no:42 submission for shower partition due to change in the tender drawing Dear Sir, With reference to above, and our previous communication letter ref no: xxx dated xxx, […]