METHOD OF STATEMENT  FOR ELECTRIC WATER HEATER INSTALLATION

METHOD OF STATEMENT  FOR ELECTRIC WATER HEATER INSTALLATION Open an approved shop drawing for electric water heater location. Electric water heater to be installed should have already passed the qualification test before installation. Check and secure that all accessories and parameters are complete base on its available manual. Locate and install water heater on the wall, level and plumb, and […]

TV SPLITTER INSTALLATION AND WIRING TERMINATIONS

TV SPLITTER INSTALLATION AND WIRING TERMINATIONS MATERIAL TO BE USED:- Flush mounted TV splitter metal enclosure with size 150xl50xlOOmm manufactured by Eletra with sufficient knock outs and frame to install 2 way splitter and 6 way splitter in this enclosure. RG 6 – C5760 Coaxial Cable is installed between individual TV outlets and 6 way splitter boxes installed in ground […]

METHOD STATEMENT PANEL BOARD INSTALLATION AND POWER CABLE TERMINATION

METHOD STATEMENT PANEL BOARD INSTALLATION AND POWER CABLE TERMINATION MATERIAL TO BE USED:- 1.       PANEL BOARDS are all metallic enclosures with completely insulated bus bar, protected Neutral bars. Earth and Neutral terminal with knock outs at top and bottom removable gland plates, and with zinc coated metal sheet 1 .2mm without any welding joints and flush mounted type. (The manufacturer, […]

METHOD OF STATEMENT FOR WATER TANK INSTALLATION

METHOD OF STATEMENT FOR WATER TANK INSTALLATION 1.       Summary:    This section includes the following:- Approve Materials: Excavation Compaction Lean Concrete Backfilling 2.       Approved Material: Underground Fiber Glass Water Tank (Capacity 13,000 Lts) 4.51m x 2.00m 2.44m x 3.12m 2.44m x 3.12m 2.44m x 3.12m Sandfilling Material 3.       Excavation:            Excavate the area as per the approved location and size […]

METHOD STATEMENT FOR UNDERGROUND WATER PIPE LINE INSTALLATION

METHOD STATEMENT FOR UNDERGROUND WATER PIPE LINE INSTALLATION DRAWINGS : Follow approved water supply drawings. MATERIALS :a.) Approved PVC schedule 80 pipes and fittings for water lines.b.) Fine sand for sand bedding. Method of Installations:a.) Prepare approved drawings for water lines and significant materials and tools for pipe installation.b.) Excavate trenches up to required level according to drawings with a […]

METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION INSIDE THE TOILET

METHOD OF STATEMENT FOR WATER SUPPLY PIPE INSTALLATION INSIDE THE TOILET Open an approved toilet detail shop drawing. This drawing should be accompanied with the approved location of mechanical pipe sleeves for both A/C indoor unit refrigeration tubes/pipes and sanitary fixtures ventilation. Installation of pipes should be done after the block work inside the toilet. Locate the pipe locations in […]

METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION

METHOD OF STATEMENT OF UNDERGROUND PIPE INSTALLATION Material to be used:  NEPRO / PIPES: Approved (Trans # M-088) NAMAT-PVC FITTINGS: Approved (Trans # M-076) Summary:   This Method of Statement includes all the underground sewer                               pipe installation. 1. Procedure Excavate trenches to provide a clearance 300mm on each of the pipe. Bedding to be compacted in layers not exceeding […]

METHOD OF STATEMENT FOR PLUMBING FIXTURE INSTALLATION

METHOD OF STATEMENT FOR PLUMBING FIXTURE INSTALLATION Open an approved shop drawings. This shop drawing consist of approved toilet details and floor plans. Assemble plumbing fixtures and trim, fittings, faucets, and other components according to manufacturers’ written instructions, approved shop drawings, and referenced standards.For Water Closet:Secure approved material inspection request (MIR) for the WC.Recheck the item for any damage and […]

METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET

METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET Open an approved shop drawings. This shop drawings consist of approved Toilet details and mechanical pipe sleeves location for both indoor unit refrigeration pipes and sanitary fixtures ventilation. Block work (except the shaft walls) and water proofing activity should be done first before installation. Waiting pipes, stub pipes and fittings […]