Method Statement for Sub base and Gravel Base

Method Statement for Excavation and Foundation Preparation of Box Culvert

Table of Contents Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments   1.0       Purpose To ensure that all excavation and foundation preparation of Box Culvert activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in […]

Method Statement for Excavation and Foundation Preparation of Box Culvert Read Post »

Risk Assessment Procedure Step wise Guide

JOB HAZARD ANALYSIS Method Statement for Excavation and Foundation Preparation of Box Culvert

  TASK: ­­­­­­­­Excavation and foundation preparation of Box culvert     Date:15th July 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use of equipment to reduce need

JOB HAZARD ANALYSIS Method Statement for Excavation and Foundation Preparation of Box Culvert Read Post »

Risk Assessment Procedure Step wise Guide

ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation of Box Culvert

HAZARD / WORK: Excavation and Foundation preparation of Box Culvert LOCATION:______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees……………………

ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation of Box Culvert Read Post »

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

Method Statement for Construction of cast-in-situ chambers (Wash out, air release, gate valve chamber, hydrant & water meter chamber)

CONTENTS Scope of Work Definitions References Subcontractors Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments 1. Scope: 1.1 This Method Statement covers the construction of cast-in-situ chambers of the fire and water supply network intended for the wash out, air release valve, gate valve and hydrant elements. 2. Definitions: 2.1     MS: STM Method

Method Statement for Construction of cast-in-situ chambers (Wash out, air release, gate valve chamber, hydrant & water meter chamber) Read Post »

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

Method Statement for Construction of Ducts for Fire & Water Supply Network

CONTENTS Scope of Work Definitions References Subcontractors Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments  1. Scope: 1.1 This Method Statement covers the construction of ducts for fire and water supply network under taxiways, roads and wherever needed. 2. Definitions: 2.1     MS: STM Method Statement : Ducts for fire and water supply networks.

Method Statement for Construction of Ducts for Fire & Water Supply Network Read Post »

Rockwool panel

Method Statement for Erecting Sandwich Panels

CONTENTS Scope of Work Definitions References Subcontractors Materials Tools  & Equipment Safety Prior Activities Procedure Responsibilities Attachments 1. Scope: 1.1 This Method Statement covers the erection/installation of wall and roof sandwich panels for the temporary site offices of Parsons, Halcrow and OAJ.   2. Definitions: 2.1     CM: Construction Manager     2.2 SE: Site Engineer

Method Statement for Erecting Sandwich Panels Read Post »