ACTIVITY HAZARD ANALYSIS Construction of Open Grouted Riprap Formed Channel

Method Statement for Construction of Open Grouted Riprap Formed

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the open grouted riprap formed channel is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and […]

Method Statement for Construction of Open Grouted Riprap Formed Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Open Grouted Riprap Formed Channel

ACTIVITY HAZARD ANALYSIS Construction of Open Grouted Riprap Formed Channel

HAZARD / WORK: Construction of Open Grouted Riprap Formed Channel LOCATION:   H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees……………………

ACTIVITY HAZARD ANALYSIS Construction of Open Grouted Riprap Formed Channel Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

Method Statement for Construction of Open Concrete Formed Channel

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the open concrete formed channel is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and conformance

Method Statement for Construction of Open Concrete Formed Channel Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

JOB HAZARD ANALYSIS Construction of Open Concrete Formed Channel

  TASK: ­­­­­­­­ Construction of Open Concrete Formed Channel (Types 2a and 2b)     Date: August 23, 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use

JOB HAZARD ANALYSIS Construction of Open Concrete Formed Channel Read Post »

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel

HAZARD / WORK: Construction of Open Concrete Formed Channel LOCATION:                                                                                                  H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X  

ACTIVITY HAZARD ANALYSIS Construction of Open Concrete Formed Channel Read Post »

Hazard Meaning and Definition

ACTIVITY HAZARD ANALYSIS Placing of Sub-base and Gravel base

HAZARD / WORK: Placing of Sub-base and Gravel base LOCATION:______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries.     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees…………………… X

ACTIVITY HAZARD ANALYSIS Placing of Sub-base and Gravel base Read Post »

Method Statement for Sub base and Gravel Base

Method Statement for Placing Sub-Base and Gravel Base by Pavers

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments 1.0    Purpose To ensure that placing of sub-base and gravel base by pavers, and related activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a

Method Statement for Placing Sub-Base and Gravel Base by Pavers Read Post »

METHOD STATEMENT FOR MV CABLE PULLING AND INSTALLATION

Method Statement for Casting of Blinding Concrete for Box Culvert and Installation of Precast Box Culvert Units

TABLE OF CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments 1. Purpose 1.1 To ensure that the Blinding of Box Culverts and Installation of Precast Box Culvert units are executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are

Method Statement for Casting of Blinding Concrete for Box Culvert and Installation of Precast Box Culvert Units Read Post »