JOB HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures

  TASK: ­­­­­­­­Excavation and foundation preparation for Building Structures     Date:31st October 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use of equipment to reduce need for MHO’s MHO Training prior […]

ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures

HAZARD / WORK: Excavation and Foundation preparation For Building     Structures    LOCATION: ______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees…………………… X 3 […]

Method Statement for Backfilling of Box Culverts and Associated Structures

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the backfilling of box culverts and associated structures (catch pits, access chambers, culvert outflow structures, transition manholes, etc.) is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in […]

JOB HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

The responsible person is to ensure the control measures below are in place before the activity is carried out   TASK: Backfilling of Box Culverts and Associated Structures     Date:14 October 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Backfilling & Compaction Equipment falling into work area Injuries to operatives in the […]

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

HAZARD / WORK: Backfilling of Box Culverts and Associated Structures LOCATION:______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees…………………… X 3 Cuts, abrasions, broken […]

Method Statement for Production of As-Built Drawings

As-built drawings are the most important documents in the construction process.  As-built drawings are usually the original design drawings revised to reflect any changes made in the field (e.g., design changes issued by change order and/or RFI, component relocations required for coordination, and rerouting of distribution systems).  All of these revisions will need prior approval of the Engineer/Consultant before implementation.  […]

JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS Construction of Open Grouted Riprap Formed Channel

Toolbox talks:-Manual HandlingCOSHHNOISE Manual Handling We lift, manoeuvre and handle goods every day of our lives in one way or another, not just whilst at work but also during social activities such as gardening, DIY, shopping and sport. A bad back or injury today, could, and regularly does, turn into a painful back problem for life! Lifting incorrectly could also […]

JOB HAZARD ANALYSIS Construction of Open Grouted Riprap Formed Channel

  TASK: ­­­­­­­­ Construction of Open Grouted Riprap Formed Channel (Type 1)     Date: September 16, 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use of equipment to reduce need for […]

Method Statement for Construction of Open Grouted Riprap Formed

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the open grouted riprap formed channel is executed safely and in accordance with the contract requirements and that all quality assurance/ control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented. […]