Programme of Works & Delivery Sequence

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Programme of Works & Delivery Sequence References: a) M/s xxx (Contractor Name) letter: xxx dated 20‐Aug‐xxxx b) M/s xxx (Contractor Name) letter: xxx dated 03‐Sep‐xxxx c) M/s xxx (Contractor Name) letter: xxx […]

Programme of Works & Delivery Sequence

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Programme of Works & Delivery Sequence Ref: a) M/s xxx (Contractor Name) letter: xxx dated 20-Aug-xxxx b) M/s xxx (Contractor Name) letter: xxx dated 3-Sep-xxxx Dear Sir, With reference to our previous […]

Response to Delay in Delivery of PODs

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Response to Delay in Delivery of PODs Dear Sir, We refer to our letter dated 20 Aug xxx ref. xxx which remained unanswered. Instead of reverting to our offer to finalize and […]

Status of delivery/approval of Ancona Smoke tiles

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Status of delivery/approval of Ancona Smoke tiles Dear Sir, We refer to our letter Ref: xxx dated 13 August xxxx As expected and communicated in our letter above, the shipment of “Ancona […]

Response to Delay in Delivery of PODs

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Response to Delay in Delivery of PODs References         :  (a) BGC letter ref: xxx dated 17 Aug xxxx                                 (b) M/s xxx (Contractor Name) letter ref: xxx dated 6 Aug xxxx                                 […]

Pending issues and Draft Schedule

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Pending issues and Draft Schedule Dear Sir, The aim of this letter is to address the current pending issues affecting the start of production, estimate a date for closing these issues, and […]

Bathtub drain

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2                Subject : Bathtub drain Dear Sir, With reference to the subject mentioned above, we would like to inform you that till date we did not receive any further communication regarding the pending bathtub drain […]

Response to Delay in Engineering Resubmission & Obtaining Engineer’s Approval.

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Response to Delay in Engineering Resubmission & Obtaining Engineer’s Approval. References Dear Mr. Sasi, With respect to the above subject and references and in response to your letter ref. (c) above, I […]

Delay in delivery of Mock-up apartment PODs.

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Delay in delivery of Mock-up apartment PODs. References Dear Sir, We are in receipt of your letter Ref. (a) above, and categorically reject your notice of delay in its entirety. Background Delivery […]

Cancellation of floor acoustic underlay (ERI-009)

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Cancellation of floor acoustic underlay (ERI-009) References: Dear Sir, With respect to the subject mentioned above, we again reject your letters ref (a) and (c) mentioned above. Your letter ref (c) is […]