Response to Notice of delay in finalizing walls & floor tiles.

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Response to Notice of delay in finalizing walls & floor tiles. References:  xxx dated 13 July xxx                        xxx dated 04 Aug xxx Dear Sir, We […]

Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations Dear Sir, As per the instructions received during site coordination meetings with your team, M/s […]

Rejection to Notice of Delay

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Rejection to Notice of Delay References: a) xxx dated 21 June xxx                       b) xxx dated 06 July xxx                       c) xxx dated 09 May xxx […]

Response to Notice of delay in finalizing walls & floor tiles.

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Response to Notice of delay in finalizing walls & floor tiles. Dear Sir, We are in receipt of your letter ref: xxx dated 02 August xxx […]

Rejection to Notice of Delay

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Rejection to Notice of Delay References: a) xxx dated 21 June xxx                       b) xxx dated 06 July xxx                       c) xxx dated 09 May xxx […]

Production Plan and prerequisite milestones

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Production Plan and prerequisite milestones Dear Sir, Following the ongoing coordination and discussions we had till date and based on your request to have the first […]

RE – Notice To Restart The Production and Delivery of Pods For xxx- 4

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject:                RE – Notice To Restart The Production and Delivery of Pods For PDLM – 4 Reference: a) M/s xxx (Contractor Name) Letter xxx dated 12 December […]

Notice of default (2)

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Notice of default (2) References:  a) xxx dated 05 April xxxx                        b) xxx dated 19 April xxxx                        c) xxx dated 27 April xxxx                        […]

Notice of default.

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Notice of default. References: a) xxx dated 05 April xxxx                        b) xxx dated 19 April xxxx                        c) xxx dated 27 April xxxx                        d) […]

Free Issue Materials status & Impact on production completion

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject                 : Free Issue Materials status & Impact on production completion Dear Mr. Wissam, We are writing to inform you that till date Free Issue Materials listed in […]