Notice of Delay – Materials Procurement

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Notice of Delay – Materials Procurement Dear Sir, Further to the material submittals we received today, we have noted the comments made […]

Notice of Delay – Materials Procurement Read Post »

Variation notification

Notice of Delay – Site Readiness

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Notice of Delay – Site Readiness Dear Sir, With regards to the above mentioned subject, we would like to notify you that

Notice of Delay – Site Readiness Read Post »

Engineer's Instruction

Mock-up Site Condition

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Mock-up Site Condition Dear Sir, Further to our email dated 23rd February xxx (copy attached) regarding the current condition of the Mock-up

Mock-up Site Condition Read Post »

Wardrobes

Mock-Up not Ready

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Mock-Up not Ready Dear Sir, Further to several exchanges of correspondences and emails regarding the mock-up flat and to my subsequent email

Mock-Up not Ready Read Post »

Justification for Manpower in Month of April xxx

Unavailability of Xxx (Name of the Subcontractor) Representative on Site and Non-Compliance to Subcontract Liabilities

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Unavailability of Xxx (Name of the Subcontractor) Representative on Site and Non-Compliance to Subcontract Liabilities Dear Sir, We acknowledge receipt of your

Unavailability of Xxx (Name of the Subcontractor) Representative on Site and Non-Compliance to Subcontract Liabilities Read Post »

Wardrobes

Mock-up Flat

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Mock-up Flat Dear Sir, We refer to your email dated 13th January xxx (copy attached) regarding the Mock-up Flat where you have

Mock-up Flat Read Post »

Engineer's Instruction

Delayed Release of Advance Payment

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Delayed Release of Advance Payment Dear Sir, We refer to your email dated 12th January xxx (copy attached) where you have informed

Delayed Release of Advance Payment Read Post »

advance payment

Delayed Release of Advance Payment

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Delayed Release of Advance Payment Dear Sir, We refer to our contract reference xxx dated 11th November xxx regarding the Supply and

Delayed Release of Advance Payment Read Post »

shake-up-sales-meeting

Communication

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Communication Dear Sir, Further to the above referred project, we would like to request that all communications from DECC to Romeo should

Communication Read Post »

Advance-Payment-Bank-Guarantee

Original Advance Payment Guarantee and Performance Guarantee

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject:            Original Advance Payment Guarantee and Performance Guarantee Dear Sir, Further to our Subcontract Agreement reference xxx dated 11th November xx regarding the

Original Advance Payment Guarantee and Performance Guarantee Read Post »