Variation notification

Notification of Delay

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject:           Notification of Delay Dear Sir, Further to the verbal instruction given by yourself to follow the revised ID drawings for the preparation of […]

Notification of Delay Read Post »

Engineer's Instruction

Confirmation of Verbal Instruction to Proceed with the Glass Panels under Provisional Sum

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject:           Confirmation of Verbal Instruction to Proceed with the Glass Panels under Provisional Sum Dear Sir, Further to our meeting today regarding the aforementioned,

Confirmation of Verbal Instruction to Proceed with the Glass Panels under Provisional Sum Read Post »

Project Work Program

Program Schedule of Works

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject:           Program Schedule of Works Dear Sir, Further to your request to provide you with the program of works with a completion date of

Program Schedule of Works Read Post »

What is Float Glass? Different types of float Glass

Supply of Intelligent Glass from UK

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject:           Supply of Intelligent Glass from UK Dear Sir, Further to your instruction to proceed with the order of the Intelligent Glass for the

Supply of Intelligent Glass from UK Read Post »

fixing doors

Damaged Kitchen Doors – Tower 2B

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Damaged Kitchen Doors – Tower 2B Dear Sir, We refer to the recent survey carried out for the Tower 2B where it

Damaged Kitchen Doors – Tower 2B Read Post »

Snagging and De-snagging

Damaged Wardrobe Doors – Tower 2B

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Damaged Wardrobe Doors – Tower 2B Dear Sir, We refer to your email dated 19th May xxx regarding the Damaged Wardrobe Doors

Damaged Wardrobe Doors – Tower 2B Read Post »

Engineer's Instruction

Damaged Wardrobe Doors – Tower 2B

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Damaged Wardrobe Doors – Tower 2B Dear Sir, We refer to your email dated 19th May xxx regarding the Damaged Wardrobe Doors

Damaged Wardrobe Doors – Tower 2B Read Post »

Variation notification

Notice of Delay – Tower 16A

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Notice of Delay – Tower 16A Dear Sir, We refer to our ongoing works on the above referred project; we would like

Notice of Delay – Tower 16A Read Post »

Damages to Completed Works

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Damages to Completed Works Dear Sir, We refer to the attached email communication forwarded to Mr. xxx and Mr. xxx on 26th

Damages to Completed Works Read Post »

Engineer's Instruction

Site Clearance

Letter Ref. xxx Date: xxx M/s xxx P. O. Box xxx, Doha, Qatar T. xxx E.   xxx Attention        :           Ms. xxxx                                     Technical Manager Project            :           xxx Qatar      Subject            :           Site Clearance Dear Sir, Further to our on-going works for the Tower 16A for the above referred project, we would like to

Site Clearance Read Post »