Narrative report for a Baseline Schedule

Narrative report for a Baseline Schedule.

Project Overview

  • Project Name: ABC Tower Construction Project
  • Contractor: XYZ Construction Ltd.
  • Client: DEF Real Estate
  • Contract Start Date: January 1, 2024
  • Contract Completion Date: December 31, 2024
  • Project Location: Downtown City

Introduction

This report presents the baseline schedule for the ABC Tower Construction Project, outlining the key phases, activities, and milestones. The baseline schedule has been developed using Primavera P6 and serves as the initial project plan against which future project performance will be measured. The objective of the schedule is to ensure that the project is completed within the contractual time frame while meeting the required quality and safety standards.

The baseline schedule includes the planned start and finish dates for each activity, identifies critical path tasks, and incorporates key milestones, dependencies, and resource allocation. This narrative provides an overview of the major elements of the schedule, assumptions, constraints, and other relevant considerations.

1. Methodology for Developing the Baseline Schedule

The baseline schedule was developed following a detailed review of the project scope, contract requirements, design documents, and client specifications. The scheduling process followed these key steps:

  1. Work Breakdown Structure (WBS): The project was divided into manageable components using a hierarchical Work Breakdown Structure (WBS) that captures all major phases and deliverables of the project.
  2. Activity Definition: Each component of the WBS was further broken down into specific activities. Every activity is well-defined with distinct start and finish dates, and includes durations, resources, and costs.
  3. Activity Sequencing: The logical relationships between activities were established to ensure proper sequencing. Dependencies such as Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF) were identified to maintain logical continuity.
  4. Resource Allocation: Labor, materials, and equipment requirements for each activity were assigned based on the project’s resource plan. The schedule considers resource availability and any constraints.
  5. Critical Path Analysis: A Critical Path Method (CPM) was used to identify the longest sequence of critical activities that determines the project’s overall duration. This analysis ensures that any delays to critical path activities would directly impact the project completion date.
  6. Milestones: Key project milestones, including contractual milestones such as foundation completion, structural topping out, building enclosure, and substantial completion, have been incorporated to monitor progress.

2. Major Phases and Milestones

The ABC Tower Construction Project consists of the following major phases, each with associated milestones:

A. Mobilization and Site Preparation (January 1 – February 15, 2024)

  • Key Activities:
  • Mobilization of equipment and personnel.
  • Site setup and temporary utilities.
  • Demolition and clearing of the site.
  • Milestone: Site Ready for Excavation – February 15, 2024.

B. Excavation and Foundations (February 16 – April 15, 2024)

  • Key Activities:
  • Excavation of the foundation pit.
  • Installation of piling and foundation concrete.
  • Underground utilities installation.
  • Milestone: Foundation Complete – April 15, 2024.

C. Superstructure Construction (April 16 – August 31, 2024)

  • Key Activities:
  • Construction of the building frame.
  • Structural steel and concrete works.
  • Erection of floors and core walls.
  • Milestone: Superstructure Topped Out – August 31, 2024.

D. Building Enclosure (September 1 – October 31, 2024)

  • Key Activities:
  • Installation of curtain walls and glazing.
  • Roof structure and waterproofing.
  • Façade finishes and external insulation.
  • Milestone: Building Enclosed – October 31, 2024.

E. Interior Fit-Out and MEP Installation (November 1 – December 15, 2024)

  • Key Activities:
  • Installation of mechanical, electrical, and plumbing (MEP) systems.
  • Interior drywall, painting, and flooring.
  • Installation of fixtures and equipment.
  • Milestone: MEP Commissioning Complete – December 15, 2024.

F. Testing, Commissioning, and Handover (December 16 – December 31, 2024)

  • Key Activities:
  • Final testing of MEP systems and elevators.
  • Site cleanup and preparation for handover.
  • Client walkthrough and final inspections.
  • Milestone: Substantial Completion – December 31, 2024.

3. Critical Path Activities

The critical path is composed of the activities that are essential for project completion within the contract duration. Any delay in these activities will impact the project completion date. Critical path activities identified in the baseline schedule include:

  1. Excavation Start and Completion
  2. Foundation Pouring
  3. Superstructure Frame Construction
  4. Curtain Wall Installation
  5. MEP Rough-in and Finishing
  6. Final Testing and Commissioning

Critical Milestone: Substantial completion is the ultimate critical path milestone, scheduled for December 31, 2024. Any slippage in earlier critical activities will impact this date.

4. Key Assumptions and Constraints

Assumptions:

  1. Weather Conditions: Normal weather patterns were assumed, with no significant delays from extreme weather.
  2. Client Decisions: Timely approval of drawings, materials, and change orders from the client.
  3. Resource Availability: Labor, materials, and equipment will be available as scheduled without any significant shortages.
  4. Permits and Inspections: All required permits and inspections will be obtained in a timely manner without delay.

Constraints:

  1. Limited Site Space: The project site is constrained due to its location in a downtown area, limiting space for materials storage and requiring just-in-time delivery.
  2. Regulatory Approvals: All construction work must comply with local building codes and regulations, and delays in regulatory approvals could impact progress.
  3. Supply Chain Delays: Any disruption in the supply chain for critical materials, such as steel and concrete, could cause schedule delays.

5. Potential Risks and Mitigation Measures

While the baseline schedule is achievable under normal circumstances, the following risks have been identified:

A. Weather-Related Delays

  • Risk: Heavy rainfall or extreme weather conditions during excavation and foundation work may delay progress.
  • Mitigation: Plan for weather contingency days in the schedule and allocate resources for accelerated work once weather conditions improve.

B. Supply Chain Interruptions

  • Risk: Delays in material deliveries, particularly for steel and façade components, could disrupt the critical path.
  • Mitigation: Engage multiple suppliers, maintain communication for early warning of disruptions, and order long-lead items well in advance.

C. Client-Requested Changes

  • Risk: Design changes requested by the client during the construction phase could delay activities.
  • Mitigation: Ensure timely communication with the client to confirm all design decisions early. Allocate float where possible for non-critical activities to absorb minor changes.

6. Monitoring and Updates

The baseline schedule will be monitored regularly throughout the project lifecycle. Monthly schedule updates will be provided to track progress, compare actual performance with the baseline, and identify any deviations. If necessary, recovery plans will be implemented to mitigate delays and bring the project back on track.

7. Conclusion

The baseline schedule for the ABC Tower Construction Project outlines a clear path to successful project completion within the contract duration of 12 months. The schedule has been carefully developed considering the project’s scope, constraints, and risks. This baseline will serve as the benchmark for measuring project performance and will be updated regularly to reflect actual progress.

The project is on target to meet the scheduled substantial completion date of December 31, 2024, provided that no unforeseen major delays occur.

Submitted by:
XYZ Construction Ltd.
[Your Name]
Project Manager
[Date]

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top