CHAPTER: 6. ESTIMATING& TENDRING
Chapter: 6. estimating& tendring ………………………………………………………………………………..220
.6.1 Introduction ………………………………………………………………………………………………………221
6.2. Methods of estimating: ……………………………………………………………………………………….222
6.2.1. Space method ………………………………………………………………………………………………222
6.2.2. Unit Method ………………………………………………………………………………………………..222
6.2.3. Element Method …………………………………………………………………………………………..223
6.2.4. Spot Method ………………………………………………………………………………………………..223
6.2.5. Detailed Method (Case Study)…………………………………………………………………………223
6.2.6. Operational Method: …………………………………………………………………………………….224
6.2.7. General WBS ………………………………………………………………………………………………..224
6.3. EXAMPLE …………………………………………………………………………………………………………..224
6.3.1. COLUMN WORKS ………………………………………………………………………………………….224
.6.3.2 SLABS WORKS ………………………………………………………………………………………………228
6.3.3. RETAINING WALL WORKS……………………………………………………………………………….231
6.4. Sheet of cost estimate: ………………………………………………………………………………………..238
.6.5 total direct cost: …………………………………………………………………………………………………362
6.5.1. Direct Cost of working items: ………………………………………………………………………….362
6.5.2. Direct cost of resource: ………………………………………………………………………………….363
6. Estimating &Tendering
6.1. INTRODUCTION
• Estimating is considered an approximate way to predict the costs of the project. By the way, tender study is considered one of the most important tasks in construction industry that enables the contractor from success through the profit that the contractor estimates and does is best to increase it though, the success of any company is measured by how much contracts can it take especially when the competition between companies is strong. So, to measure how the management department is successful we can use some indicators:
• Number of tenders can be taken divided by number of tenders that are being studied.
• The value of tenders can be taken divided by the value of tenders that are being studied.
• The difference between studied tender and the other one that can be obtained and, the next one respectively attributed to the total price.
6.2. METHODS OF ESTIMATING:
6.2.1. Space method
• Space method is away to estimate the cost of a structure by using the square meter cost in a similar structure.
6.2.2. Unit Method
• Unit method is away to estimate the cost of structure by using the unit cost of similar structure
• The cost of the whole structure is distributed to the units used in that structure like (Garage- Cars), (Hospital-Families) .
6.2.3. Element Method
• Element method is away to estimate accost of a structure by the cost of the structure elements like foundations, skeleton, decoration, etc.
6.2.4. Spot Method
• Spot method is a theoretical method to determine the cost of the structure using the experience
6.2.5. Detailed Method (Case Study)
• Estimating the items cost using predicted prices and quantities.
• There are two types:
• Unit rate method (case study)
• Items cost estimation is depending on production rate and a non- stop work.
• The cost elements are (Labors – Equipment –
Material –Sub Contractor)
6.2.6. Operational Method:
• Items cost estimation is depending on the construction duration and assuming that the item will be constructed as planned exactly so, the actual duration of the remaining in the site will be calculated
6.2.7. General WBS
• The WBS is a deliverable –oriented break down of components of the project. It helps the project manager and the project team identify the components requiring specific people, equipment, and materials. the WBS is the primary input to resource planning.
6.3. EXAMPLE
6.3.1. COLUMN WORKS
FOR LOWER BASEMENT: (SECOND BASEMENT)
1. SHUTTERING WORKS:
a) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE LE/DAY | |
راجن | 12 | 150 |
باشخ | 3 | 120 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=12*150+3*120=2160 LE/DAY
• Production rate for column=30 m3/day
• Quantity for column=94.5 m3
• Duration=quantity/production rate*no. of crew
=94.5/30=4 days
• Labor cost=duration*daily labor cost
=4*2160=8640 LE
b) FOR MATRIAL:
TYPE | QUANTITY (M3) | PRICE (LE/M3) | PERCENT OF DEPRECIATION |
SHEATHING | 18.75 | 5000 | %20 |
YOKS | 3.825 | 5000 | %20 |
BRACING | 2.76 | 5000 | %20 |
SHORE | 11.04 | 5000 | %2.5 |
تادناربلا | 2.76 | 5000 | %20 |
تاطحلا | 5.52 | 5000 | %20 |
تاشرفلا | 14.2451328 | 5000 | %2.5 |
• Cost of sheathing= quantity*price*percent of depreciation
=18.75*5650*.067= 5,293.84 LE
• Cost of yoks=3.825*5650*.02= 510.000 LE
• Cost of bracing=2.76*5650*.02= 276.00 LE
• Cost of shore=11.04*5500*.02= 138.00 LE
• Cost of تادنربلا= 2.76*5650*.02= 138.00 LE
• Cost of تاطحلا= 5.52*5650*.02= 276.00 LE
• Cost of تاشرفلا= 14.3*5000*.02= 712.26 LE
• Total cost of wood= 7,749.00 LE
c) FOR EQUIPMENT: there is no equipment d) FOR S/C: there is no s/c
Shuttering total cost= 16,389 LE
2. STEEL FIXING:
a) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
دادح | 12 | 150 |
دعاسم | 3 | 120 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=12*150+3*120=2160 LE/DAY
• Production rate for column=3.2 ton/day
• Quantity for column= 14 ton
• Duration=quantity/production rate*no. of crew
=14/3.2=5 days
• Labor cost=duration*daily labor cost
=5*2160=10,800.00 LE
b) MATRIAL COST:
• Quantity= 14 ton
• Price/ton=9800 LE/TON
• Cost of steel=14*9800=137,200.00 LE
c) FOR EQUIPMENT: there is no equipment d) FOR S/C: there is no s/c
Steel fixing total cost=148,000 LE
3. PLACING:
a) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
راجن | 3 | 150 |
ىجمروف | 4 | 120 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=3*150+4*120=1090 LE/DAY
• Duration=quantity/production rate*no. of crew
=94.5/50=2 days
• Labor cost=2*1090=2180 LE
b) FOR MATRIAL:
• Ready concrete mix=545 LE/M3
• Special addition=15 LE/M3
• Material cost/m3=545+15=560 LE/M3
• Material cost=94.5*560=52,920 LE
c) FOR EQUIPMENT:
• Pump cost/m3=50LE/M3
• Pump total cost=50*94.5=4,725 LE
d) FOR S/C: there is no s/c
Placing total cost= 59,825 LE
TOTAL COST=SHUTTERING COST+STEEL FIXING COST+PLACING COST=224,214 LE
6.3.2. SLABS WORKS
FOR LOWER BASEMENT: (SECOND BASEMENT)
4. SHUTTERING WORKS:
e) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE LE/DAY | |
راجن | 12 | 150 |
باشخ | 3 | 120 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=12*150+3*120=2160 LE/DAY
• Production rate for Slabs =30 m3/day
• Quantity for 2nd basement slab=483.6 m3
• Duration=quantity/production rate*no.of crew=483.6/30=17 days
• Labor cost=duration*daily labor cost=17*2160=36720 LE
f) FOR MATRIAL:
TYPE | QUANTITY (M3) | PRICE (LE/M3) | PERCENT OF DEPRECIATION |
ةنازتل | 84.1 | 5650 | 15% |
يكسوم | 235.1 | 5500 | 10% |
يريللف | 504.5 | 5500 | 2.2% |
ريماسم | 3 kg/m3 | 13 LE/kg | 50% |
• Cost = quantity*price*percent of depreciation
• ةنازتللا بشخ ةفلكت = 84.1*5650*0.15 = 71274.75 LE
• يكسوملا بشخ ةفلكت = 235.1*5500*0.1 = 129305 LE
• يريللفلا بشخ ةفلكت = 504.5*5500*0.022 =61044.5 LE
• ريماسملا ةفلكت = 3*(84.1+235.1+504.5)*0.5*13 = 16062.1 LE
Shuttering total cost= 314406.3 LE
5. STEEL FIXING:
e) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
دادح | 12 | 150 |
دعاسم | 3 | 120 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=12*150+3*120= 2160 LE/DAY
• Production rate for slabs = 4.5 ton/day
• Quantity for column= 51.64 ton with 7% depreciation
• Duration=quantity/production rate*no. of crew= 51.64 * 1.07 / 4.5 = 12 days
• Labor cost=duration*daily labor cost
=12*2160= 25920 LE
f) MATRIAL COST:
• Quantity= 51.64 ton
• Price/ton=9800 LE/TON
• Cost of steel=51.64*1.07*9800= 541497 LE)نط /مجك 5( طابرلا كلس ةفلكت =5 *52*13 = 3380 LE
Steel fixing total cost=570797 LE
6. PLACING:
e) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
راجن | 3 | 150 |
ىجمروف | 8 | 160 |
• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY
• Labor crew cost/day=3*150+8*160= 1730 LE/DAY
• Duration=quantity/production rate*no. of crew=483.6/150= 4 days
• Labor cost= 4*1730= 6920 LE
f) FOR MATRIAL:
• Ready concrete mix=545 LE/M3
• Special addition=15 LE/M3
• Material cost/m3=545+15=560 LE/M3
• Material cost=483.6*560=270816 LE
g) FOR EQUIPMENT:
• Pump cost/m3=50LE/M3
• Pump total cost=50*483.6= 24180 LE
Placing total cost= 301916 LE
TOTAL COST=SHUTTERING COST+STEEL FIXING COST+PLACING COST
= (1187119.3) LE
6.3.3. RETAINING WALL WORKS
1. Filling behind front retaining walls: –
Pa rt “ A”
رتم 11 = مدرلا قمع •
رتم 203 = مدرلا لوط •
رتم 2 = مدرلا ضرع •
3م 4466 = 2* 203* 11 = قمع * ضرع * لوط = هيمكلا •
• Duration = Quantity/ No.of crews * P.R
= 4466/ 150=30 days
مويلا/ هفلكتلا | تادعملا |
180 LE/ hr | ردول |
150 LE/ hr | بلاق |
150 LE/day | يندم فرشم |
g) FOR LABOR:
• Labor cost=duration*daily labor cost=30*150= 4500 LE
h) FOR EQUIPMENT: Working hours = 8 hr / day
• Equipment cost/day = 180*8+150*8= 2640 LE/day
• Equipment cost= 30*2640=79200 LE
i) FOR S/C: there is no s/c
j) FOR MATRIAL: there is no material
2. Filling behind back retaining walls :-
رتم 11 = مدرلا قمع • رتم 203 = مدرلا لوط • رتم 2 = مدرلا ضرع •
3م 4466 = 2* 203* 11 = قمع * ضرع * لوط = هيمكلا •
• Duration = Quantity/ No.of crews * P.R
4466/100 = 45 days
مويلا/ هفلكتلا | تادعملا |
180 LE/ hr | ردول |
150 LE/ hr | بلاق |
150 LE/day | يندم فرشم |
a) For Labor
Labor cost=duration*daily labor cost=45*150= 6750 LE
b) FOR EQUIPMENT:
• Working hours = 8 hr / day
• Equipment cost/day = 180*8+150*8= 2640 LE/day
• Equipment cost= 45*2640=118800 LE
c) FOR S/C: there is no s/c
d) FOR MATRIAL: there is no material
Filling total cost =4500+79200+6750+118800=209250 LE
3. SHUTTERING WORKS:
e) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE LE/DAY | |
راجن | 12 | 150 |
باشخ | 3 | 120 |
• Labor crew cost/day=12*150+3*120=2160 LE/DAY
• Production rate for retaining wall=80 m3/day
• Quantity for column=622 m3
• Duration=quantity/production rate*no.of crew
=622/80=8 days
• Labor cost=duration*daily labor cost
=8*2160=17280 LE
f) FOR MATRIAL:
-: يلا هينكسلا ينابملا يف هحلسملا هناسرخلا نم بعكم رتم 1 جاتحي
3م 78 = 622*0.125 = يكسوم •
3م 156 = 622*0.25 = هنازيتلا •
3م 498 = 622*0.8 = قورع •
رامسم مجك 1866 = 622*3 = رامسم •
” كلاهلاا ” بشخلا ةفلكت •
هينج 42900=78*5500*0.1 = يكسوملا بشخ ةفلكت •
هينج 132210=156*5650*0.15
= هنازيتلالا بشخ ةفلكت •
هينج 68475=498*5500*0.025 = قورعلا ةفلكت •
هينج 24631.2=1866*13.2 = رامسملا ةفلكت •
“%50 رامسملا كلاه”
• FOR EQUIPMENT: there is no equipment
• FOR S/C: there is no s/c
Shuttering total cost= 17280+268216.2 = 285496.2 LE
4. STEEL FIXING:
g) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
دادح | 12 | 150 |
دعاسم | 3 | 120 |
• Labor crew cost/day=12*150+3*120=2160 LE/DAY
• Production rate for Retaining Wall =10 ton/day
• Quantity for Retaining Wall = 87 ton
• Duration=quantity/production rate*no. of crew
=87/10=8.7 ~ 9 days
• Labor cost=duration*daily labor cost
=9*2160=17280 LE
1 ton of steel needs → 5 kg “ طابر كلس“
h) MATRIAL COST:
• Quantity= 87 ton
• Price/ton=9800 LE/TON
• Price/kg =13 LE
• طابرلا كلس ةفلكت =5*87*13 = 5655 LE
• FOR EQUIPMENT: there is no equipment
• FOR S/C: there is no s/c
Total Cost of steel=87*9800+5655=858255 LE
5. PLACING:
Cast for Basement 2 R.W Part A
h) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
راجن | 3 | 150 |
ىجمروف | 4 | 120 |
• Labor crew cost/day=3*150+4*120=1090 LE/DAY
• Duration=quantity/production rate*no. of crew
=622/150=4.15 days ~ 4 days
• Labor cost=4*1090=4360 LE
i) FOR MATRIAL:
• Ready concrete mix=545 LE/M3
• Special addition=15 LE/M3
• Material cost/m3=545+15=560 LE/M3
• Material cost=622*560=348320 LE
j) FOR EQUIPMENT:
• Pump cost/m3=50LE/M3
• Pump total cost=50*622=31100 LE
k) FOR S/C: there is no s/c
Placing total cost= 379420 LE
6. Membrane For R.W Part A
a) FOR LABOR:
LABOR CREW | ||
NO | ALL-IN RATE (LE/DAY) | |
يعيانص | 1 | 150 |
دعاسم | 1 | 120 |
• Area of membrane = 1589 M2
• 2م/ هينج 60 = ةدناسلا طئاوحلل لزعلا ذيفنتو ديروت
• Labor crew cost/day=1*150+1*120=270 LE/DAY
• Duration=quantity/production rate*no. of crew=1589/40=40 days
Membrane cost=40*270 =10800 LE
TOTAL COST = Filling cost + SHUTTERING COST+STEEL FIXING COST+PLACING COST + membrane cost
=209250+285496.2+858255+379420+10800 = 1743221.2 LE.
6.4. SHEET OF COST ESTIMATE:
COST ESTIMATE SHEET | |||||||||||||
ZONE(A) | |||||||||||||
ZONE(A) _ pc footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 201.15 | m3 | 2 | 4.00 | 1728 0 | 76 | 15287.4 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 32567.4 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 201.15 | m3 | 1 | 3 | 4710 | 560 | 112644 | 0 | 50 | 10057. 5 |
238
total direct cost =labor+material+equipment+s/c | 127411.5 | |||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
BACKFILLING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
150.00 | 150.00 | 451.00 | m3 | 2 | 2.00 | 600 | 30 | 13530 | 0 | 5280 | ||
total direct cost =labor+material+equipment+s/c | 19410.0 | |||||||||||
total pc footing cost zone A = | 179,388.9 | |||||||||||
ZONE(A) _ RC footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 296.45 | m3 | 2 | 5.00 | 2160 0 | 76 | 22530.2 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 44130.2 | |||||||||||
FIXING STEEL | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C |
239
2160 | 3.2 | 23.23 | Ton | 2 | 4 | 1728 0 | 9800 | 227654 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 244934.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 296.45 | m3 | 1 | 3 | 4710 | 560 | 166012 | 0 | 50 | 14822. 5 | ||
total direct cost =labor+material+equipment+s/c | 185544.5 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 452.3 | m2 | 2 | 4 | 2160 | 15 | 6784.5 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 8944.5 | ||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
BACKFILLING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
150.00 | 150.00 | 1334.00 | m3 | 2 | 5.00 | 1500 | 30 | 40020 | 0 | 13200 |
240
total direct cost =labor+material+equipment+s/c | 54720.0 | ||||||||||||
total rc footing cost zone A = | 538,273.2 | ||||||||||||
ZONE(A) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 266.60 | m3 | 1 | 4.00 | 8640 | 88 | 23460.8 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 32100.8 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 37.3 | m3 | 2 | 2 | 8640 | 9800 | 365540 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 374180.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
241
1090 | 150 | 266.60 | m3 | 1 | 2 | 2180 | 560 | 149296.0 0 | 0 | 50 | 13330 | ||
total direct cost =labor+material+equipment+s/c | 164806.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 780.4 | M2 | 1 | 20 | 5400 | 60 | 46824 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 52224.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 1560.8 | M3 | 1 | 11 | 1650 | 30 | 46824 | 0 | 2640 | 29040 | ||
total direct cost =labor+material+equipment+s/c | 77514.0 | ||||||||||||
total = | 700824.8 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 266.60 | m3 | 1 | 4.00 | 8640 | 88 | 23460.8 | 0 | 0 |
242
total direct cost =labor+material+equipment+s/c | 32100.8 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 37.3 | m3 | 2 | 2 | 8640 | 9800 | 365540 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 374180.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 266.60 | m3 | 1 | 2 | 2180 | 560 | 149296.0 0 | 0 | 50 | 13330 | ||
total direct cost =labor+material+equipment+s/c | 164806.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 780.4 | M2 | 1 | 20 | 5400 | 60 | 46824 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 52224.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C |
243
150 | 150 | 1560.8 | M3 | 1 | 11 | 1650 | 30 | 46824 | 0 | 2640 | 29040 | ||
total direct cost =labor+material+equipment+s/c | 77514.0 | ||||||||||||
total = | 700824.8 | ||||||||||||
Total RW zone A | 1,401,649.6 | ||||||||||||
ZONE(A) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 89.50 | m3 | 1 | 3 | 6480 | 82 | 7339 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 13819.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 13 | m3 | 1 | 5 | 1080 0 | 9800 | 127400 | 0 | 0 |
244
total direct cost =labor+material+equipment+s/c | 138200.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 89.5 | m3 | 1 | 2 | 2180 | 560 | 50120 | 0 | 50 | 4475 | ||
total direct cost =labor+material+equipment+s/c | 56775.0 | ||||||||||||
total = | 208794.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 94.50 | m3 | 1 | 4.00 | 8640 | 82 | 7749 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 16389.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 14 | m3 | 1 | 5 | 1080 0 | 9800 | 137200 | 0 | 0 |
245
total direct cost =labor+material+equipment+s/c | 148000.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 94.5 | m3 | 1 | 2 | 2180 | 560 | 52920 | 0 | 50 | 4725 | ||
total direct cost =labor+material+equipment+s/c | 59825.0 | ||||||||||||
total = | 224214.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 42.80 | m3 | 1 | 2.00 | 4320 | 82 | 3509.6 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7829.6 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 7 | m3 | 1 | 3 | 6480 | 9800 | 68600 | 0 | 0 |
246
total direct cost =labor+material+equipment+s/c | 75080.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 42.8 | m3 | 1 | 1 | 1090 | 560 | 23968 | 0 | 50 | 2140 | ||
total direct cost =labor+material+equipment+s/c | 27198.0 | ||||||||||||
total = | 110107.6 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 39.00 | m3 | 1 | 2.00 | 4320 | 82 | 3198 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7518.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 7 | m3 | 1 | 3 | 6480 | 9800 | 68600 | 0 | 0 |
247
total direct cost =labor+material+equipment+s/c | 75080.0 | ||||||||||||
PLACING | labor | material | S/ C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 39 | m3 | 1 | 1 | 1090 | 560 | 21840 | 0 | 50 | 1950 | ||
total direct cost =labor+material+equipment+s/c | 24880.0 | ||||||||||||
total = | 107478.0 | ||||||||||||
total column cost zone A = | 865,549.6 | ||||||||||||
ZONE(A) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 483.60 | m3 | 2 | 9.00 | 3888 0 | 95 | 45942 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 84822.0 |
248
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 51.64 | m3 | 2 | 6.00 | 2592 0 | 9800 | 506072 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 531992.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 483.60 | m3 | 2 | 2.00 | 6920 | 560 | 270816 | 0 | 50 | 24180 | ||
total direct cost =labor+material+equipment+s/c | 301916.0 | ||||||||||||
total = | 918730.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 510.00 | m3 | 2 | 9.00 | 3888 0 | 95 | 48450 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 87330.0 |
249
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 52.3 | m3 | 2 | 6.00 | 2592 0 | 9800 | 512540 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 538460.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 510.00 | m3 | 2 | 2.00 | 6920 | 560 | 285600 | 0 | 50 | 25500 | ||
total direct cost =labor+material+equipment+s/c | 318020.0 | ||||||||||||
total = | 943810.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 958.80 | M3 | 1 | 7 | 1050 | 30 | 28764 | 0 | 2640 | 18480 | ||
total direct cost =labor+material+equipment+s/c | 48294.0 |
250
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.00 | TON | 1 | 1 | 540 | 9800 | 9780.4 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10320.4 | ||||||||||||
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 318.90 | M3 | 1 | 4 | 2560 | 560 | 178584 | 0 | 50/M3 | 20745 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 201889.0 | ||||||||||||
total = | 260503.4 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 131.60 | m3 | 1 | 5.00 | 1080 0 | 95 | 12502 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23302.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment |
251
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 16.5 | m3 | 1 | 4.00 | 8640 | 9800 | 161700 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 170340.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 131.60 | m3 | 1 | 1.00 | 1730 | 560 | 73696 | 0 | 50 | 6580 | ||
total direct cost =labor+material+equipment+s/c | 82006.0 | ||||||||||||
total = | 275648.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 131.60 | m3 | 1 | 5.00 | 1080 0 | 95 | 12502 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23302.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment |
252
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 16.5 | m3 | 1 | 4 | 8640 | 9800 | 161700 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 170340.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 131.60 | m3 | 1 | 1 | 1730 | 560 | 73696 | 0 | 50 | 6580 | ||
total direct cost =labor+material+equipment+s/c | 82006.0 | ||||||||||||
total = | 275648.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone A | 3,398,115.4 | ||||||||||||
ZONE(A) _ BRICKS | |||||||||||||
Code | Work Type | Calculations |
253
labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | ||
540.00 | 3000.00 | 5307.00 | Brick | 1 | 2 | 1080 | 1.096 | 5816.472 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 6896.5 | |||||||||||
total = | 6896.5 | |||||||||||
TOTAL COST OF ZONE (A) | #REF! | |||||||||||
ZONE (B) | ||||||||||||
ZONE(B) _ pc footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C |
2160.00 | 30.00 | 170.90 | m3 | 2 | 3.00 | 1296 0 | 76 | 12988.4 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 25948.4 | |||||||||||
A2 | PLACING | labor | material | S/C | equipment |
254
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 170.9 | m3 | 1 | 2 | 3140 | 560 | 95704 | 0 | 50 | 8545 | ||
total direct cost =labor+material+equipment+s/c | 107389.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LEm3 | D.C | D.C | D.C | |||
150 | 150 | 295 | m3 | 2 | 1 | 300 | 30 | 8850 | 0 | 2640 | |||
total direct cost =labor+material+equipment+s/c | 11790.0 | ||||||||||||
total pc footing cost zone B = | 145,127.4 | ||||||||||||
ZONE(B) _ RC footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 259.06 | m3 | 2 | 5.00 | 2160 0 | 76 | 19688.56 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 41288.6 |
255
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 18.1 | Ton | 2 | 3 | 1296 0 | 9800 | 177380 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 190340.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 259.06 | m3 | 1 | 3 | 4710 | 560 | 145073.6 | 0 | 50 | 12953 | ||
total direct cost =labor+material+equipment+s/c | 162736.6 | ||||||||||||
ISOLATION | labor | material | S/ C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 428.1 | m2 | 2 | 4 | 1080 | 15 | 6421.5 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 7501.5 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LEm3 | D.C | D.C | D.C | |||
150 | 150 | 771 | m3 | 2 | 3 | 900 | 30 | 23130 | 0 | 7920 |
256
total direct cost =labor+material+equipment+s/c | 31950.0 | ||||||||||||
total Rc footing cost zone B = | 433,816.7 | ||||||||||||
ZONE(B) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 63.00 | m3 | 1 | 1.00 | 2160 | 88 | 5544 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7704.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 8.8 | m3 | 1 | 1 | 2160 | 9800 | 86240 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 88400.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 63.00 | m3 | 1 | 1 | 1090 | 560 | 35280.00 | 0 | 50 | 3150 |
257
total direct cost =labor+material+equipment+s/c | 39520.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 153 | M2 | 1 | 4 | 1080 | 60 | 9180 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10260.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 157.75 | M3 | 1 | 2 | 300 | 30 | 4732.5 | 0 | 2640 | 5280 | ||
total direct cost =labor+material+equipment+s/c | 10312.5 | ||||||||||||
total = | 156196.5 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 63.00 | m3 | 1 | 1.00 | 2160 | 88 | 5544 | 0 | 0 |
258
total direct cost =labor+material+equipment+s/c | 7704.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 8.8 | m3 | 1 | 1 | 2160 | 9800 | 86240 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 88400.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 63.00 | m3 | 1 | 1 | 1090 | 560 | 35280.00 | 0 | 50 | 3150 | ||
total direct cost =labor+material+equipment+s/c | 39520.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 153 | M2 | 1 | 4 | 1080 | 60 | 9180 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10260.0 | ||||||||||||
BACKFILLING | labor | material | S/ C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C |
259
150 | 150 | 157.75 | M3 | 1 | 2 | 300 | 30 | 4732.5 | 0 | 2640 | 5280 | ||
total direct cost =labor+material+equipment+s/c | 10312.5 | ||||||||||||
total = | 156196.5 | ||||||||||||
Total RW zone A | 312,393.00 | ||||||||||||
ZONE(B) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 87.00 | m3 | 1 | 3.00 | 6480 | 82 | 7134 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 13614.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 12 | m3 | 1 | 4 | 8640 | 9800 | 117600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 126240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
260
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 87 | m3 | 1 | 2 | 2180 | 560 | 48720 | 0 | 50 | 4350 | ||
total direct cost =labor+material+equipment+s/c | 55250.0 | ||||||||||||
total = | 195104.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 93.00 | m3 | 1 | 4.00 | 8640 | 82 | 7626 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 16266.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 14 | m3 | 1 | 5 | 1080 0 | 9800 | 137200 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 148000.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
261
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 93 | m3 | 1 | 2 | 2180 | 560 | 52080 | 0 | 50 | 4650 | ||
total direct cost =labor+material+equipment+s/c | 58910.0 | ||||||||||||
total = | 223176.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 37.00 | m3 | 1 | 2.00 | 4320 | 82 | 3034 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7354.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
262
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 37 | m3 | 1 | 1 | 1090 | 560 | 20720 | 0 | 50 | 1850 | ||
total direct cost =labor+material+equipment+s/c | 23660.0 | ||||||||||||
total = | 94134.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 36.00 | m3 | 1 | 2.00 | 4320 | 82 | 2952 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7272.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
263
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 36 | m3 | 1 | 1 | 1090 | 560 | 20160 | 0 | 50 | 1800 | ||
total direct cost =labor+material+equipment+s/c | 23050.0 | ||||||||||||
total = | 93442.0 | ||||||||||||
total column cost zone B = | 792,740.0 | ||||||||||||
ZONE(B) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 481.90 | m3 | 2 | 9.00 | 3888 0 | 95 | 45780.5 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 84660.5 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 51.7 | m3 | 2 | 6 | 2592 0 | 9800 | 506660 | 0 | 0 |
264
total direct cost =labor+material+equipment+s/c | 532580.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 481.90 | m3 | 2 | 2 | 6920 | 560 | 269864 | 0 | 50 | 24095 | ||
total direct cost =labor+material+equipment+s/c | 300879.0 | ||||||||||||
total = | 918119.5 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 497.00 | m3 | 2 | 9.00 | 3888 0 | 95 | 47215 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 86095.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 49.9 | m3 | 2 | 6 | 2592 0 | 9800 | 489020 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 514940.0 |
265
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 497.00 | m3 | 2 | 2 | 6920 | 560 | 278320 | 0 | 50 | 24850 | ||
total direct cost =labor+material+equipment+s/c | 310090.0 | ||||||||||||
total = | 911125.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 1011.90 | M3 | 1 | 7 | 1050 | 30 | 30357 | 0 | 2640 | 18480 | ||
total direct cost =labor+material+equipment+s/c | 49887.0 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.05 | TON | 1 | 1 | 540 | 9800 | 10250.8 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10790.8 |
266
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 337.30 | M3 | 1 | 4 | 2560 | 560 | 188888 | 0 | 50/M3 | 21665 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 213113.0 | ||||||||||||
total = | 273790.8 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 132.40 | m3 | 1 | 5.00 | 1080 0 | 95 | 12578 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23378.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 17 | m3 | 1 | 4 | 8640 | 9800 | 166600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 175240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
267
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 132.40 | m3 | 1 | 1 | 1730 | 560 | 74144 | 0 | 50 | 6620 | ||
total direct cost =labor+material+equipment+s/c | 82494.0 | ||||||||||||
total = | 281112.0 | ||||||||||||
REPETATIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 132.40 | m3 | 1 | 5.00 | 1080 0 | 95 | 12578 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23378.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 17 | m3 | 1 | 4 | 8640 | 9800 | 166600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 175240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
268
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 132.40 | m3 | 1 | 1 | 1730 | 560 | 74144 | 0 | 50 | 6620 | ||
total direct cost =labor+material+equipment+s/c | 82494.0 | ||||||||||||
total = | 281112.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone B | 3,399,963.3 | ||||||||||||
ZONE(B) _ BRICKS | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | |||
540.00 | 3000.00 | 5902.00 | Brick | 1 | 2 | 1080 | 1.096 | 6468.592 | 0 | 0 |
269
total direct cost =labor+material+equipment+s/c | 7548.6 | ||||||||||||
total = | 7548.592 | ||||||||||||
TOTAL COST OF ZONE (B) | 5,091,589.0 | ||||||||||||
ZONE (C) | |||||||||||||
ZONE(C) _ pc footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 285.90 | m3 | 2 | 5.00 | 2160 0 | 76 | 21728.4 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 43328.4 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 285.9 | m3 | 1 | 3 | 4710 | 560 | 160104 | 0 | 50 | 14295 |
270
total direct cost =labor+material+equipment+s/c | 179109.0 | |||||||||||
BACKFILLING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | DC | ||
150 | 150 | 269 | m3 | 2 | 1 | 300 | 30 | 8070 | 0 | 2640 | ||
total direct cost =labor+material+equipment+s/c | 11010.0 | |||||||||||
total pc footing cost zone C = | 233,447.4 | |||||||||||
ZONE(C) _ RC footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 396.00 | m3 | 3 | 5.00 | 3240 0 | 76 | 30096 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 62496.0 | |||||||||||
FIXING STEEL | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | ||
2160 | 3.2 | 29.82 | Ton | 2 | 5 | 9800 | 292236 | 0 | 0 |
271
2160 0 | |||||||||||||
total direct cost =labor+material+equipment+s/c | 313836.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 396 | m3 | 2 | 2 | 6280 | 560 | 221760 | 0 | 50 | 19800 | ||
total direct cost =labor+material+equipment+s/c | 247840.0 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 566.94 | m2 | 3 | 3 | 2430 | 15 | 8504.1 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 10934.1 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | DC | |||
150 | 150 | 659 | m3 | 2 | 3 | 900 | 30 | 19770 | 0 | 7920 | |||
total direct cost =labor+material+equipment+s/c | 28590.0 | ||||||||||||
total Rc footing cost zone C = | 663,696.1 |
272
ZONE(C) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 71.00 | m3 | 1 | 1.00 | 2160 | 88 | 6248 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 8408.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 10 | m3 | 1 | 1 | 2160 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 100160.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 71.00 | m3 | 1 | 1 | 1090 | 560 | 39760.00 | 0 | 50 | 3550 |
273
total direct cost =labor+material+equipment+s/c | 44400.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 202 | M2 | 1 | 6 | 1620 | 60 | 12120 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 13740.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 135.5 | M3 | 1 | 1 | 150 | 30 | 4065 | 0 | 2640 | 2640 | ||
total direct cost =labor+material+equipment+s/c | 6855.0 | ||||||||||||
total = | 173563.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 71.00 | m3 | 1 | 1.00 | 2160 | 88 | 6248 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 8408.0 |
274
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 10 | m3 | 1 | 1 | 2160 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 100160.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 71.00 | m3 | 1 | 1 | 1090 | 560 | 39760.00 | 0 | 50 | 3550 | ||
total direct cost =labor+material+equipment+s/c | 44400.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 202 | M2 | 1 | 6 | 1620 | 60 | 12120 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 13740.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 135.5 | M3 | 1 | 1 | 150 | 30 | 4065 | 0 | 2640 | 2640 | ||
total direct cost =labor+material+equipment+s/c | 6855.0 |
275
total = | 173563.0 | ||||||||||||
Total RW zone C | 347,126.0 | ||||||||||||
ZONE(C) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 120.00 | m3 | 2 | 2.00 | 8640 | 82 | 9840 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 18480.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 16 | m3 | 2 | 3 | 1296 0 | 9800 | 156800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 169760.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
276
1090 | 50 | 120 | m3 | 2 | 2 | 4360 | 560 | 67200 | 0 | 50 | 6000 | ||
total direct cost =labor+material+equipment+s/c | 77560.0 | ||||||||||||
total = | 265800.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 125.00 | m3 | 2 | 3.00 | 1296 0 | 82 | 10250 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23210.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 18 | m3 | 2 | 3 | 1296 0 | 9800 | 176400 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 189360.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
277
1090 | 50 | 125 | m3 | 2 | 2 | 4360 | 560 | 70000 | 0 | 50 | 6250 | ||
total direct cost =labor+material+equipment+s/c | 80610.0 | ||||||||||||
total = | 293180.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 59.00 | m3 | 1 | 2.00 | 4320 | 82 | 4838 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 9158.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 10 | m3 | 2 | 2 | 8640 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 106640.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
278
1090 | 50 | 59 | m3 | 1 | 2 | 2180 | 560 | 33040 | 0 | 50 | 2950 | ||
total direct cost =labor+material+equipment+s/c | 38170.0 | ||||||||||||
total = | 153968.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 72.00 | m3 | 1 | 3.00 | 6480 | 82 | 5904 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 12384.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 9 | m3 | 1 | 3 | 6480 | 9800 | 88200 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 94680.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
279
1090 | 50 | 72 | m3 | 1 | 2 | 2180 | 560 | 40320 | 0 | 50 | 3600 | ||
total direct cost =labor+material+equipment+s/c | 46100.0 | ||||||||||||
total = | 153164.0 | ||||||||||||
total column cost zone C = | 1,172,440.0 | ||||||||||||
ZONE(C) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 810.35 | m3 | 3 | 10.00 | 6480 0 | 95 | 76983.25 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 141783.3 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 90.3 | m3 | 3 | 7 | 4536 0 | 9800 | 884940 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 930300.0 |
280
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 810.35 | m3 | 2 | 3 | 1038 0 | 560 | 453796 | 0 | 50 | 40517. 5 | ||
total direct cost =labor+material+equipment+s/c | 504693.5 | ||||||||||||
total = | 1576776.8 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 507.00 | m3 | 3 | 6.00 | 3888 0 | 95 | 48165 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 87045.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 88.6 | m3 | 3 | 7 | 4536 0 | 9800 | 868280 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 913640.0 |
281
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 507.00 | m3 | 2 | 2 | 6920 | 560 | 283920 | 0 | 50 | 25350 | ||
total direct cost =labor+material+equipment+s/c | 316190.0 | ||||||||||||
total = | 1316875.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 1632.80 | M3 | 1 | 11 | 1650 | 30 | 48984 | 0 | 2640 | 29040 | ||
total direct cost =labor+material+equipment+s/c | 79674.0 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.69 | TON | 1 | 1 | 540 | 9800 | 16532.6 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 17072.6 |
282
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 544.25 | M3 | 1 | 6 | 3840 | 560 | 304780 | 0 | 50/M3 | 34412. 5 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 343032.5 | ||||||||||||
total = | 439779.1 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 194.60 | m3 | 1 | 7.00 | 1512 0 | 95 | 18487 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 33607.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 25.6 | m3 | 2 | 3 | 1296 0 | 9800 | 250880 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 263840.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
283
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 194.60 | m3 | 1 | 2 | 3460 | 560 | 108976 | 0 | 50 | 9730 | ||
total direct cost =labor+material+equipment+s/c | 122166.0 | ||||||||||||
total = | 419613.0 | ||||||||||||
REPETATIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 194.60 | m3 | 1 | 7.00 | 1512 0 | 95 | 18487 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 33607.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 25.6 | m3 | 1 | 6 | 1296 0 | 9800 | 250880 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 263840.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
284
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 194.60 | m3 | 1 | 2 | 3460 | 560 | 108976 | 0 | 50 | 9730 | ||
total direct cost =labor+material+equipment+s/c | 122166.0 | ||||||||||||
total = | 419613.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone C | 5,184,362.9 | ||||||||||||
ZONE(C) _ BRICKS | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | |||
540.00 | 3000.00 | 4916.00 | Brick | 1 | 2 | 1080 | 1.096 | 5387.936 | 0 | 0 |
285
total direct cost =labor+material+equipment+s/c | 6467.9 | ||||||||||||
total = | 6467.9 | ||||||||||||
TOTAL COST OF ZONE ( C) | 7,607,540.3 | ||||||||||||
ZONE (D) | |||||||||||||
ZONE(D) _ pc footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 262.70 | m3 | 2 | 5.00 | 2160 0 | 76 | 19965.2 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 41565.2 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 262.7 | m3 | 1 | 3 | 4710 | 560 | 147112 | 0 | 50 | 13135 | ||
total direct cost =labor+material+equipment+s/c | 164957.0 |
286
BACKFILLING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/m3 | D.C | D.C | DC | ||
150 | 150 | 301 | m3 | 2 | 2 | 600 | 30 | 9030 | 0 | 5280 | ||
total direct cost =labor+material+equipment+s/c | 14910.0 | |||||||||||
total pc footing cost zone D = | 221,432.2 | |||||||||||
ZONE(D) _ RC footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 468.13 | m3 | 2 | 8.00 | 3456 0 | 76 | 35577.88 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 70137.9 | |||||||||||
FIXING STEEL | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | ||
2160 | 3.2 | 26.57 | Ton | 2 | 5 | 9800 | 260386 | 0 | 0 |
287
2160 0 | |||||||||||||
total direct cost =labor+material+equipment+s/c | 281986.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 468.13 | m3 | 2 | 3 | 9420 | 560 | 262152.8 | 0 | 50 | 23406. 5 | ||
total direct cost =labor+material+equipment+s/c | 294979.3 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 708.74 | m2 | 3 | 4 | 3240 | 15 | 10631.1 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 13871.1 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/m3 | D.C | D.C | DC | |||
150 | 150 | 722 | m3 | 2 | 3 | 900 | 30 | 21660 | 0 | 7920 | |||
total direct cost =labor+material+equipment+s/c | 30480.0 | ||||||||||||
total Rc footing cost zone D = | 691,454.3 |
288
ZONE(D) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 57.00 | m3 | 1 | 1.00 | 2160 | 88 | 5016 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7176.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 27.5 | m3 | 1 | 3 | 6480 | 9800 | 269500 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 275980.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 57.00 | m3 | 1 | 1 | 1090 | 560 | 31920.00 | 0 | 50 | 2850 |
289
total direct cost =labor+material+equipment+s/c | 35860.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 162.3 | M2 | 1 | 5 | 1350 | 60 | 9738 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 11088.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 324.6 | M3 | 1 | 3 | 450 | 30 | 9738 | 0 | 2640 | 7920 | ||
total direct cost =labor+material+equipment+s/c | 18108.0 | ||||||||||||
total = | 348212.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 57.00 | m3 | 1 | 1.00 | 2160 | 88 | 5016 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7176.0 |
290
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 27.5 | m3 | 1 | 3 | 6480 | 9800 | 269500 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 275980.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 57.00 | m3 | 1 | 1 | 1090 | 560 | 31920.00 | 0 | 50 | 2850 | ||
total direct cost =labor+material+equipment+s/c | 35860.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 162.3 | M2 | 1 | 5 | 1350 | 60 | 9738 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 11088.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 324.6 | M3 | 1 | 3 | 450 | 30 | 9738 | 0 | 2640 | 7920 | ||
total direct cost =labor+material+equipment+s/c | 18108.0 |
291
total = | 348212.0 | ||||||||||||
Total RW zone D | 696,424.0 | ||||||||||||
ZONE(D) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 168.40 | m3 | 2 | 3.00 | 1296 0 | 82 | 13808.8 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 26768.8 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 21 | m3 | 2 | 4 | 1728 0 | 9800 | 205800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 223080.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 168.4 | m3 | 2 | 2 | 4360 | 560 | 94304 | 0 | 50 | 8420 |
292
total direct cost =labor+material+equipment+s/c | 107084.0 | ||||||||||||
total = | 356932.8 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 171.00 | m3 | 2 | 3.00 | 1296 0 | 82 | 14022 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 26982.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 22 | m3 | 2 | 4 | 1728 0 | 9800 | 215600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 232880.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 171 | m3 | 2 | 2 | 4360 | 560 | 95760 | 0 | 50 | 8550 |
293
total direct cost =labor+material+equipment+s/c | 108670.0 | ||||||||||||
total = | 368532.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 75.00 | m3 | 2 | 2.00 | 8640 | 82 | 6150 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 14790.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 13 | m3 | 2 | 3 | 1296 0 | 9800 | 127400 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 140360.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 75 | m3 | 2 | 1 | 2180 | 560 | 42000 | 0 | 50 | 3750 |
294
total direct cost =labor+material+equipment+s/c | 47930.0 | ||||||||||||
total = | 203080.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 69.00 | m3 | 2 | 2.00 | 8640 | 82 | 5658 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 14298.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 12 | m3 | 2 | 2 | 8640 | 9800 | 117600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 126240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 69 | m3 | 2 | 1 | 2180 | 560 | 38640 | 0 | 50 | 3450 |
295
total direct cost =labor+material+equipment+s/c | 44270.0 | ||||||||||||
total = | 184808.0 | ||||||||||||
total column cost zone D = | 1,482,968.8 | ||||||||||||
ZONE(D) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 389.45 | m3 | 2 | 7.00 | 3024 0 | 95 | 36997.75 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 67237.8 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 42.2 | m3 | 2 | 5 | 2160 0 | 9800 | 413560 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 435160.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
296
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 389.45 | m3 | 2 | 2 | 6920 | 560 | 218092 | 0 | 50 | 19472. 5 | ||
total direct cost =labor+material+equipment+s/c | 244484.5 | ||||||||||||
total = | 746882.3 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 395.10 | m3 | 2 | 7.00 | 3024 0 | 95 | 37534.5 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 67774.5 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 42.7 | m3 | 2 | 5 | 2160 0 | 9800 | 418460 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 440060.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
297
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 395.10 | m3 | 2 | 2 | 6920 | 560 | 221256 | 0 | 50 | 19755 | ||
total direct cost =labor+material+equipment+s/c | 247931.0 | ||||||||||||
total = | 755765.5 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 741.75 | M3 | 1 | 5 | 750 | 30 | 22252.5 | 0 | 2640 | 13200 | ||
total direct cost =labor+material+equipment+s/c | 36202.5 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 0.77 | TON | 1 | 1 | 540 | 9800 | 7511.7 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 8051.7 | ||||||||||||
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C |
298
640.00 | 100.00 | 247.25 | M3 | 1 | 3 | 1920 | 560 | 138460 | 0 | 50/M3 | 15962. 5 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 156342.5 | ||||||||||||
total = | 200596.7 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 199.00 | m3 | 1 | 7.00 | 1512 0 | 95 | 18905 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 34025.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 26.2 | m3 | 2 | 3 | 1296 0 | 9800 | 256760 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 269720.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 199.00 | m3 | 1 | 2 | 3460 | 560 | 111440 | 0 | 50 | 9950 |
299
total direct cost =labor+material+equipment+s/c | 124850.0 | ||||||||||||
total = | 428595.0 | ||||||||||||
REPETATIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 199.00 | m3 | 1 | 7.00 | 1512 0 | 95 | 18905 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 34025.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 26.2 | m3 | 1 | 6 | 1296 0 | 9800 | 256760 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 269720.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 199.00 | m3 | 1 | 2 | 3460 | 560 | 111440 | 0 | 50 | 9950 |
300
total direct cost =labor+material+equipment+s/c | 124850.0 | ||||||||||||
total = | 428595.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone D | 3,590,104.5 | ||||||||||||
ZONE(D) _ BRICKS | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | |||
540.00 | 3000.00 | 6307.00 | Brick | 1 | 3 | 1620 | 1.096 | 6912.472 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 8532.5 | ||||||||||||
total = | 8532.5 |
301
TOTAL COST OF ZONE (D) | 6,690,916.2 | ||||||||||||
ZONE (E) | |||||||||||||
ZONE(E) _ pc footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 230.60 | m3 | 2 | 4.00 | 1728 0 | 76 | 17525.6 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 34805.6 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 230.6 | m3 | 2 | 2 | 6280 | 560 | 129136 | 0 | 50 | 11530 | ||
total direct cost =labor+material+equipment+s/c | 146946.0 | ||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment |
302
BACKFILLING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
150.00 | 150.00 | 331.00 | m3 | 2 | 2.00 | 600 | 30 | 9930 | 0 | 5280 | ||
total direct cost =labor+material+equipment+s/c | 15810.0 | |||||||||||
total pc footing cost zone E = | 197,561.6 | |||||||||||
ZONE(E) _ RC footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 401.00 | m3 | 2 | 7.00 | 3024 0 | 76 | 30476 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 60716.0 | |||||||||||
FIXING STEEL | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | ||
2160 | 3.2 | 30.36 | Ton | 2 | 5 | 2160 0 | 9800 | 297528 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 319128.0 |
303
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 401 | m3 | 2 | 3 | 9420 | 560 | 224560 | 0 | 50 | 20050 | ||
total direct cost =labor+material+equipment+s/c | 254030.0 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 567.54 | m2 | 2 | 5 | 2700 | 15 | 8513.1 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 11213.1 | ||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
BACKFILLING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
150.00 | 150.00 | 862.00 | m3 | 2 | 3.00 | 900 | 30 | 25860 | 0 | 7920 | |||
total direct cost =labor+material+equipment+s/c | 34680.0 | ||||||||||||
total Rc footing cost zone E = | 679,767.1 |
304
ZONE(E) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 59.25 | m3 | 1 | 1.00 | 2160 | 88 | 5214 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7374.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 8.35 | m3 | 1 | 1 | 2160 | 9800 | 81830 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 83990.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 59.25 | m3 | 1 | 1 | 1090 | 560 | 33180.00 | 0 | 50 | 2962.5 |
305
total direct cost =labor+material+equipment+s/c | 37232.5 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 169.2 | M2 | 1 | 5 | 1350 | 60 | 10152 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 11502.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 338.44 | M3 | 1 | 3 | 450 | 30 | 10153.2 | 0 | 2640 | 7920 | ||
total direct cost =labor+material+equipment+s/c | 18523.2 | ||||||||||||
total = | 158621.7 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 59.25 | m3 | 1 | 1.00 | 2160 | 88 | 5214 | 0 | 0 |
306
total direct cost =labor+material+equipment+s/c | 7374.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 8.35 | m3 | 1 | 1 | 2160 | 9800 | 81830 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 83990.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 59.25 | m3 | 1 | 1 | 1090 | 560 | 33180.00 | 0 | 50 | 2962.5 | ||
total direct cost =labor+material+equipment+s/c | 37232.5 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 169.2 | M2 | 1 | 5 | 1350 | 60 | 10152 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 11502.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 338.44 | M3 | 1 | 3 | 450 | 30 | 10153.2 | 0 | 2640 | 7920 |
307
total direct cost =labor+material+equipment+s/c | 18523.2 | ||||||||||||
total = | 158621.7 | ||||||||||||
Total RW zone E | 317,243.4 | ||||||||||||
ZONE(E) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 120.00 | m3 | 2 | 2.00 | 8640 | 82 | 9840 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 18480.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 16 | m3 | 2 | 3 | 1296 0 | 9800 | 156800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 169760.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
308
1090 | 50 | 120 | m3 | 2 | 2 | 4360 | 560 | 67200 | 0 | 50 | 6000 | ||
total direct cost =labor+material+equipment+s/c | 77560.0 | ||||||||||||
total = | 265800.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 125.00 | m3 | 2 | 3.00 | 1296 0 | 82 | 10250 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23210.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 18 | m3 | 2 | 3 | 1296 0 | 9800 | 176400 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 189360.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
309
1090 | 50 | 125 | m3 | 2 | 2 | 4360 | 560 | 70000 | 0 | 50 | 6250 | ||
total direct cost =labor+material+equipment+s/c | 80610.0 | ||||||||||||
total = | 293180.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 59.00 | m3 | 1 | 2.00 | 4320 | 82 | 4838 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 9158.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 10 | m3 | 2 | 2 | 8640 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 106640.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
310
1090 | 50 | 59 | m3 | 1 | 2 | 2180 | 560 | 33040 | 0 | 50 | 2950 | ||
total direct cost =labor+material+equipment+s/c | 38170.0 | ||||||||||||
total = | 153968.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 36.00 | m3 | 1 | 2.00 | 4320 | 82 | 2952 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7272.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 9 | m3 | 2 | 2 | 8640 | 9800 | 88200 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 96840.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
311
1090 | 50 | 36 | m3 | 1 | 1 | 1090 | 560 | 20160 | 0 | 50 | 1800 | ||
total direct cost =labor+material+equipment+s/c | 23050.0 | ||||||||||||
total = | 127162.0 | ||||||||||||
total column cost zone E = | 1,094,434.0 | ||||||||||||
ZONE(E) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 810.35 | m3 | 3 | 10.00 | 6480 0 | 95 | 76983.25 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 141783.3 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 90.3 | m3 | 3 | 7 | 4536 0 | 9800 | 884940 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 930300.0 |
312
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 810.35 | m3 | 2 | 3 | 1038 0 | 560 | 453796 | 0 | 50 | 40517. 5 | ||
total direct cost =labor+material+equipment+s/c | 504693.5 | ||||||||||||
total = | 1576776.8 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 507.00 | m3 | 3 | 6.00 | 3888 0 | 95 | 48165 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 87045.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 88.6 | m3 | 3 | 7 | 4536 0 | 9800 | 868280 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 913640.0 |
313
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 507.00 | m3 | 2 | 2 | 6920 | 560 | 283920 | 0 | 50 | 25350 | ||
total direct cost =labor+material+equipment+s/c | 316190.0 | ||||||||||||
total = | 1316875.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 1632.80 | M3 | 1 | 11 | 1650 | 30 | 48984 | 0 | 2640 | 29040 | ||
total direct cost =labor+material+equipment+s/c | 79674.0 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.69 | TON | 1 | 1 | 540 | 9800 | 16532.6 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 17072.6 |
314
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 544.25 | M3 | 1 | 6 | 3840 | 560 | 304780 | 0 | 50/M3 | 34412. 5 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 343032.5 | ||||||||||||
total = | 439779.1 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 194.60 | m3 | 2 | 4.00 | 1728 0 | 95 | 18487 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 35767.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 25.6 | m3 | 2 | 3 | 1296 0 | 9800 | 250880 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 263840.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
315
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 194.60 | m3 | 2 | 1 | 3460 | 560 | 108976 | 0 | 50 | 9730 | ||
total direct cost =labor+material+equipment+s/c | 122166.0 | ||||||||||||
total = | 421773.0 | ||||||||||||
REPETATIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 194.60 | m3 | 2 | 4.00 | 1728 0 | 95 | 18487 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 35767.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 25.6 | m3 | 2 | 3 | 1296 0 | 9800 | 250880 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 263840.0 | ||||||||||||
PLACING | labor | material | S/C | equipment |
316
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 194.60 | m3 | 2 | 1 | 3460 | 560 | 108976 | 0 | 50 | 9730 | ||
total direct cost =labor+material+equipment+s/c | 122166.0 | ||||||||||||
total = | 421773.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone E | 5,193,002.9 | ||||||||||||
ZONE(E) _ BRICKS | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | |||
540.00 | 3000.00 | 4916.00 | Brick | 1 | 2 | 1080 | 1.096 | 5387.936 | 0 | 0 |
317
total direct cost =labor+material+equipment+s/c | 6467.9 | ||||||||||||
total = | 6467.9 | ||||||||||||
TOTAL COST OF ZONE (E) | 7,488,476.9 | ||||||||||||
ZONE (F) | |||||||||||||
ZONE(F) _ pc footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 164.00 | m3 | 2 | 3.00 | 1296 0 | 76 | 12464 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 25424.0 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 164 | m3 | 1 | 2 | 3140 | 560 | 91840 | 0 | 50 | 8200 | ||
total direct cost =labor+material+equipment+s/c | 103180.0 |
318
BACKFILLING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LEm3 | D.C | D.C | D.C | ||
150 | 150 | 289 | m3 | 2 | 1 | 300 | 30 | 8670 | 0 | 2640 | ||
total direct cost =labor+material+equipment+s/c | 11610.0 | |||||||||||
total pc footing cost zone F = | 140,214.0 | |||||||||||
ZONE(F) _ RC footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 249.67 | m3 | 2 | 5.00 | 2160 0 | 76 | 18974.92 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 40574.9 | |||||||||||
FIXING STEEL | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | ||
2160 | 3.2 | 15.94 | Ton | 2 | 3 | 1296 0 | 9800 | 156212 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 169172.0 |
319
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 249.67 | m3 | 1 | 3 | 4710 | 560 | 139815.2 | 0 | 50 | 12483. 5 | ||
total direct cost =labor+material+equipment+s/c | 157008.7 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 435.16 | m2 | 2 | 4 | 2160 | 15 | 6527.4 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 8687.4 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LEm3 | D.C | D.C | D.C | |||
150 | 150 | 693 | m3 | 2 | 3 | 900 | 30 | 20790 | 0 | 7920 | |||
total direct cost =labor+material+equipment+s/c | 29610.0 | ||||||||||||
total Rc footing cost zone F = | 405,053.0 | ||||||||||||
ZONE(F) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT |
320
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 113.50 | m3 | 2 | 1.00 | 4320 | 88 | 9988 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 14308.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 15.9 | m3 | 2 | 1 | 4320 | 9800 | 155820 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 160140.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 113.50 | m3 | 1 | 1 | 1090 | 560 | 63560.00 | 0 | 50 | 5675 | ||
total direct cost =labor+material+equipment+s/c | 70325.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C |
321
270 | 40 | 324.1 | M2 | 2 | 5 | 2700 | 60 | 19446 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 22146.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 648.2 | M3 | 1 | 5 | 750 | 30 | 19446 | 0 | 2640 | 13200 | ||
total direct cost =labor+material+equipment+s/c | 33396.0 | ||||||||||||
total = | 300315.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 113.50 | m3 | 2 | 1.00 | 4320 | 88 | 9988 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 14308.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C |
322
2160 | 10 | 15.9 | m3 | 2 | 1 | 4320 | 9800 | 155820 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 160140.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 113.50 | m3 | 1 | 1 | 1090 | 560 | 63560.00 | 0 | 50 | 5675 | ||
total direct cost =labor+material+equipment+s/c | 70325.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 324.1 | M2 | 2 | 5 | 2700 | 60 | 19446 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 22146.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 648.2 | M3 | 1 | 5 | 750 | 30 | 19446 | 0 | 2640 | 13200 | ||
total direct cost =labor+material+equipment+s/c | 33396.0 | ||||||||||||
total = | 300315.0 | ||||||||||||
Total RW zone F | 600,630.0 |
323
ZONE(F) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 86.00 | m3 | 1 | 3.00 | 6480 | 82 | 7052 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 13532.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 18 | m3 | 1 | 6 | 1296 0 | 9800 | 176400 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 189360.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 86 | m3 | 1 | 2 | 2180 | 560 | 48160 | 0 | 50 | 4300 |
324
total direct cost =labor+material+equipment+s/c | 54640.0 | ||||||||||||
total = | 257532.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 66.00 | m3 | 1 | 3.00 | 6480 | 82 | 5412 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 11892.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 10 | m3 | 1 | 4 | 8640 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 106640.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 66 | m3 | 1 | 2 | 2180 | 560 | 36960 | 0 | 50 | 3300 | ||
total direct cost =labor+material+equipment+s/c | 42440.0 |
325
total = | 160972.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 29.67 | m3 | 1 | 1.00 | 2160 | 82 | 2432.94 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 4592.9 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 9 | m3 | 1 | 3 | 6480 | 9800 | 88200 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 94680.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 29.67 | m3 | 1 | 1 | 1090 | 560 | 16615.2 | 0 | 50 | 1483.5 | ||
total direct cost =labor+material+equipment+s/c | 19188.7 | ||||||||||||
total = | 118461.6 |
326
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 27.12 | m3 | 1 | 1.00 | 2160 | 82 | 2223.84 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 4383.8 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 10 | m3 | 1 | 4 | 8640 | 9800 | 98000 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 106640.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 27.12 | m3 | 1 | 1 | 1090 | 560 | 15187.2 | 0 | 50 | 1356 | ||
total direct cost =labor+material+equipment+s/c | 17633.2 | ||||||||||||
total = | 128657.0 | ||||||||||||
total column cost zone F = | 922,936.8 |
327
ZONE(F) _ SLABS | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 481.90 | m3 | 2 | 9.00 | 3888 0 | 95 | 45780.5 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 84660.5 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 51.7 | m3 | 2 | 6 | 2592 0 | 9800 | 506660 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 532580.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 481.90 | m3 | 2 | 2 | 6920 | 560 | 269864 | 0 | 50 | 24095 |
328
total direct cost =labor+material+equipment+s/c | 300879.0 | ||||||||||||
total = | 918119.5 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 497.00 | m3 | 2 | 9.00 | 3888 0 | 95 | 47215 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 86095.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 49.9 | m3 | 2 | 6 | 2592 0 | 9800 | 489020 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 514940.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 497.00 | m3 | 2 | 2 | 6920 | 560 | 278320 | 0 | 50 | 24850 | ||
total direct cost =labor+material+equipment+s/c | 310090.0 |
329
total = | 911125.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 1011.90 | M3 | 1 | 7 | 1050 | 30 | 30357 | 0 | 2640 | 18480 | ||
total direct cost =labor+material+equipment+s/c | 49887.0 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.05 | TON | 1 | 1 | 540 | 9800 | 10250.8 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10790.8 | ||||||||||||
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 337.30 | M3 | 1 | 4 | 2560 | 560 | 188888 | 0 | 50/M3 | 21665 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 213113.0 | ||||||||||||
total = | 273790.8 | ||||||||||||
GROUND FLOOR |
330
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 132.40 | m3 | 1 | 5.00 | 1080 0 | 95 | 12578 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23378.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 17 | m3 | 1 | 4 | 8640 | 9800 | 166600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 175240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 132.40 | m3 | 1 | 1 | 1730 | 560 | 74144 | 0 | 50 | 6620 | ||
total direct cost =labor+material+equipment+s/c | 82494.0 | ||||||||||||
total = | 281112.0 | ||||||||||||
REPETATIVE FLOOR |
331
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 132.40 | m3 | 1 | 5.00 | 1080 0 | 95 | 12578 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23378.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 17 | m3 | 1 | 4 | 8640 | 9800 | 166600 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 175240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 132.40 | m3 | 1 | 1 | 1730 | 560 | 74144 | 0 | 50 | 6620 | ||
total direct cost =labor+material+equipment+s/c | 82494.0 | ||||||||||||
total = | 281112.0 | ||||||||||||
labor | material | S/C | equipment |
332
Elec. Empty Conduits | labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | |
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 172,480.0 | ||||||||||||
total slabs cost zone F | 3,399,963.3 | ||||||||||||
ZONE(F) _ BRICKS | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | |||
540.00 | 3000.00 | 5902.00 | Brick | 1 | 2 | 1080 | 1.096 | 6468.592 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7548.6 | ||||||||||||
total = | 7548.6 | ||||||||||||
TOTAL COST OF ZONE (F) | 5,476,345.7 | ||||||||||||
ZONE (G) | |||||||||||||
ZONE(G) _ pc footing | |||||||||||||
333
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | |
2160.00 | 30.00 | 145.10 | m3 | 2 | 3.00 | 1296 0 | 76 | 11027.6 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23987.6 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 145.1 | m3 | 1 | 2 | 3140 | 560 | 81256 | 0 | 50 | 7255 | ||
total direct cost =labor+material+equipment+s/c | 91651.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | DC | |||
150 | 150 | 310 | m3 | 2 | 2 | 600 | 30 | 9300 | 0 | 5280 | |||
total direct cost =labor+material+equipment+s/c | 15180.0 | ||||||||||||
total pc footing cost zone G = | 130,818.6 |
334
ZONE(G) _ RC footing | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 297.33 | m3 | 2 | 5.00 | 2160 0 | 76 | 22597.08 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 44197.1 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 20.15 | Ton | 2 | 4 | 1728 0 | 9800 | 197470 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 214750.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 297.33 | m3 | 2 | 2 | 6280 | 560 | 166504.8 | 0 | 50 | 14866. 5 |
335
total direct cost =labor+material+equipment+s/c | 187651.3 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 511.92 | m2 | 2 | 4 | 2160 | 15 | 7678.8 | 0 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 9838.8 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | DC | |||
150 | 150 | 1051 | m3 | 2 | 4 | 1200 | 30 | 31530 | 0 | 10560 | |||
total direct cost =labor+material+equipment+s/c | 43290.0 | ||||||||||||
total Rc footing cost zone G = | 499,727.2 | ||||||||||||
ZONE(G) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C |
336
2160.00 | 80.00 | 202.40 | m3 | 1 | 3.00 | 6480 | 88 | 17811.2 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 24291.2 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 28.3 | m3 | 1 | 3 | 6480 | 9800 | 277340 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 283820.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 202.40 | m3 | 1 | 2 | 2180 | 560 | 113344.0 0 | 0 | 50 | 10120 | ||
total direct cost =labor+material+equipment+s/c | 125644.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 394.25 | M2 | 1 | 10 | 2700 | 60 | 23655 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 26355.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment |
337
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 788.5 | M3 | 1 | 6 | 900 | 30 | 23655 | 0 | 2640 | 15840 | ||
total direct cost =labor+material+equipment+s/c | 40395.0 | ||||||||||||
total = | 500505.2 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 202.40 | m3 | 1 | 3.00 | 6480 | 88 | 17811.2 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 24291.2 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 28.3 | m3 | 1 | 3 | 6480 | 9800 | 277340 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 283820.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C |
338
1090 | 150 | 202.40 | m3 | 1 | 2 | 2180 | 560 | 113344.0 0 | 0 | 50 | 10120 | ||
total direct cost =labor+material+equipment+s/c | 125644.0 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 394.25 | M2 | 1 | 10 | 2700 | 60 | 23655 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 26355.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 788.5 | M3 | 1 | 6 | 900 | 30 | 23655 | 0 | 2640 | 15840 | ||
total direct cost =labor+material+equipment+s/c | 40395.0 | ||||||||||||
total = | 500505.2 | ||||||||||||
Total RW zone G | 1,001,010.4 | ||||||||||||
ZONE(G) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations |
339
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 74.50 | m3 | 1 | 3.00 | 6480 | 82 | 6109 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 12589.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 74.5 | m3 | 1 | 2 | 2180 | 560 | 41720 | 0 | 50 | 3725 | ||
total direct cost =labor+material+equipment+s/c | 47625.0 | ||||||||||||
total = | 123334.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations |
340
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 33.00 | m3 | 1 | 2.00 | 4320 | 82 | 2706 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 7026.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 33 | m3 | 1 | 1 | 1090 | 560 | 18480 | 0 | 50 | 1650 | ||
total direct cost =labor+material+equipment+s/c | 21220.0 | ||||||||||||
total = | 91366.0 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations |
341
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 30.00 | m3 | 1 | 1.00 | 2160 | 82 | 2460 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 4620.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 30 | m3 | 1 | 1 | 1090 | 560 | 16800 | 0 | 50 | 1500 | ||
total direct cost =labor+material+equipment+s/c | 19390.0 | ||||||||||||
total = | 87130.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations |
342
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 30.00 | m3 | 1 | 1.00 | 2160 | 82 | 2460 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 4620.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 6 | m3 | 1 | 2 | 4320 | 9800 | 58800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 63120.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 30 | m3 | 1 | 1 | 1090 | 560 | 16800 | 0 | 50 | 1500 | ||
total direct cost =labor+material+equipment+s/c | 19390.0 | ||||||||||||
total = | 87130.0 | ||||||||||||
total column cost zone G = | 563,220.0 | ||||||||||||
ZONE(G) _ SLABS | |||||||||||||
LOWER BASEMENT |
343
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 483.60 | m3 | 2 | 9.00 | 3888 0 | 95 | 45942 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 84822.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 51.64 | m3 | 2 | 6 | 2592 0 | 9800 | 506072 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 531992.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 483.60 | m3 | 2 | 2 | 6920 | 560 | 270816 | 0 | 50 | 24180 | ||
total direct cost =labor+material+equipment+s/c | 301916.0 | ||||||||||||
total = | 918730.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations |
344
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 510.00 | m3 | 2 | 9.00 | 3888 0 | 95 | 48450 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 87330.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 52.3 | m3 | 2 | 6 | 2592 0 | 9800 | 512540 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 538460.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 510.00 | m3 | 2 | 2 | 6920 | 560 | 285600 | 0 | 50 | 25500 | ||
total direct cost =labor+material+equipment+s/c | 318020.0 | ||||||||||||
total = | 943810.0 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations |
345
labor | material | S/C | equipment | ||||||||||
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 956.80 | M3 | 1 | 7 | 1050 | 30 | 28704 | 0 | 2640 | 18480 | ||
total direct cost =labor+material+equipment+s/c | 48234.0 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 0.99 | TON | 1 | 1 | 540 | 9800 | 9682.4 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10222.4 | ||||||||||||
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 318.90 | M3 | 1 | 4 | 2560 | 560 | 178584 | 0 | 50/M3 | 20745 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 201889.0 | ||||||||||||
total = | 260345.4 | ||||||||||||
GROUND FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C |
346
2160.00 | 30.00 | 131.60 | m3 | 1 | 5.00 | 1080 0 | 95 | 12502 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23302.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 16.5 | m3 | 1 | 4 | 8640 | 9800 | 161700 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 170340.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 131.60 | m3 | 1 | 1 | 1730 | 560 | 73696 | 0 | 50 | 6580 | ||
total direct cost =labor+material+equipment+s/c | 82006.0 | ||||||||||||
total = | 275648.0 | ||||||||||||
REPETITIVE FLOOR | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C |
347
2160.00 | 30.00 | 131.60 | m3 | 1 | 5.00 | 1080 0 | 95 | 12502 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 23302.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 16.5 | m3 | 1 | 4 | 8640 | 9800 | 161700 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 170340.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 131.60 | m3 | 1 | 1 | 1730 | 560 | 73696 | 0 | 50 | 6580 | ||
total direct cost =labor+material+equipment+s/c | 82006.0 | ||||||||||||
total = | 275648.0 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 172480 | 0 | 0 |
348
total direct cost =labor+material+equipment+s/c | 172,480.0 | |||||||||||
total slabs cost zone G | 3,397,957.4 | |||||||||||
ZONE(G) _ BRICKS | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | ||
540.00 | 3000.00 | 1710.00 | Brick | 1 | 1 | 540 | 1.096 | 1874.16 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 2414.2 | |||||||||||
total = | 2414.2 | |||||||||||
TOTAL COST OF ZONE (G) | 5,595,147.7 | |||||||||||
ZONE (H) | ||||||||||||
ZONE(H) _ pc footing | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
A1 | SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C |
349
2160.00 | 30.00 | 165.90 | m3 | 2 | 3.00 | 1296 0 | 76 | 12608.4 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 25568.4 | ||||||||||||
A2 | PLACING | labor | material | S/C | equipment | ||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 165.9 | m3 | 1 | 2 | 3140 | 560 | 92904 | 0 | 50 | 8295 | ||
total direct cost =labor+material+equipment+s/c | 104339.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/m3 | D.C | D.C | DC | |||
150 | 150 | 361 | m3 | 2 | 2 | 600 | 30 | 10830 | 0 | 5280 | |||
total direct cost =labor+material+equipment+s/c | 16710.0 | ||||||||||||
total pc footing cost zone H = | 146,617.4 | ||||||||||||
ZONE(H) _ RC footing | |||||||||||||
Code | Work Type | Calculations |
350
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 421.74 | m3 | 2 | 8.00 | 3456 0 | 76 | 32052.24 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 66612.2 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 15.09 | Ton | 2 | 3 | 1296 0 | 9800 | 147882 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 160842.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1570 | 100 | 421.74 | m3 | 2 | 3 | 9420 | 560 | 236174.4 | 0 | 50 | 21087 | ||
total direct cost =labor+material+equipment+s/c | 266681.4 | ||||||||||||
ISOLATION | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | pump cost/m3 | D.C | ||
270 | 70 | 590.74 | m2 | 2 | 5 | 2700 | 15 | 8861.1 | 0 | 0 | 0 |
351
total direct cost =labor+material+equipment+s/c | 11561.1 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/m3 | D.C | D.C | DC | |||
150 | 150 | 997 | m3 | 2 | 4 | 1200 | 30 | 29910 | 0 | 10560 | |||
total direct cost =labor+material+equipment+s/c | 41670.0 | ||||||||||||
total Rc footing cost zone H = | 547,366.7 | ||||||||||||
ZONE(H) _ RETAINING WALL | |||||||||||||
LOWER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 129.25 | m3 | 1 | 2.00 | 4320 | 88 | 11374 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 15694.0 |
352
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 15.4 | m3 | 1 | 2 | 4320 | 9800 | 150920 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 155240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 129.25 | m3 | 1 | 1 | 1090 | 560 | 72380.00 | 0 | 50 | 6462.5 | ||
total direct cost =labor+material+equipment+s/c | 79932.5 | ||||||||||||
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 369.35 | M2 | 1 | 10 | 2700 | 60 | 22161 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 24861.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 738.7 | M3 | 1 | 5 | 750 | 30 | 22161 | 0 | 2640 | 13200 | ||
total direct cost =labor+material+equipment+s/c | 36111.0 |
353
total = | 311838.5 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 80.00 | 129.25 | m3 | 1 | 2.00 | 4320 | 88 | 11374 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 15694.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 10 | 15.4 | m3 | 1 | 2 | 4320 | 9800 | 150920 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 155240.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 150 | 129.25 | m3 | 1 | 1 | 1090 | 560 | 72380.00 | 0 | 50 | 6462.5 | ||
total direct cost =labor+material+equipment+s/c | 79932.5 |
354
Membrane | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M2 | D.C | D.C | D.C | |||
270 | 40 | 369.35 | M2 | 1 | 10 | 2700 | 60 | 22161 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 24861.0 | ||||||||||||
BACKFILLING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/M3 | D.C | ||
150 | 150 | 738.7 | M3 | 1 | 5 | 750 | 30 | 22161 | 0 | 2640 | 13200 | ||
total direct cost =labor+material+equipment+s/c | 36111.0 | ||||||||||||
total = | 311838.5 | ||||||||||||
Total RW zone H | 623,677.0 | ||||||||||||
ZONE(H) _ COLUMN | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 70.00 | m3 | 1 | 3.00 | 6480 | 82 | 5740 | 0 | 0 |
355
total direct cost =labor+material+equipment+s/c | 12220.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 11 | m3 | 1 | 4 | 8640 | 9800 | 107800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 116440.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 70 | m3 | 1 | 2 | 2180 | 560 | 39200 | 0 | 50 | 3500 | ||
total direct cost =labor+material+equipment+s/c | 44880.0 | ||||||||||||
total = | 173540.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment | ||||||||||
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 70.00 | m3 | 1 | 3.00 | 6480 | 82 | 5740 | 0 | 0 |
356
total direct cost =labor+material+equipment+s/c | 12220.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 3.2 | 11 | m3 | 1 | 4 | 8640 | 9800 | 107800 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 116440.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1090 | 50 | 70 | m3 | 1 | 2 | 2180 | 560 | 39200 | 0 | 50 | 3500 | ||
total direct cost =labor+material+equipment+s/c | 44880.0 | ||||||||||||
total = | 173540.0 | ||||||||||||
total column cost zone H = | 347,080.0 | ||||||||||||
ZONE(H) _SLAB | |||||||||||||
LOWER BASEMENT | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment |
357
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 490.60 | m3 | 2 | 9.00 | 3888 0 | 95 | 46607 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 85487.0 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 50.8 | m3 | 2 | 6 | 2592 0 | 9800 | 497840 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 523760.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 490.60 | m3 | 2 | 2 | 6920 | 560 | 274736 | 0 | 50 | 24530 | ||
total direct cost =labor+material+equipment+s/c | 306186.0 | ||||||||||||
total = | 915433.0 | ||||||||||||
UPPER BASEMENT | |||||||||||||
Work Type | Calculations | ||||||||||||
labor | material | S/C | equipment |
358
SHUTTERING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
2160.00 | 30.00 | 511.90 | m3 | 2 | 9.00 | 3888 0 | 95 | 48630.5 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 87510.5 | ||||||||||||
FIXING STEEL | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/ton | D.C | D.C | D.C | |||
2160 | 4.5 | 50.8 | m3 | 2 | 6 | 2592 0 | 9800 | 497840 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 523760.0 | ||||||||||||
PLACING | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
1730 | 150 | 511.90 | m3 | 2 | 2 | 6920 | 560 | 286664 | 0 | 50 | 25595 | ||
total direct cost =labor+material+equipment+s/c | 319179.0 | ||||||||||||
total = | 930449.5 | ||||||||||||
SOG | |||||||||||||
Code | Work Type | Calculations | |||||||||||
labor | material | S/C | equipment |
359
FILLING TO SOG | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE/day | D.C | |
150.00 | 150.00 | 983.25 | M3 | 1 | 7 | 1050 | 30 | 29497.5 | 0 | 2640 | 18480 | ||
total direct cost =labor+material+equipment+s/c | 49027.5 | ||||||||||||
STEEL FIXING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | D.C | ||
540.00 | 2.00 | 1.02 | TON | 1 | 1 | 540 | 9800 | 9956.8 | 0 | 0 | |||
total direct cost =labor+material+equipment+s/c | 10496.8 | ||||||||||||
PLACING | labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | LE | D.C | |
640.00 | 100.00 | 327.75 | M3 | 1 | 4 | 2560 | 560 | 183540 | 0 | 50/M3 | 21187. 5 | ||
1200/da y | |||||||||||||
total direct cost =labor+material+equipment+s/c | 207287.5 | ||||||||||||
total = | 266811.8 | ||||||||||||
Elec. Empty Conduits | labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit e | no.of crew | duratio n | D.C | LE/M3 | D.C | D.C | pump cost/m3 | D.C | ||
0 | 0 | 0.00 | 0 | 0 | 0 | 0 | 0.00 | 73920 | 0 | 0 |
360
total direct cost =labor+material+equipment+s/c | 73,920.0 | |||||||||||
total slabs cost zone H | 2,186,614.3 | |||||||||||
ZONE(H) _ BRICKS | ||||||||||||
Code | Work Type | Calculations | ||||||||||
labor | material | S/C | equipment | |||||||||
labor crew cost/day | pro.rat e | quantit y | unit | no.of crew | duratio n | D.C | LE/bric k | D.C | D.C | D.C | ||
540.00 | 3000.00 | 7062.00 | Brick | 1 | 3 | 1620 | 1.096 | 7739.952 | 0 | 0 | ||
total direct cost =labor+material+equipment+s/c | 9360.0 | |||||||||||
total = | 9360.0 | |||||||||||
TOTAL COST OF ZONE (H) | 3,860,715.4 |
•
6.5. TOTAL DIRECT COST:
6.5.1. Direct Cost of working items:
T.D.C | T.Q | cost/unit | |
PC footing | 1,394,607.5 | 1626.25 | 857.6 |
RC footing | 4,459,154.3 | 2789.38 | 1,598.6 |
RWs | 5,300,153.4 | 1924 | 2,754.8 |
Columns | 7,241,369.2 | 2852.73 | 2,538.4 |
Slabs | 29,750,083.9 | 12831.55 | 2,318.5 |
Bricks | 55,236.1 | 36715.00 | 1.5 |
Total | 48,200,604.3 | 22,023.9 |
6.5.2. Direct cost of resource:
LABOR | MATERIAL | S/C | EQUIPMENT | Total | |
COST | 3,562,730 | 41,602,604 | 1,281,280.0 | 1,753,991 | 48,200,604 |
% | 7.4% | 86.3% | 2.7% | 3.6% | 100.0% |