Estimation and Tendering Sample for a Building

Estimation and Tendering Sample for a Building

CHAPTER: 6. ESTIMATING& TENDRING

Chapter: 6. estimating& tendring ………………………………………………………………………………..220

.6.1 Introduction ………………………………………………………………………………………………………221

6.2. Methods of estimating: ……………………………………………………………………………………….222

6.2.1. Space method ………………………………………………………………………………………………222

6.2.2. Unit Method ………………………………………………………………………………………………..222

6.2.3. Element Method …………………………………………………………………………………………..223

6.2.4. Spot Method ………………………………………………………………………………………………..223

6.2.5. Detailed Method (Case Study)…………………………………………………………………………223

6.2.6. Operational Method: …………………………………………………………………………………….224

6.2.7. General WBS ………………………………………………………………………………………………..224

6.3. EXAMPLE …………………………………………………………………………………………………………..224

6.3.1. COLUMN WORKS ………………………………………………………………………………………….224

.6.3.2 SLABS WORKS ………………………………………………………………………………………………228

6.3.3. RETAINING WALL WORKS……………………………………………………………………………….231

6.4. Sheet of cost estimate: ………………………………………………………………………………………..238

.6.5 total direct cost: …………………………………………………………………………………………………362

6.5.1. Direct Cost of working items: ………………………………………………………………………….362

6.5.2. Direct cost of resource: ………………………………………………………………………………….363

6. Estimating &Tendering

6.1. INTRODUCTION

•       Estimating is considered an approximate way to predict the costs of the project. By the way, tender study is considered one of the most important tasks in construction industry that enables the contractor from success through the profit that the contractor estimates and does is best to increase it though, the success of any company is measured by how much contracts can it take especially when the competition between  companies  is strong.  So, to  measure how the management department is successful we can use some indicators:

•       Number  of  tenders  can  be  taken  divided  by number of tenders that are being studied.

•       The value of tenders can be taken divided by the value of tenders that are being studied.

•       The difference between studied tender and the other one that can be obtained and, the next one respectively attributed to the total price.

6.2. METHODS OF ESTIMATING:

6.2.1. Space method

•       Space method is away to estimate the cost of a structure by using the square meter cost in a similar structure.

6.2.2. Unit Method

•       Unit  method  is  away  to  estimate  the  cost  of structure by using the unit cost of similar structure

•       The cost of the whole structure is distributed to the units used in that structure like (Garage- Cars), (Hospital-Families) .

6.2.3. Element Method

•       Element method is away to estimate accost of a structure by the cost of the structure elements like foundations, skeleton, decoration, etc.

6.2.4. Spot Method

•       Spot   method   is   a   theoretical   method   to determine  the cost of the structure  using  the experience

6.2.5. Detailed Method (Case Study)

•       Estimating the items cost using predicted prices and quantities.

•     There are two types:

•     Unit rate method (case study)

•       Items    cost    estimation    is    depending     on production rate and a non- stop work.

•     The  cost  elements  are  (Labors  –  Equipment  –

Material –Sub Contractor)

6.2.6. Operational Method:

•       Items   cost   estimation   is   depending   on   the construction  duration  and  assuming  that  the item will be constructed as planned exactly so, the actual duration of the remaining in the site will be calculated

6.2.7. General WBS

•       The WBS is a deliverable –oriented break down of components of the project. It helps the project manager and the project team identify the components requiring specific people, equipment,   and   materials.   the   WBS   is   the primary input to resource planning.

6.3. EXAMPLE

6.3.1. COLUMN WORKS

FOR LOWER BASEMENT: (SECOND BASEMENT)

1. SHUTTERING WORKS:

a) FOR LABOR:

LABOR CREW
 NOALL-IN RATE LE/DAY
راجن12150
باشخ3120

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=12*150+3*120=2160 LE/DAY

• Production rate for column=30 m3/day

• Quantity for column=94.5 m3

• Duration=quantity/production rate*no. of crew

=94.5/30=4 days

• Labor cost=duration*daily labor cost

=4*2160=8640 LE

b) FOR MATRIAL:

TYPEQUANTITY (M3)PRICE (LE/M3)PERCENT OF DEPRECIATION
SHEATHING18.755000%20
YOKS3.8255000%20
BRACING2.765000%20
SHORE11.045000%2.5
تادناربلا2.765000%20
تاطحلا5.525000%20
تاشرفلا14.24513285000%2.5

• Cost of sheathing= quantity*price*percent of depreciation

=18.75*5650*.067= 5,293.84 LE

• Cost of yoks=3.825*5650*.02= 510.000 LE

• Cost of bracing=2.76*5650*.02= 276.00  LE

• Cost of shore=11.04*5500*.02= 138.00 LE

• Cost of تادنربلا= 2.76*5650*.02= 138.00 LE

• Cost of تاطحلا= 5.52*5650*.02= 276.00 LE

• Cost of تاشرفلا= 14.3*5000*.02= 712.26 LE

• Total cost of wood= 7,749.00 LE

c)  FOR EQUIPMENT:  there is no equipment d) FOR S/C:  there is no s/c

Shuttering total cost= 16,389 LE

2. STEEL FIXING:

a) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
دادح12150
دعاسم3120

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=12*150+3*120=2160 LE/DAY

• Production rate for column=3.2 ton/day

• Quantity for column= 14 ton

• Duration=quantity/production rate*no. of crew

=14/3.2=5 days

• Labor cost=duration*daily labor cost

=5*2160=10,800.00 LE

b) MATRIAL COST:

• Quantity= 14 ton

• Price/ton=9800 LE/TON

• Cost of steel=14*9800=137,200.00 LE

c) FOR EQUIPMENT:  there is no equipment d) FOR S/C:  there is no s/c

Steel fixing total cost=148,000 LE

3. PLACING:

a) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
راجن3150
ىجمروف4120

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=3*150+4*120=1090 LE/DAY

• Duration=quantity/production rate*no. of crew

=94.5/50=2 days

• Labor cost=2*1090=2180 LE

b) FOR MATRIAL:

• Ready concrete mix=545 LE/M3

• Special addition=15 LE/M3

• Material cost/m3=545+15=560 LE/M3

• Material cost=94.5*560=52,920 LE

c) FOR EQUIPMENT:

• Pump cost/m3=50LE/M3

• Pump total cost=50*94.5=4,725 LE

d) FOR S/C:  there is no s/c

Placing total cost= 59,825 LE

TOTAL COST=SHUTTERING COST+STEEL FIXING COST+PLACING COST=224,214 LE

6.3.2. SLABS WORKS

FOR LOWER BASEMENT: (SECOND BASEMENT)

4. SHUTTERING WORKS:

e) FOR LABOR:

LABOR CREW
 NOALL-IN RATE LE/DAY
راجن12150
باشخ3120

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=12*150+3*120=2160 LE/DAY

• Production rate for Slabs =30 m3/day

• Quantity for 2nd basement slab=483.6 m3

• Duration=quantity/production rate*no.of crew=483.6/30=17 days

• Labor cost=duration*daily labor cost=17*2160=36720 LE

f)  FOR MATRIAL:

  TYPEQUANTITY (M3)PRICE (LE/M3)PERCENT OF DEPRECIATION
ةنازتل84.1565015%
يكسوم235.1550010%
يريللف504.555002.2%
ريماسم3 kg/m313 LE/kg50%

• Cost = quantity*price*percent of depreciation

• ةنازتللا بشخ ةفلكت = 84.1*5650*0.15 = 71274.75 LE

• يكسوملا بشخ ةفلكت = 235.1*5500*0.1 = 129305 LE

• يريللفلا بشخ ةفلكت = 504.5*5500*0.022 =61044.5 LE

• ريماسملا ةفلكت = 3*(84.1+235.1+504.5)*0.5*13 = 16062.1 LE

Shuttering total cost= 314406.3 LE

5. STEEL FIXING:

e)  FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
دادح12150
دعاسم3120

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=12*150+3*120= 2160 LE/DAY

• Production rate for slabs = 4.5 ton/day

• Quantity for column= 51.64 ton with 7% depreciation

• Duration=quantity/production rate*no. of crew= 51.64 * 1.07 / 4.5 = 12 days

• Labor cost=duration*daily labor cost

=12*2160= 25920 LE

f)  MATRIAL COST:

• Quantity= 51.64 ton

• Price/ton=9800 LE/TON

•  Cost of steel=51.64*1.07*9800= 541497 LE)نط /مجك 5( طابرلا كلس ةفلكت =5 *52*13 = 3380 LE

Steel fixing total cost=570797 LE

6. PLACING:

e) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
راجن3150
ىجمروف8160

• Labor crew cost/day=∑NO.OF LABOR*LABORE COST PER DAY

• Labor crew cost/day=3*150+8*160= 1730 LE/DAY

• Duration=quantity/production rate*no. of crew=483.6/150= 4 days

• Labor cost= 4*1730= 6920 LE

f)  FOR MATRIAL:

• Ready concrete mix=545 LE/M3

• Special addition=15 LE/M3

• Material cost/m3=545+15=560 LE/M3

• Material cost=483.6*560=270816 LE

g) FOR EQUIPMENT:

• Pump cost/m3=50LE/M3

• Pump total cost=50*483.6= 24180 LE

Placing total cost= 301916 LE

TOTAL COST=SHUTTERING COST+STEEL FIXING COST+PLACING COST

= (1187119.3) LE

6.3.3. RETAINING WALL WORKS

1. Filling behind front retaining walls: –

 Pa rt  “ A”

رتم 11 = مدرلا قمع   •

رتم 203 = مدرلا لوط   •

رتم 2 = مدرلا ضرع   •

3م  4466 = 2* 203* 11 = قمع * ضرع * لوط = هيمكلا   •

•  Duration = Quantity/ No.of crews * P.R

= 4466/ 150=30 days

مويلا/ هفلكتلاتادعملا
180 LE/ hrردول
150 LE/ hrبلاق
150 LE/dayيندم فرشم

g) FOR LABOR:

•  Labor cost=duration*daily labor cost=30*150= 4500 LE

h) FOR EQUIPMENT: Working hours = 8 hr / day

•  Equipment cost/day = 180*8+150*8= 2640 LE/day

•  Equipment cost= 30*2640=79200 LE

i)   FOR S/C:  there is no s/c

j)   FOR MATRIAL:  there is no material

2. Filling behind back retaining walls :-

رتم 11 = مدرلا قمع   • رتم 203 = مدرلا لوط   • رتم 2 = مدرلا ضرع   •

3م  4466 = 2* 203* 11 = قمع * ضرع * لوط = هيمكلا   •

•  Duration = Quantity/ No.of crews * P.R

4466/100 = 45 days

مويلا/ هفلكتلاتادعملا
180 LE/ hrردول
150 LE/ hrبلاق
150 LE/dayيندم فرشم

a)  For Labor

Labor cost=duration*daily labor cost=45*150= 6750 LE

b) FOR EQUIPMENT:

•  Working hours = 8 hr / day

•  Equipment cost/day = 180*8+150*8= 2640 LE/day

•  Equipment cost= 45*2640=118800 LE

c)  FOR S/C:  there is no s/c

d) FOR MATRIAL:  there is no material

Filling total cost =4500+79200+6750+118800=209250 LE

3. SHUTTERING WORKS:

e) FOR LABOR:

LABOR CREW
 NOALL-IN RATE LE/DAY
راجن12150
باشخ3120

• Labor crew cost/day=12*150+3*120=2160 LE/DAY

• Production rate for retaining wall=80 m3/day

• Quantity for column=622 m3

• Duration=quantity/production rate*no.of crew

=622/80=8 days

• Labor cost=duration*daily labor cost

=8*2160=17280 LE

f)  FOR MATRIAL:

-: يلا هينكسلا ينابملا يف هحلسملا هناسرخلا نم بعكم رتم 1 جاتحي

3م 78 = 622*0.125 = يكسوم   •

3م 156 = 622*0.25 = هنازيتلا   •

3م 498 = 622*0.8 = قورع   •

رامسم مجك 1866 = 622*3 = رامسم   •

” كلاهلاا ” بشخلا ةفلكت •

هينج 42900=78*5500*0.1 = يكسوملا بشخ ةفلكت •

هينج 132210=156*5650*0.15

= هنازيتلالا بشخ ةفلكت •

هينج 68475=498*5500*0.025 = قورعلا ةفلكت •

هينج 24631.2=1866*13.2 = رامسملا ةفلكت •

“%50 رامسملا كلاه”

•   FOR EQUIPMENT:  there is no equipment

•   FOR S/C:  there is no s/c

Shuttering total cost= 17280+268216.2  = 285496.2   LE

4. STEEL FIXING:

g) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
دادح12150
دعاسم3120

• Labor crew cost/day=12*150+3*120=2160 LE/DAY

• Production rate for Retaining Wall =10 ton/day

• Quantity for Retaining Wall = 87 ton

• Duration=quantity/production rate*no. of crew

=87/10=8.7 ~ 9 days

• Labor cost=duration*daily labor cost

=9*2160=17280 LE

1 ton of steel needs → 5 kg “ طابر كلس“

h) MATRIAL COST:

• Quantity= 87 ton

• Price/ton=9800 LE/TON

• Price/kg =13 LE

• طابرلا كلس ةفلكت =5*87*13 = 5655 LE

•  FOR EQUIPMENT:  there is no equipment

•  FOR S/C:  there is no s/c

Total Cost of steel=87*9800+5655=858255 LE

5. PLACING:

Cast for Basement 2 R.W Part A

h) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
راجن3150
ىجمروف4120

• Labor crew cost/day=3*150+4*120=1090 LE/DAY

• Duration=quantity/production rate*no. of crew

=622/150=4.15 days ~ 4 days

• Labor cost=4*1090=4360 LE

i)  FOR MATRIAL:

• Ready concrete mix=545 LE/M3

• Special addition=15 LE/M3

• Material cost/m3=545+15=560 LE/M3

• Material cost=622*560=348320 LE

j)  FOR EQUIPMENT:

• Pump cost/m3=50LE/M3

• Pump total cost=50*622=31100 LE

k) FOR S/C:  there is no s/c

Placing total cost= 379420 LE

6. Membrane For R.W Part A

a) FOR LABOR:

LABOR CREW
 NOALL-IN RATE (LE/DAY)
يعيانص1150
دعاسم1120

• Area of membrane = 1589 M2

• 2م/ هينج 60 = ةدناسلا طئاوحلل لزعلا ذيفنتو ديروت

• Labor crew cost/day=1*150+1*120=270 LE/DAY

• Duration=quantity/production rate*no. of crew=1589/40=40 days

Membrane cost=40*270 =10800  LE

TOTAL COST = Filling cost + SHUTTERING COST+STEEL FIXING COST+PLACING COST + membrane cost

=209250+285496.2+858255+379420+10800 = 1743221.2 LE.

6.4. SHEET OF COST ESTIMATE:

COST ESTIMATE SHEET
  ZONE(A)
  ZONE(A) _ pc footing
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      201.15      m3      2      4.00    1728 0      76      15287.4      0      0
  total direct cost =labor+material+equipment+s/c32567.4
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      201.15      m3      1      3      4710      560      112644      0      50    10057. 5

238

  total direct cost =labor+material+equipment+s/c127411.5
      Code      Work Type    Calculations
labormaterialS/Cequipment
         BACKFILLINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      150.00      150.00      451.00      m3      2      2.00      600      30      13530      0      5280
  total direct cost =labor+material+equipment+s/c19410.0
total pc footing cost zone A  =179,388.9
    ZONE(A) _ RC footing
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      296.45      m3      2      5.00    2160 0      76      22530.2      0      0
  total direct cost =labor+material+equipment+s/c44130.2
     FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C

239

      2160    3.2    23.23    Ton    2    4  1728 0    9800    227654    0    0
  total direct cost =labor+material+equipment+s/c244934.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      296.45      m3      1      3      4710      560      166012      0      50    14822. 5
  total direct cost =labor+material+equipment+s/c185544.5
           ISOLATION  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      452.3      m2      2      4      2160      15      6784.5      0      0      0
  total direct cost =labor+material+equipment+s/c8944.5
      Code      Work Type    Calculations
labormaterialS/Cequipment
       BACKFILLINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
    150.00    150.00    1334.00    m3    2    5.00    1500    30    40020    0    13200

240

             
  total direct cost =labor+material+equipment+s/c54720.0
total rc footing cost zone A  =538,273.2
    ZONE(A) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      266.60      m3      1      4.00      8640      88      23460.8      0      0
  total direct cost =labor+material+equipment+s/c32100.8
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    37.3    m3    2    2    8640    9800    365540    0    0
  total direct cost =labor+material+equipment+s/c374180.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

241

        1090      150      266.60      m3      1      2      2180      560    149296.0 0      0      50      13330
  total direct cost =labor+material+equipment+s/c164806.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    780.4    M2    1    20    5400    60    46824    0    0
  total direct cost =labor+material+equipment+s/c52224.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    1560.8    M3    1    11    1650    30    46824    0    2640    29040
  total direct cost =labor+material+equipment+s/c77514.0
total =700824.8
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
     SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
  2160.00  80.00  266.60  m3  1  4.00  8640  88  23460.8  0  0

242

             
  total direct cost =labor+material+equipment+s/c32100.8
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    37.3    m3    2    2    8640    9800    365540    0    0
  total direct cost =labor+material+equipment+s/c374180.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      266.60      m3      1      2      2180      560    149296.0 0      0      50      13330
  total direct cost =labor+material+equipment+s/c164806.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    780.4    M2    1    20    5400    60    46824    0    0
  total direct cost =labor+material+equipment+s/c52224.0
     BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C

243

      150    150    1560.8    M3    1    11    1650    30    46824    0    2640    29040
  total direct cost =labor+material+equipment+s/c77514.0
total =700824.8
  Total RW zone A  1,401,649.6
    ZONE(A) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      89.50      m3      1      3      6480      82      7339      0      0
  total direct cost =labor+material+equipment+s/c13819.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    13    m3    1    5  1080 0    9800    127400    0    0

244

  total direct cost =labor+material+equipment+s/c138200.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      89.5      m3      1      2      2180      560      50120      0      50      4475
  total direct cost =labor+material+equipment+s/c56775.0
total =208794.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      94.50      m3      1      4.00      8640      82      7749      0      0
  total direct cost =labor+material+equipment+s/c16389.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    14    m3    1    5  1080 0    9800    137200    0    0

245

  total direct cost =labor+material+equipment+s/c148000.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      94.5      m3      1      2      2180      560      52920      0      50      4725
  total direct cost =labor+material+equipment+s/c59825.0
total =224214.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      42.80      m3      1      2.00      4320      82      3509.6      0      0
  total direct cost =labor+material+equipment+s/c7829.6
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    7    m3    1    3    6480    9800    68600    0    0

246

  total direct cost =labor+material+equipment+s/c75080.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      42.8      m3      1      1      1090      560      23968      0      50      2140
  total direct cost =labor+material+equipment+s/c27198.0
total =110107.6
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      39.00      m3      1      2.00      4320      82      3198      0      0
  total direct cost =labor+material+equipment+s/c7518.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    7    m3    1    3    6480    9800    68600    0    0

247

  total direct cost =labor+material+equipment+s/c75080.0
           PLACING  labor  materialS/ C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      39      m3      1      1      1090      560      21840      0      50      1950
  total direct cost =labor+material+equipment+s/c24880.0
total =107478.0
total column cost zone A =865,549.6
  ZONE(A) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      483.60      m3      2      9.00    3888 0      95      45942      0      0
  total direct cost =labor+material+equipment+s/c84822.0

248

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    51.64    m3    2    6.00  2592 0    9800    506072    0    0
  total direct cost =labor+material+equipment+s/c531992.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      483.60      m3      2      2.00      6920      560      270816      0      50      24180
  total direct cost =labor+material+equipment+s/c301916.0
total =918730.0
UPPER BASEMENT
     Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      510.00      m3      2      9.00    3888 0      95      48450      0      0
  total direct cost =labor+material+equipment+s/c87330.0

249

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    52.3    m3    2    6.00  2592 0    9800    512540    0    0
  total direct cost =labor+material+equipment+s/c538460.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      510.00      m3      2      2.00      6920      560      285600      0      50      25500
  total direct cost =labor+material+equipment+s/c318020.0
total =943810.0
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      958.80      M3      1      7      1050      30      28764      0      2640      18480
  total direct cost =labor+material+equipment+s/c48294.0

250

         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.00      TON      1      1      540      9800      9780.4      0      0
  total direct cost =labor+material+equipment+s/c10320.4
         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      318.90      M3      1      4      2560      560      178584      050/M3      20745
  1200/da y
  total direct cost =labor+material+equipment+s/c201889.0
total =260503.4
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      131.60      m3      1      5.00    1080 0      95      12502      0      0
  total direct cost =labor+material+equipment+s/c23302.0
 FIXING STEELlabormaterialS/Cequipment

251

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    16.5    m3    1    4.00    8640    9800    161700    0    0
  total direct cost =labor+material+equipment+s/c170340.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      131.60      m3      1      1.00      1730      560      73696      0      50      6580
  total direct cost =labor+material+equipment+s/c82006.0
total =275648.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      131.60      m3      1      5.00    1080 0      95      12502      0      0
  total direct cost =labor+material+equipment+s/c23302.0
 FIXING STEELlabormaterialS/Cequipment

252

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    16.5    m3    1    4    8640    9800    161700    0    0
  total direct cost =labor+material+equipment+s/c170340.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      131.60      m3      1      1      1730      560      73696      0      50      6580
  total direct cost =labor+material+equipment+s/c82006.0
total =275648.0
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone A3,398,115.4
  ZONE(A) _ BRICKS
  Code  Work Type  Calculations

253

   
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
      540.00      3000.00      5307.00      Brick      1      2      1080      1.096      5816.472      0      0
  total direct cost =labor+material+equipment+s/c6896.5
total =6896.5
TOTAL COST OF ZONE (A)#REF!
ZONE (B)
  ZONE(B) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      170.90      m3      2      3.00    1296 0      76      12988.4      0      0
  total direct cost =labor+material+equipment+s/c25948.4
A2PLACINGlabormaterialS/Cequipment

254

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      170.9      m3      1      2      3140      560      95704      0      50      8545
  total direct cost =labor+material+equipment+s/c107389.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LEm3  D.C  D.C  D.C
    150    150    295    m3    2    1    300    30    8850    0    2640
  total direct cost =labor+material+equipment+s/c11790.0
total pc footing cost zone B  =145,127.4
  ZONE(B) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      259.06      m3      2      5.00    2160 0      76      19688.56      0      0
  total direct cost =labor+material+equipment+s/c41288.6

255

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    18.1    Ton    2    3  1296 0    9800    177380    0    0
  total direct cost =labor+material+equipment+s/c190340.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      259.06      m3      1      3      4710      560      145073.6      0      50      12953
  total direct cost =labor+material+equipment+s/c162736.6
           ISOLATION  labor  materialS/ C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      428.1      m2      2      4      1080      15      6421.5      0      0      0
  total direct cost =labor+material+equipment+s/c7501.5
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LEm3  D.C  D.C  D.C
    150    150    771    m3    2    3    900    30    23130    0    7920

256

  total direct cost =labor+material+equipment+s/c31950.0
total Rc footing cost zone B  =433,816.7
  ZONE(B) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      63.00      m3      1      1.00      2160      88      5544      0      0
  total direct cost =labor+material+equipment+s/c7704.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    8.8    m3    1    1    2160    9800    86240    0    0
  total direct cost =labor+material+equipment+s/c88400.0
       PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1090  150  63.00  m3  1  1  1090  560  35280.00  0  50  3150

257

              
  total direct cost =labor+material+equipment+s/c39520.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    153    M2    1    4    1080    60    9180    0    0
  total direct cost =labor+material+equipment+s/c10260.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    157.75    M3    1    2    300    30    4732.5    0    2640    5280
  total direct cost =labor+material+equipment+s/c10312.5
total =156196.5
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
       SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
    2160.00    80.00    63.00    m3    1    1.00    2160    88    5544    0    0

258

             
  total direct cost =labor+material+equipment+s/c7704.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    8.8    m3    1    1    2160    9800    86240    0    0
  total direct cost =labor+material+equipment+s/c88400.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      63.00      m3      1      1      1090      560      35280.00      0      50      3150
  total direct cost =labor+material+equipment+s/c39520.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    153    M2    1    4    1080    60    9180    0    0
  total direct cost =labor+material+equipment+s/c10260.0
     BACKFILLING  labor  materialS/ C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C

259

      150    150    157.75    M3    1    2    300    30    4732.5    0    2640    5280
  total direct cost =labor+material+equipment+s/c10312.5
total =156196.5
Total RW zone A312,393.00
  ZONE(B) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      87.00      m3      1      3.00      6480      82      7134      0      0
  total direct cost =labor+material+equipment+s/c13614.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    12    m3    1    4    8640    9800    117600    0    0
  total direct cost =labor+material+equipment+s/c126240.0
 PLACINGlabormaterialS/Cequipment

260

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      87      m3      1      2      2180      560      48720      0      50      4350
  total direct cost =labor+material+equipment+s/c55250.0
total =195104.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      93.00      m3      1      4.00      8640      82      7626      0      0
  total direct cost =labor+material+equipment+s/c16266.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    14    m3    1    5  1080 0    9800    137200    0    0
  total direct cost =labor+material+equipment+s/c148000.0
 PLACINGlabormaterialS/Cequipment

261

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      93      m3      1      2      2180      560      52080      0      50      4650
  total direct cost =labor+material+equipment+s/c58910.0
total =223176.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      37.00      m3      1      2.00      4320      82      3034      0      0
  total direct cost =labor+material+equipment+s/c7354.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
 PLACINGlabormaterialS/Cequipment

262

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      37      m3      1      1      1090      560      20720      0      50      1850
  total direct cost =labor+material+equipment+s/c23660.0
total =94134.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      36.00      m3      1      2.00      4320      82      2952      0      0
  total direct cost =labor+material+equipment+s/c7272.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
 PLACINGlabormaterialS/Cequipment

263

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      36      m3      1      1      1090      560      20160      0      50      1800
  total direct cost =labor+material+equipment+s/c23050.0
total =93442.0
total column cost zone B =792,740.0
  ZONE(B) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      481.90      m3      2      9.00    3888 0      95      45780.5      0      0
  total direct cost =labor+material+equipment+s/c84660.5
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    51.7    m3    2    6  2592 0    9800    506660    0    0

264

  total direct cost =labor+material+equipment+s/c532580.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      481.90      m3      2      2      6920      560      269864      0      50      24095
  total direct cost =labor+material+equipment+s/c300879.0
total =918119.5
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      497.00      m3      2      9.00    3888 0      95      47215      0      0
  total direct cost =labor+material+equipment+s/c86095.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    49.9    m3    2    6  2592 0    9800    489020    0    0
  total direct cost =labor+material+equipment+s/c514940.0

265

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      497.00      m3      2      2      6920      560      278320      0      50      24850
  total direct cost =labor+material+equipment+s/c310090.0
total =911125.0
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      1011.90      M3      1      7      1050      30      30357      0      2640      18480
  total direct cost =labor+material+equipment+s/c49887.0
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.05      TON      1      1      540      9800      10250.8      0      0
  total direct cost =labor+material+equipment+s/c10790.8

266

         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      337.30      M3      1      4      2560      560      188888      050/M3      21665
  1200/da y
  total direct cost =labor+material+equipment+s/c213113.0
total =273790.8
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      132.40      m3      1      5.00    1080 0      95      12578      0      0
  total direct cost =labor+material+equipment+s/c23378.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    17    m3    1    4    8640    9800    166600    0    0
  total direct cost =labor+material+equipment+s/c175240.0
 PLACINGlabormaterialS/Cequipment

267

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      132.40      m3      1      1      1730      560      74144      0      50      6620
  total direct cost =labor+material+equipment+s/c82494.0
total =281112.0
REPETATIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      132.40      m3      1      5.00    1080 0      95      12578      0      0
  total direct cost =labor+material+equipment+s/c23378.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    17    m3    1    4    8640    9800    166600    0    0
  total direct cost =labor+material+equipment+s/c175240.0
 PLACINGlabormaterialS/Cequipment

268

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      132.40      m3      1      1      1730      560      74144      0      50      6620
  total direct cost =labor+material+equipment+s/c82494.0
total =281112.0
 
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone B3,399,963.3
  ZONE(B) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
  540.00  3000.00  5902.00  Brick  1  2  1080  1.096  6468.592  0  0

269

             
  total direct cost =labor+material+equipment+s/c7548.6
  total =7548.592
TOTAL COST OF ZONE (B)5,091,589.0
ZONE (C)
  ZONE(C) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      285.90      m3      2      5.00    2160 0      76      21728.4      0      0
  total direct cost =labor+material+equipment+s/c43328.4
          A2          PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      285.9      m3      1      3      4710      560      160104      0      50      14295

270

  total direct cost =labor+material+equipment+s/c179109.0
           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  DC
      150      150      269      m3      2      1      300      30      8070      0      2640
  total direct cost =labor+material+equipment+s/c11010.0
total pc footing cost zone C =233,447.4
  ZONE(C) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      396.00      m3      3      5.00    3240 0      76      30096      0      0
  total direct cost =labor+material+equipment+s/c62496.0
       FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
  2160  3.2  29.82  Ton  2  5   9800  292236  0  0

271

        2160 0    
  total direct cost =labor+material+equipment+s/c313836.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      396      m3      2      2      6280      560      221760      0      50      19800
  total direct cost =labor+material+equipment+s/c247840.0
           ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      566.94      m2      3      3      2430      15      8504.1      0      0      0
  total direct cost =labor+material+equipment+s/c10934.1
           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  DC
      150      150      659      m3      2      3      900      30      19770      0      7920
  total direct cost =labor+material+equipment+s/c28590.0
total Rc footing cost zone C =663,696.1

272

  ZONE(C) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      71.00      m3      1      1.00      2160      88      6248      0      0
  total direct cost =labor+material+equipment+s/c8408.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    10    m3    1    1    2160    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c100160.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      71.00      m3      1      1      1090      560      39760.00      0      50      3550

273

  total direct cost =labor+material+equipment+s/c44400.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    202    M2    1    6    1620    60    12120    0    0
  total direct cost =labor+material+equipment+s/c13740.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    135.5    M3    1    1    150    30    4065    0    2640    2640
  total direct cost =labor+material+equipment+s/c6855.0
total =173563.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      71.00      m3      1      1.00      2160      88      6248      0      0
  total direct cost =labor+material+equipment+s/c8408.0

274

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    10    m3    1    1    2160    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c100160.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      71.00      m3      1      1      1090      560      39760.00      0      50      3550
  total direct cost =labor+material+equipment+s/c44400.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    202    M2    1    6    1620    60    12120    0    0
  total direct cost =labor+material+equipment+s/c13740.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    135.5    M3    1    1    150    30    4065    0    2640    2640
  total direct cost =labor+material+equipment+s/c6855.0

275

total =173563.0
  Total RW zone C  347,126.0
  ZONE(C) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      120.00      m3      2      2.00      8640      82      9840      0      0
  total direct cost =labor+material+equipment+s/c18480.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    16    m3    2    3  1296 0    9800    156800    0    0
  total direct cost =labor+material+equipment+s/c169760.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

276

        1090      50      120      m3      2      2      4360      560      67200      0      50      6000
  total direct cost =labor+material+equipment+s/c77560.0
total =265800.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      125.00      m3      2      3.00    1296 0      82      10250      0      0
  total direct cost =labor+material+equipment+s/c23210.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    18    m3    2    3  1296 0    9800    176400    0    0
  total direct cost =labor+material+equipment+s/c189360.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

277

        1090      50      125      m3      2      2      4360      560      70000      0      50      6250
  total direct cost =labor+material+equipment+s/c80610.0
total =293180.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      59.00      m3      1      2.00      4320      82      4838      0      0
  total direct cost =labor+material+equipment+s/c9158.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    10    m3    2    2    8640    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c106640.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

278

        1090      50      59      m3      1      2      2180      560      33040      0      50      2950
  total direct cost =labor+material+equipment+s/c38170.0
total =153968.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      72.00      m3      1      3.00      6480      82      5904      0      0
  total direct cost =labor+material+equipment+s/c12384.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    9    m3    1    3    6480    9800    88200    0    0
  total direct cost =labor+material+equipment+s/c94680.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

279

        1090      50      72      m3      1      2      2180      560      40320      0      50      3600
  total direct cost =labor+material+equipment+s/c46100.0
total =153164.0
total column cost zone C =1,172,440.0
  ZONE(C) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      810.35      m3      3      10.00    6480 0      95      76983.25      0      0
  total direct cost =labor+material+equipment+s/c141783.3
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    90.3    m3    3    7  4536 0    9800    884940    0    0
  total direct cost =labor+material+equipment+s/c930300.0

280

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      810.35      m3      2      3    1038 0      560      453796      0      50    40517. 5
  total direct cost =labor+material+equipment+s/c504693.5
total =1576776.8
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      507.00      m3      3      6.00    3888 0      95      48165      0      0
  total direct cost =labor+material+equipment+s/c87045.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    88.6    m3    3    7  4536 0    9800    868280    0    0
  total direct cost =labor+material+equipment+s/c913640.0

281

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      507.00      m3      2      2      6920      560      283920      0      50      25350
  total direct cost =labor+material+equipment+s/c316190.0
total =1316875.0
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      1632.80      M3      1      11      1650      30      48984      0      2640      29040
  total direct cost =labor+material+equipment+s/c79674.0
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.69      TON      1      1      540      9800      16532.6      0      0
  total direct cost =labor+material+equipment+s/c17072.6

282

         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      544.25      M3      1      6      3840      560      304780      050/M3    34412. 5
  1200/da y
  total direct cost =labor+material+equipment+s/c343032.5
total =439779.1
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      194.60      m3      1      7.00    1512 0      95      18487      0      0
  total direct cost =labor+material+equipment+s/c33607.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    25.6    m3    2    3  1296 0    9800    250880    0    0
  total direct cost =labor+material+equipment+s/c263840.0
 PLACINGlabormaterialS/Cequipment

283

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      194.60      m3      1      2      3460      560      108976      0      50      9730
  total direct cost =labor+material+equipment+s/c122166.0
total =419613.0
REPETATIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      194.60      m3      1      7.00    1512 0      95      18487      0      0
  total direct cost =labor+material+equipment+s/c33607.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    25.6    m3    1    6  1296 0    9800    250880    0    0
  total direct cost =labor+material+equipment+s/c263840.0
 PLACINGlabormaterialS/Cequipment

284

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      194.60      m3      1      2      3460      560      108976      0      50      9730
  total direct cost =labor+material+equipment+s/c122166.0
total =419613.0
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone C5,184,362.9
  ZONE(C) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
    540.00    3000.00    4916.00    Brick    1    2    1080    1.096    5387.936    0    0

285

             
  total direct cost =labor+material+equipment+s/c6467.9
total =6467.9
TOTAL COST OF ZONE ( C)7,607,540.3
ZONE (D)
  ZONE(D) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      262.70      m3      2      5.00    2160 0      76      19965.2      0      0
  total direct cost =labor+material+equipment+s/c41565.2
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      262.7      m3      1      3      4710      560      147112      0      50      13135
  total direct cost =labor+material+equipment+s/c164957.0

286

           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/m3  D.C  D.C  DC
      150      150      301      m3      2      2      600      30      9030      0      5280
  total direct cost =labor+material+equipment+s/c14910.0
total pc footing cost zone D =221,432.2
  ZONE(D) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      468.13      m3      2      8.00    3456 0      76      35577.88      0      0
  total direct cost =labor+material+equipment+s/c70137.9
       FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
  2160  3.2  26.57  Ton  2  5   9800  260386  0  0

287

        2160 0    
  total direct cost =labor+material+equipment+s/c281986.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      468.13      m3      2      3      9420      560      262152.8      0      50    23406. 5
  total direct cost =labor+material+equipment+s/c294979.3
           ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      708.74      m2      3      4      3240      15      10631.1      0      0      0
  total direct cost =labor+material+equipment+s/c13871.1
           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/m3  D.C  D.C  DC
      150      150      722      m3      2      3      900      30      21660      0      7920
  total direct cost =labor+material+equipment+s/c30480.0
total Rc footing cost zone D =691,454.3

288

  ZONE(D) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      57.00      m3      1      1.00      2160      88      5016      0      0
  total direct cost =labor+material+equipment+s/c7176.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    27.5    m3    1    3    6480    9800    269500    0    0
  total direct cost =labor+material+equipment+s/c275980.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      57.00      m3      1      1      1090      560      31920.00      0      50      2850

289

  total direct cost =labor+material+equipment+s/c35860.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    162.3    M2    1    5    1350    60    9738    0    0
  total direct cost =labor+material+equipment+s/c11088.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    324.6    M3    1    3    450    30    9738    0    2640    7920
  total direct cost =labor+material+equipment+s/c18108.0
total =348212.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      57.00      m3      1      1.00      2160      88      5016      0      0
  total direct cost =labor+material+equipment+s/c7176.0

290

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    27.5    m3    1    3    6480    9800    269500    0    0
  total direct cost =labor+material+equipment+s/c275980.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      57.00      m3      1      1      1090      560      31920.00      0      50      2850
  total direct cost =labor+material+equipment+s/c35860.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    162.3    M2    1    5    1350    60    9738    0    0
  total direct cost =labor+material+equipment+s/c11088.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    324.6    M3    1    3    450    30    9738    0    2640    7920
  total direct cost =labor+material+equipment+s/c18108.0

291

total =348212.0
Total RW zone D696,424.0
  ZONE(D) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      168.40      m3      2      3.00    1296 0      82      13808.8      0      0
  total direct cost =labor+material+equipment+s/c26768.8
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    21    m3    2    4  1728 0    9800    205800    0    0
  total direct cost =labor+material+equipment+s/c223080.0
       PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1090  50  168.4  m3  2  2  4360  560  94304  0  50  8420

292

              
  total direct cost =labor+material+equipment+s/c107084.0
total =356932.8
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      171.00      m3      2      3.00    1296 0      82      14022      0      0
  total direct cost =labor+material+equipment+s/c26982.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    22    m3    2    4  1728 0    9800    215600    0    0
  total direct cost =labor+material+equipment+s/c232880.0
       PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1090  50  171  m3  2  2  4360  560  95760  0  50  8550

293

              
  total direct cost =labor+material+equipment+s/c108670.0
total =368532.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      75.00      m3      2      2.00      8640      82      6150      0      0
  total direct cost =labor+material+equipment+s/c14790.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    13    m3    2    3  1296 0    9800    127400    0    0
  total direct cost =labor+material+equipment+s/c140360.0
       PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1090  50  75  m3  2  1  2180  560  42000  0  50  3750

294

              
  total direct cost =labor+material+equipment+s/c47930.0
total =203080.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      69.00      m3      2      2.00      8640      82      5658      0      0
  total direct cost =labor+material+equipment+s/c14298.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    12    m3    2    2    8640    9800    117600    0    0
  total direct cost =labor+material+equipment+s/c126240.0
       PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1090  50  69  m3  2  1  2180  560  38640  0  50  3450

295

              
  total direct cost =labor+material+equipment+s/c44270.0
total =184808.0
total column cost zone D =1,482,968.8
  ZONE(D) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      389.45      m3      2      7.00    3024 0      95      36997.75      0      0
  total direct cost =labor+material+equipment+s/c67237.8
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    42.2    m3    2    5  2160 0    9800    413560    0    0
  total direct cost =labor+material+equipment+s/c435160.0
 PLACINGlabormaterialS/Cequipment

296

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      389.45      m3      2      2      6920      560      218092      0      50    19472. 5
  total direct cost =labor+material+equipment+s/c244484.5
total =746882.3
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      395.10      m3      2      7.00    3024 0      95      37534.5      0      0
  total direct cost =labor+material+equipment+s/c67774.5
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    42.7    m3    2    5  2160 0    9800    418460    0    0
  total direct cost =labor+material+equipment+s/c440060.0
 PLACINGlabormaterialS/Cequipment

297

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      395.10      m3      2      2      6920      560      221256      0      50      19755
  total direct cost =labor+material+equipment+s/c247931.0
total =755765.5
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      741.75      M3      1      5      750      30      22252.5      0      2640      13200
  total direct cost =labor+material+equipment+s/c36202.5
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      0.77      TON      1      1      540      9800      7511.7      0      0
  total direct cost =labor+material+equipment+s/c8051.7
   PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C

298

        640.00      100.00      247.25      M3      1      3      1920      560      138460      050/M3    15962. 5
  1200/da y
  total direct cost =labor+material+equipment+s/c156342.5
total =200596.7
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      199.00      m3      1      7.00    1512 0      95      18905      0      0
  total direct cost =labor+material+equipment+s/c34025.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    26.2    m3    2    3  1296 0    9800    256760    0    0
  total direct cost =labor+material+equipment+s/c269720.0
       PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1730  150  199.00  m3  1  2  3460  560  111440  0  50  9950

299

              
  total direct cost =labor+material+equipment+s/c124850.0
total =428595.0
REPETATIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      199.00      m3      1      7.00    1512 0      95      18905      0      0
  total direct cost =labor+material+equipment+s/c34025.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    26.2    m3    1    6  1296 0    9800    256760    0    0
  total direct cost =labor+material+equipment+s/c269720.0
       PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
  1730  150  199.00  m3  1  2  3460  560  111440  0  50  9950

300

              
  total direct cost =labor+material+equipment+s/c124850.0
total =428595.0
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone D3,590,104.5
  ZONE(D) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
      540.00      3000.00      6307.00      Brick      1      3      1620      1.096      6912.472      0      0
  total direct cost =labor+material+equipment+s/c8532.5
total =8532.5

301

TOTAL COST OF ZONE (D)6,690,916.2
ZONE (E)
  ZONE(E) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      230.60      m3      2      4.00    1728 0      76      17525.6      0      0
  total direct cost =labor+material+equipment+s/c34805.6
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      230.6      m3      2      2      6280      560      129136      0      50      11530
  total direct cost =labor+material+equipment+s/c146946.0
      Code      Work Type    Calculations
labormaterialS/Cequipment

302

         BACKFILLINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      150.00      150.00      331.00      m3      2      2.00      600      30      9930      0      5280
  total direct cost =labor+material+equipment+s/c15810.0
total pc footing cost zone E =197,561.6
  ZONE(E) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      401.00      m3      2      7.00    3024 0      76      30476      0      0
  total direct cost =labor+material+equipment+s/c60716.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    30.36    Ton    2    5  2160 0    9800    297528    0    0
  total direct cost =labor+material+equipment+s/c319128.0

303

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      401      m3      2      3      9420      560      224560      0      50      20050
  total direct cost =labor+material+equipment+s/c254030.0
           ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      567.54      m2      2      5      2700      15      8513.1      0      0      0
  total direct cost =labor+material+equipment+s/c11213.1
      Code      Work Type    Calculations
labormaterialS/Cequipment
         BACKFILLINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      150.00      150.00      862.00      m3      2      3.00      900      30      25860      0      7920
  total direct cost =labor+material+equipment+s/c34680.0
total Rc footing cost zone E =679,767.1

304

  ZONE(E) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      59.25      m3      1      1.00      2160      88      5214      0      0
  total direct cost =labor+material+equipment+s/c7374.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    8.35    m3    1    1    2160    9800    81830    0    0
  total direct cost =labor+material+equipment+s/c83990.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      59.25      m3      1      1      1090      560      33180.00      0      50      2962.5

305

  total direct cost =labor+material+equipment+s/c37232.5
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    169.2    M2    1    5    1350    60    10152    0    0
  total direct cost =labor+material+equipment+s/c11502.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    338.44    M3    1    3    450    30    10153.2    0    2640    7920
  total direct cost =labor+material+equipment+s/c18523.2
total =158621.7
  UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      59.25      m3      1      1.00      2160      88      5214      0      0

306

  total direct cost =labor+material+equipment+s/c7374.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    8.35    m3    1    1    2160    9800    81830    0    0
  total direct cost =labor+material+equipment+s/c83990.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      59.25      m3      1      1      1090      560      33180.00      0      50      2962.5
  total direct cost =labor+material+equipment+s/c37232.5
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    169.2    M2    1    5    1350    60    10152    0    0
  total direct cost =labor+material+equipment+s/c11502.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    338.44    M3    1    3    450    30    10153.2    0    2640    7920

307

  total direct cost =labor+material+equipment+s/c18523.2
total =158621.7
Total RW zone E317,243.4
  ZONE(E) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      120.00      m3      2      2.00      8640      82      9840      0      0
  total direct cost =labor+material+equipment+s/c18480.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    16    m3    2    3  1296 0    9800    156800    0    0
  total direct cost =labor+material+equipment+s/c169760.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

308

        1090      50      120      m3      2      2      4360      560      67200      0      50      6000
  total direct cost =labor+material+equipment+s/c77560.0
total =265800.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      125.00      m3      2      3.00    1296 0      82      10250      0      0
  total direct cost =labor+material+equipment+s/c23210.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    18    m3    2    3  1296 0    9800    176400    0    0
  total direct cost =labor+material+equipment+s/c189360.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

309

        1090      50      125      m3      2      2      4360      560      70000      0      50      6250
  total direct cost =labor+material+equipment+s/c80610.0
total =293180.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      59.00      m3      1      2.00      4320      82      4838      0      0
  total direct cost =labor+material+equipment+s/c9158.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    10    m3    2    2    8640    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c106640.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

310

        1090      50      59      m3      1      2      2180      560      33040      0      50      2950
  total direct cost =labor+material+equipment+s/c38170.0
total =153968.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      36.00      m3      1      2.00      4320      82      2952      0      0
  total direct cost =labor+material+equipment+s/c7272.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    9    m3    2    2    8640    9800    88200    0    0
  total direct cost =labor+material+equipment+s/c96840.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

311

        1090      50      36      m3      1      1      1090      560      20160      0      50      1800
  total direct cost =labor+material+equipment+s/c23050.0
total =127162.0
total column cost zone E =1,094,434.0
  ZONE(E) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      810.35      m3      3      10.00    6480 0      95      76983.25      0      0
  total direct cost =labor+material+equipment+s/c141783.3
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    90.3    m3    3    7  4536 0    9800    884940    0    0
  total direct cost =labor+material+equipment+s/c930300.0

312

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      810.35      m3      2      3    1038 0      560      453796      0      50    40517. 5
  total direct cost =labor+material+equipment+s/c504693.5
total =1576776.8
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      507.00      m3      3      6.00    3888 0      95      48165      0      0
  total direct cost =labor+material+equipment+s/c87045.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    88.6    m3    3    7  4536 0    9800    868280    0    0
  total direct cost =labor+material+equipment+s/c913640.0

313

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      507.00      m3      2      2      6920      560      283920      0      50      25350
  total direct cost =labor+material+equipment+s/c316190.0
total =1316875.0
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      1632.80      M3      1      11      1650      30      48984      0      2640      29040
  total direct cost =labor+material+equipment+s/c79674.0
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.69      TON      1      1      540      9800      16532.6      0      0
  total direct cost =labor+material+equipment+s/c17072.6

314

         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      544.25      M3      1      6      3840      560      304780      050/M3    34412. 5
  1200/da y
  total direct cost =labor+material+equipment+s/c343032.5
total =439779.1
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      194.60      m3      2      4.00    1728 0      95      18487      0      0
  total direct cost =labor+material+equipment+s/c35767.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    25.6    m3    2    3  1296 0    9800    250880    0    0
  total direct cost =labor+material+equipment+s/c263840.0
 PLACINGlabormaterialS/Cequipment

315

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      194.60      m3      2      1      3460      560      108976      0      50      9730
  total direct cost =labor+material+equipment+s/c122166.0
total =421773.0
REPETATIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      194.60      m3      2      4.00    1728 0      95      18487      0      0
  total direct cost =labor+material+equipment+s/c35767.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    25.6    m3    2    3  1296 0    9800    250880    0    0
  total direct cost =labor+material+equipment+s/c263840.0
 PLACINGlabormaterialS/Cequipment

316

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      194.60      m3      2      1      3460      560      108976      0      50      9730
  total direct cost =labor+material+equipment+s/c122166.0
total =421773.0
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone E5,193,002.9
  ZONE(E) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
    540.00    3000.00    4916.00    Brick    1    2    1080    1.096    5387.936    0    0

317

             
  total direct cost =labor+material+equipment+s/c6467.9
total  =6467.9
TOTAL COST OF ZONE (E)7,488,476.9
ZONE (F)
  ZONE(F) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      164.00      m3      2      3.00    1296 0      76      12464      0      0
  total direct cost =labor+material+equipment+s/c25424.0
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      164      m3      1      2      3140      560      91840      0      50      8200
  total direct cost =labor+material+equipment+s/c103180.0

318

         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LEm3  D.C  D.C  D.C
    150    150    289    m3    2    1    300    30    8670    0    2640
  total direct cost =labor+material+equipment+s/c11610.0
total pc footing cost zone F  =140,214.0
  ZONE(F) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      249.67      m3      2      5.00    2160 0      76      18974.92      0      0
  total direct cost =labor+material+equipment+s/c40574.9
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    15.94    Ton    2    3  1296 0    9800    156212    0    0
  total direct cost =labor+material+equipment+s/c169172.0

319

           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      249.67      m3      1      3      4710      560      139815.2      0      50    12483. 5
  total direct cost =labor+material+equipment+s/c157008.7
           ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      435.16      m2      2      4      2160      15      6527.4      0      0      0
  total direct cost =labor+material+equipment+s/c8687.4
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LEm3  D.C  D.C  D.C
    150    150    693    m3    2    3    900    30    20790    0    7920
  total direct cost =labor+material+equipment+s/c29610.0
total Rc footing cost zone F  =405,053.0
  ZONE(F) _ RETAINING WALL
LOWER BASEMENT   

320

       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      113.50      m3      2      1.00      4320      88      9988      0      0
  total direct cost =labor+material+equipment+s/c14308.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    15.9    m3    2    1    4320    9800    155820    0    0
  total direct cost =labor+material+equipment+s/c160140.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      113.50      m3      1      1      1090      560      63560.00      0      50      5675
  total direct cost =labor+material+equipment+s/c70325.0
     MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C

321

      270    40    324.1    M2    2    5    2700    60    19446    0    0
  total direct cost =labor+material+equipment+s/c22146.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    648.2    M3    1    5    750    30    19446    0    2640    13200
  total direct cost =labor+material+equipment+s/c33396.0
total =300315.0
  UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      113.50      m3      2      1.00      4320      88      9988      0      0
  total direct cost =labor+material+equipment+s/c14308.0
     FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C

322

      2160    10    15.9    m3    2    1    4320    9800    155820    0    0
  total direct cost =labor+material+equipment+s/c160140.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      113.50      m3      1      1      1090      560      63560.00      0      50      5675
  total direct cost =labor+material+equipment+s/c70325.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    324.1    M2    2    5    2700    60    19446    0    0
  total direct cost =labor+material+equipment+s/c22146.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    648.2    M3    1    5    750    30    19446    0    2640    13200
  total direct cost =labor+material+equipment+s/c33396.0
total =300315.0
Total RW zone F600,630.0

323

  ZONE(F) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      86.00      m3      1      3.00      6480      82      7052      0      0
  total direct cost =labor+material+equipment+s/c13532.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    18    m3    1    6  1296 0    9800    176400    0    0
  total direct cost =labor+material+equipment+s/c189360.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      86      m3      1      2      2180      560      48160      0      50      4300

324

  total direct cost =labor+material+equipment+s/c54640.0
total =257532.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      66.00      m3      1      3.00      6480      82      5412      0      0
  total direct cost =labor+material+equipment+s/c11892.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    10    m3    1    4    8640    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c106640.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      66      m3      1      2      2180      560      36960      0      50      3300
  total direct cost =labor+material+equipment+s/c42440.0

325

total =160972.0
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      29.67      m3      1      1.00      2160      82      2432.94      0      0
  total direct cost =labor+material+equipment+s/c4592.9
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    9    m3    1    3    6480    9800    88200    0    0
  total direct cost =labor+material+equipment+s/c94680.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      29.67      m3      1      1      1090      560      16615.2      0      50      1483.5
  total direct cost =labor+material+equipment+s/c19188.7
total =118461.6

326

REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      27.12      m3      1      1.00      2160      82      2223.84      0      0
  total direct cost =labor+material+equipment+s/c4383.8
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    10    m3    1    4    8640    9800    98000    0    0
  total direct cost =labor+material+equipment+s/c106640.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      27.12      m3      1      1      1090      560      15187.2      0      50      1356
  total direct cost =labor+material+equipment+s/c17633.2
total =128657.0
total column cost zone F =922,936.8

327

  ZONE(F) _ SLABS
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      481.90      m3      2      9.00    3888 0      95      45780.5      0      0
  total direct cost =labor+material+equipment+s/c84660.5
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    51.7    m3    2    6  2592 0    9800    506660    0    0
  total direct cost =labor+material+equipment+s/c532580.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      481.90      m3      2      2      6920      560      269864      0      50      24095

328

  total direct cost =labor+material+equipment+s/c300879.0
total =918119.5
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      497.00      m3      2      9.00    3888 0      95      47215      0      0
  total direct cost =labor+material+equipment+s/c86095.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    49.9    m3    2    6  2592 0    9800    489020    0    0
  total direct cost =labor+material+equipment+s/c514940.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      497.00      m3      2      2      6920      560      278320      0      50      24850
  total direct cost =labor+material+equipment+s/c310090.0

329

total =911125.0
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      1011.90      M3      1      7      1050      30      30357      0      2640      18480
  total direct cost =labor+material+equipment+s/c49887.0
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.05      TON      1      1      540      9800      10250.8      0      0
  total direct cost =labor+material+equipment+s/c10790.8
         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      337.30      M3      1      4      2560      560      188888      050/M3      21665
  1200/da y
  total direct cost =labor+material+equipment+s/c213113.0
total =273790.8
GROUND FLOOR

330

       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      132.40      m3      1      5.00    1080 0      95      12578      0      0
  total direct cost =labor+material+equipment+s/c23378.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    17    m3    1    4    8640    9800    166600    0    0
  total direct cost =labor+material+equipment+s/c175240.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      132.40      m3      1      1      1730      560      74144      0      50      6620
  total direct cost =labor+material+equipment+s/c82494.0
total =281112.0
REPETATIVE FLOOR

331

       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      132.40      m3      1      5.00    1080 0      95      12578      0      0
  total direct cost =labor+material+equipment+s/c23378.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    17    m3    1    4    8640    9800    166600    0    0
  total direct cost =labor+material+equipment+s/c175240.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      132.40      m3      1      1      1730      560      74144      0      50      6620
  total direct cost =labor+material+equipment+s/c82494.0
total =281112.0
    labor  material  S/C  equipment

332

         Elec. Empty Conduitslabor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0
  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone F3,399,963.3
    ZONE(F) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
      540.00      3000.00      5902.00      Brick      1      2      1080      1.096      6468.592      0      0
  total direct cost =labor+material+equipment+s/c7548.6
total =7548.6
TOTAL COST OF ZONE (F)5,476,345.7
ZONE (G)
  ZONE(G) _ pc footing
 

333

      Code      Work Type    Calculations
labormaterialS/Cequipment
        A1        SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      145.10      m3      2      3.00    1296 0      76      11027.6      0      0
  total direct cost =labor+material+equipment+s/c23987.6
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      145.1      m3      1      2      3140      560      81256      0      50      7255
  total direct cost =labor+material+equipment+s/c91651.0
           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  DC
      150      150      310      m3      2      2      600      30      9300      0      5280
  total direct cost =labor+material+equipment+s/c15180.0
total pc footing cost zone G =130,818.6

334

  ZONE(G) _ RC footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      297.33      m3      2      5.00    2160 0      76      22597.08      0      0
  total direct cost =labor+material+equipment+s/c44197.1
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    20.15    Ton    2    4  1728 0    9800    197470    0    0
  total direct cost =labor+material+equipment+s/c214750.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      297.33      m3      2      2      6280      560      166504.8      0      50    14866. 5

335

  total direct cost =labor+material+equipment+s/c187651.3
           ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
      270      70      511.92      m2      2      4      2160      15      7678.8      0      0      0
  total direct cost =labor+material+equipment+s/c9838.8
           BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  DC
      150      150      1051      m3      2      4      1200      30      31530      0      10560
  total direct cost =labor+material+equipment+s/c43290.0
total Rc footing cost zone G =499,727.2
  ZONE(G) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
   SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C

336

        2160.00      80.00      202.40      m3      1      3.00      6480      88      17811.2      0      0
  total direct cost =labor+material+equipment+s/c24291.2
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    28.3    m3    1    3    6480    9800    277340    0    0
  total direct cost =labor+material+equipment+s/c283820.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      202.40      m3      1      2      2180      560    113344.0 0      0      50      10120
  total direct cost =labor+material+equipment+s/c125644.0
         Membrane  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    394.25    M2    1    10    2700    60    23655    0    0
  total direct cost =labor+material+equipment+s/c26355.0
   BACKFILLING  labor  material  S/C  equipment

337

  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    788.5    M3    1    6    900    30    23655    0    2640    15840
  total direct cost =labor+material+equipment+s/c40395.0
total =500505.2
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      202.40      m3      1      3.00      6480      88      17811.2      0      0
  total direct cost =labor+material+equipment+s/c24291.2
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    28.3    m3    1    3    6480    9800    277340    0    0
  total direct cost =labor+material+equipment+s/c283820.0
     PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C

338

        1090      150      202.40      m3      1      2      2180      560    113344.0 0      0      50      10120
  total direct cost =labor+material+equipment+s/c125644.0
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    394.25    M2    1    10    2700    60    23655    0    0
  total direct cost =labor+material+equipment+s/c26355.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    788.5    M3    1    6    900    30    23655    0    2640    15840
  total direct cost =labor+material+equipment+s/c40395.0
total =500505.2
  Total RW zone G  1,001,010.4
  ZONE(G) _ COLUMN
LOWER BASEMENT
  Code  Work Type  Calculations

339

   
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      74.50      m3      1      3.00      6480      82      6109      0      0
  total direct cost =labor+material+equipment+s/c12589.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      74.5      m3      1      2      2180      560      41720      0      50      3725
  total direct cost =labor+material+equipment+s/c47625.0
total =123334.0
UPPER BASEMENT
     Work Type    Calculations

340

  labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      33.00      m3      1      2.00      4320      82      2706      0      0
  total direct cost =labor+material+equipment+s/c7026.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      33      m3      1      1      1090      560      18480      0      50      1650
  total direct cost =labor+material+equipment+s/c21220.0
total =91366.0
GROUND FLOOR
     Work Type    Calculations

341

  labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      30.00      m3      1      1.00      2160      82      2460      0      0
  total direct cost =labor+material+equipment+s/c4620.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      30      m3      1      1      1090      560      16800      0      50      1500
  total direct cost =labor+material+equipment+s/c19390.0
total =87130.0
REPETITIVE FLOOR
     Work Type    Calculations

342

  labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      30.00      m3      1      1.00      2160      82      2460      0      0
  total direct cost =labor+material+equipment+s/c4620.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    6    m3    1    2    4320    9800    58800    0    0
  total direct cost =labor+material+equipment+s/c63120.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      30      m3      1      1      1090      560      16800      0      50      1500
  total direct cost =labor+material+equipment+s/c19390.0
total =87130.0
total column cost zone G =563,220.0
  ZONE(G) _ SLABS
LOWER BASEMENT

343

      Code      Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      483.60      m3      2      9.00    3888 0      95      45942      0      0
  total direct cost =labor+material+equipment+s/c84822.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    51.64    m3    2    6  2592 0    9800    506072    0    0
  total direct cost =labor+material+equipment+s/c531992.0
           PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      483.60      m3      2      2      6920      560      270816      0      50      24180
  total direct cost =labor+material+equipment+s/c301916.0
total =918730.0
UPPER BASEMENT
 Work TypeCalculations

344

   
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      510.00      m3      2      9.00    3888 0      95      48450      0      0
  total direct cost =labor+material+equipment+s/c87330.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    52.3    m3    2    6  2592 0    9800    512540    0    0
  total direct cost =labor+material+equipment+s/c538460.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      510.00      m3      2      2      6920      560      285600      0      50      25500
  total direct cost =labor+material+equipment+s/c318020.0
total =943810.0
SOG
  Code  Work Type  Calculations

345

   
labormaterialS/Cequipment
         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      956.80      M3      1      7      1050      30      28704      0      2640      18480
  total direct cost =labor+material+equipment+s/c48234.0
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      0.99      TON      1      1      540      9800      9682.4      0      0
  total direct cost =labor+material+equipment+s/c10222.4
       PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
    640.00    100.00    318.90    M3    1    4    2560    560    178584    050/M3    20745
1200/da y
  total direct cost =labor+material+equipment+s/c201889.0
total =260345.4
GROUND FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
   SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C

346

        2160.00      30.00      131.60      m3      1      5.00    1080 0      95      12502      0      0
  total direct cost =labor+material+equipment+s/c23302.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    16.5    m3    1    4    8640    9800    161700    0    0
  total direct cost =labor+material+equipment+s/c170340.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      131.60      m3      1      1      1730      560      73696      0      50      6580
  total direct cost =labor+material+equipment+s/c82006.0
total =275648.0
REPETITIVE FLOOR
       Work Type    Calculations
labormaterialS/Cequipment
   SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C

347

        2160.00      30.00      131.60      m3      1      5.00    1080 0      95      12502      0      0
  total direct cost =labor+material+equipment+s/c23302.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    16.5    m3    1    4    8640    9800    161700    0    0
  total direct cost =labor+material+equipment+s/c170340.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      131.60      m3      1      1      1730      560      73696      0      50      6580
  total direct cost =labor+material+equipment+s/c82006.0
total =275648.0
           Elec. Empty ConduitslabormaterialS/Cequipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  172480      0      0

348

  total direct cost =labor+material+equipment+s/c172,480.0
total slabs cost zone G3,397,957.4
  ZONE(G) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
      540.00      3000.00      1710.00      Brick      1      1      540      1.096      1874.16      0      0
  total direct cost =labor+material+equipment+s/c2414.2
total =2414.2
TOTAL COST OF ZONE (G)5,595,147.7
ZONE (H)
  ZONE(H) _ pc footing
 
      Code      Work Type    Calculations
labormaterialS/Cequipment
  A1  SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C

349

        2160.00      30.00      165.90      m3      2      3.00    1296 0      76      12608.4      0      0
  total direct cost =labor+material+equipment+s/c25568.4
          A2          PLACING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      165.9      m3      1      2      3140      560      92904      0      50      8295
  total direct cost =labor+material+equipment+s/c104339.0
           BACKFILLING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/m3  D.C  D.C  DC
      150      150      361      m3      2      2      600      30      10830      0      5280
  total direct cost =labor+material+equipment+s/c16710.0
total pc footing cost zone H  =146,617.4
  ZONE(H) _ RC footing
 
  Code  Work Type  Calculations

350

   
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      421.74      m3      2      8.00    3456 0      76      32052.24      0      0
  total direct cost =labor+material+equipment+s/c66612.2
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    15.09    Ton    2    3  1296 0    9800    147882    0    0
  total direct cost =labor+material+equipment+s/c160842.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1570      100      421.74      m3      2      3      9420      560      236174.4      0      50      21087
  total direct cost =labor+material+equipment+s/c266681.4
       ISOLATIONlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.Cpump cost/m3  D.C
  270  70  590.74  m2  2  5  2700  15  8861.1  0  0  0

351

              
  total direct cost =labor+material+equipment+s/c11561.1
           BACKFILLING  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/m3  D.C  D.C  DC
      150      150      997      m3      2      4      1200      30      29910      0      10560
  total direct cost =labor+material+equipment+s/c41670.0
total Rc footing cost zone H =547,366.7
  ZONE(H) _ RETAINING WALL
LOWER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      129.25      m3      1      2.00      4320      88      11374      0      0
  total direct cost =labor+material+equipment+s/c15694.0

352

         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    15.4    m3    1    2    4320    9800    150920    0    0
  total direct cost =labor+material+equipment+s/c155240.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      129.25      m3      1      1      1090      560      72380.00      0      50      6462.5
  total direct cost =labor+material+equipment+s/c79932.5
         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    369.35    M2    1    10    2700    60    22161    0    0
  total direct cost =labor+material+equipment+s/c24861.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    738.7    M3    1    5    750    30    22161    0    2640    13200
  total direct cost =labor+material+equipment+s/c36111.0

353

total =311838.5
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      80.00      129.25      m3      1      2.00      4320      88      11374      0      0
  total direct cost =labor+material+equipment+s/c15694.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    10    15.4    m3    1    2    4320    9800    150920    0    0
  total direct cost =labor+material+equipment+s/c155240.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      150      129.25      m3      1      1      1090      560      72380.00      0      50      6462.5
  total direct cost =labor+material+equipment+s/c79932.5

354

         MembranelabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M2  D.C  D.C  D.C
    270    40    369.35    M2    1    10    2700    60    22161    0    0
  total direct cost =labor+material+equipment+s/c24861.0
         BACKFILLINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/M3  D.C
    150    150    738.7    M3    1    5    750    30    22161    0    2640    13200
  total direct cost =labor+material+equipment+s/c36111.0
total =311838.5
  Total RW zone H  623,677.0
  ZONE(H) _ COLUMN
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment
     SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
  2160.00  30.00  70.00  m3  1  3.00  6480  82  5740  0  0

355

             
  total direct cost =labor+material+equipment+s/c12220.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    11    m3    1    4    8640    9800    107800    0    0
  total direct cost =labor+material+equipment+s/c116440.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      70      m3      1      2      2180      560      39200      0      50      3500
  total direct cost =labor+material+equipment+s/c44880.0
total =173540.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment
     SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
  2160.00  30.00  70.00  m3  1  3.00  6480  82  5740  0  0

356

             
  total direct cost =labor+material+equipment+s/c12220.0
         FIXING STEEL  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    3.2    11    m3    1    4    8640    9800    107800    0    0
  total direct cost =labor+material+equipment+s/c116440.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1090      50      70      m3      1      2      2180      560      39200      0      50      3500
  total direct cost =labor+material+equipment+s/c44880.0
total =173540.0
total column cost zone H =347,080.0
  ZONE(H) _SLAB
LOWER BASEMENT
      Code      Work Type    Calculations
labormaterialS/Cequipment

357

         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      490.60      m3      2      9.00    3888 0      95      46607      0      0
  total direct cost =labor+material+equipment+s/c85487.0
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    50.8    m3    2    6  2592 0    9800    497840    0    0
  total direct cost =labor+material+equipment+s/c523760.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      490.60      m3      2      2      6920      560      274736      0      50      24530
  total direct cost =labor+material+equipment+s/c306186.0
total =915433.0
UPPER BASEMENT
       Work Type    Calculations
labormaterialS/Cequipment

358

         SHUTTERINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      2160.00      30.00      511.90      m3      2      9.00    3888 0      95      48630.5      0      0
  total direct cost =labor+material+equipment+s/c87510.5
         FIXING STEELlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/ton  D.C  D.C  D.C
    2160    4.5    50.8    m3    2    6  2592 0    9800    497840    0    0
  total direct cost =labor+material+equipment+s/c523760.0
           PLACINGlabormaterialS/Cequipment
labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      1730      150      511.90      m3      2      2      6920      560      286664      0      50      25595
  total direct cost =labor+material+equipment+s/c319179.0
total =930449.5
SOG
      Code      Work Type    Calculations
labormaterialS/Cequipment

359

         FILLING TO SOGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE/day  D.C
      150.00      150.00      983.25      M3      1      7      1050      30      29497.5      0      2640      18480
  total direct cost =labor+material+equipment+s/c49027.5
         STEEL FIXINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  D.C
      540.00      2.00      1.02      TON      1      1      540      9800      9956.8      0      0
  total direct cost =labor+material+equipment+s/c10496.8
         PLACINGlabor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.C  LE/M3  D.C  D.C  LE  D.C
      640.00      100.00      327.75      M3      1      4      2560      560      183540      050/M3    21187. 5
  1200/da y
  total direct cost =labor+material+equipment+s/c207287.5
total =266811.8
           Elec. Empty Conduits  labor  material  S/C  equipment
labor crew cost/daypro.rat equantit yunit eno.of crewduratio n  D.C  LE/M3  D.C  D.Cpump cost/m3  D.C
      0      0      0.00                 0      0      0      0      0.00  73920      0      0

360

  total direct cost =labor+material+equipment+s/c73,920.0
total slabs cost zone H2,186,614.3
  ZONE(H) _ BRICKS
      Code      Work Type    Calculations
labormaterialS/Cequipment
  labor crew cost/daypro.rat equantit y  unitno.of crewduratio n  D.CLE/bric k  D.C  D.C  D.C
      540.00      3000.00      7062.00      Brick      1      3      1620      1.096      7739.952      0      0
  total direct cost =labor+material+equipment+s/c9360.0
total =9360.0
TOTAL COST OF ZONE (H)3,860,715.4

6.5. TOTAL DIRECT COST:

6.5.1. Direct Cost of working items:

   T.D.C  T.Q  cost/unit
  PC footing  1,394,607.5  1626.25  857.6
  RC footing  4,459,154.3  2789.38  1,598.6
  RWs  5,300,153.4  1924  2,754.8
  Columns  7,241,369.2  2852.73  2,538.4
  Slabs  29,750,083.9  12831.55  2,318.5
  Bricks  55,236.1  36715.00  1.5
  Total  48,200,604.3  22,023.9 

6.5.2. Direct cost of resource:

   LABOR  MATERIAL  S/C  EQUIPMENT  Total
    COST    3,562,730    41,602,604    1,281,280.0    1,753,991  48,200,604
    %    7.4%    86.3%    2.7%    3.6%    100.0%

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top