EOT(Extension of Time) claim process involves following steps

EOT(Extension of Time) claim process involves following steps

๐—˜๐—ข๐—ง (๐—˜๐˜…๐˜๐—ฒ๐—ป๐˜€๐—ถ๐—ผ๐—ป ๐—ผ๐—ณ ๐—ง๐—ถ๐—บ๐—ฒ) ๐—ฐ๐—น๐—ฎ๐—ถ๐—บ ๐—ฝ๐—ฟ๐—ผ๐—ฐ๐—ฒ๐˜€๐˜€ involves several steps to properly document and justify the need for an extension to the project completion date.

Here’s a general outline of the EOT claim process:

๐Ÿญ. ๐—œ๐—ฑ๐—ฒ๐—ป๐˜๐—ถ๐—ณ๐—ถ๐—ฐ๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—ผ๐—ณ ๐——๐—ฒ๐—น๐—ฎ๐˜† ๐—˜๐˜ƒ๐—ฒ๐—ป๐˜๐˜€:
โ€ข Identify and document all events or circumstances that have caused delays to the project schedule. These could include weather delays, design changes, unforeseen site conditions, delays by other contractors, etc.

๐Ÿฎ. ๐——๐—ผ๐—ฐ๐˜‚๐—บ๐—ฒ๐—ป๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—š๐—ฎ๐˜๐—ต๐—ฒ๐—ฟ๐—ถ๐—ป๐—ด:
โ€ข Collect all relevant documentation to support the claim, such as:
โ€ข Project schedules (baseline and updated)
โ€ข Daily progress reports
โ€ข Correspondence (letters, emails, meeting minutes) related to delays
โ€ข Change orders or variations
โ€ข Site diaries or logs
โ€ข Weather reports or other external factors affecting progress

๐Ÿฏ. ๐—”๐—ป๐—ฎ๐—น๐˜†๐˜€๐—ถ๐˜€ ๐—ผ๐—ณ ๐——๐—ฒ๐—น๐—ฎ๐˜† ๐—œ๐—บ๐—ฝ๐—ฎ๐—ฐ๐˜:
โ€ข Assess the impact of each delay event on the project schedule, considering its duration, criticality, and any associated ripple effects on subsequent activities.

๐Ÿฐ. ๐—ฃ๐—ฟ๐—ฒ๐—ฝ๐—ฎ๐—ฟ๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—ผ๐—ณ ๐—˜๐—ข๐—ง ๐—–๐—น๐—ฎ๐—ถ๐—บ ๐——๐—ผ๐—ฐ๐˜‚๐—บ๐—ฒ๐—ป๐˜:
โ€ข Prepare a comprehensive EOT claim document outlining the reasons for the delay, the impact on the project schedule, and the justification for an extension of time.
โ€ข Include a clear narrative describing each delay event, its causes, and its effects on the project timeline.
โ€ข Provide supporting documentation for each delay event to substantiate the claim.

๐Ÿฑ. ๐—ค๐˜‚๐—ฎ๐—ป๐˜๐—ถ๐—ณ๐—ถ๐—ฐ๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—ผ๐—ณ ๐—ง๐—ถ๐—บ๐—ฒ ๐—˜๐˜…๐˜๐—ฒ๐—ป๐˜€๐—ถ๐—ผ๐—ป:
โ€ข Quantify the amount of additional time required to complete the project, taking into account all delay events and their cumulative impact on the schedule.
โ€ข Calculate the total extension of time sought and propose a revised completion date.

๐Ÿฒ. ๐—ฅ๐—ฒ๐˜ƒ๐—ถ๐—ฒ๐˜„ ๐—ฎ๐—ป๐—ฑ ๐—”๐—ฝ๐—ฝ๐—ฟ๐—ผ๐˜ƒ๐—ฎ๐—น:
โ€ขSubmit the EOT claim document to the appropriate parties for review and approval, typically including the client, main contractor, and any other relevant stakeholders.
โ€ข Allow for a period of negotiation and discussion to resolve any disagreements or disputes regarding the claim.

๐Ÿณ. ๐—™๐—ผ๐—ฟ๐—บ๐—ฎ๐—น ๐——๐—ผ๐—ฐ๐˜‚๐—บ๐—ฒ๐—ป๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป:
โ€ข Once approved, formalize the extension of time by issuing a Variation Order or Change Order, amending the contract to reflect the revised completion date.

๐Ÿด. ๐—œ๐—บ๐—ฝ๐—น๐—ฒ๐—บ๐—ฒ๐—ป๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—ฎ๐—ป๐—ฑ ๐— ๐—ผ๐—ป๐—ถ๐˜๐—ผ๐—ฟ๐—ถ๐—ป๐—ด:
โ€ข Update project schedules and other relevant documentation to reflect the approved extension of time.
โ€ข Monitor progress against the revised schedule to ensure that the project remains on track to meet the new completion date.

Throughout the EOT claim process, clear communication, documentation, and adherence to contractual requirements are essential to ensure a fair and successful resolution of project delays.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top