Undertaking for law height form work for slab above ettic slab (0.7m   height) and pool deck

Undertaking letter

Date: xxx Ref no: xxx To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub               : Undertaking for law height form work for slab above ettic slab (0.7m   height) and pool deck. Dear Sir, With reference to the above, we are hereby undertaking that our formwork for 0.7m height slab above ettic slab… Continue reading Undertaking for law height form work for slab above ettic slab (0.7m   height) and pool deck

Submission of the proposal to close the distribution pump opening in PT slab

Shop Drawing

Date: xxx Ref no: xxx To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub                : Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor Dear Sir, With reference to the above, we are hereby submitting the proposal and approval by… Continue reading Submission of the proposal to close the distribution pump opening in PT slab

Incident Report and Documents Submission

delivery of Tiles and cheque copy.

Date: xxx Ref no: xxx To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub            :   Incident Report and Documents Submission Dear Sir, With reference to the above, we are submitting all the required documents as per your instructions and as per your list provided as follows: 1. Building Permit  / Affection Plan… Continue reading Incident Report and Documents Submission

Undertaking letter by Main contractor for structural safety /building safety as  required in application no:xxx.

Undertaking letter

Date: xxx Ref no: xxx To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub      :  Undertaking letter by Main contractor for structural safety /building    safety as  required in application no:xxx. Dear Sir, With reference to the above, we the main contractor M/s xxx contracting LLC , PO Box:xxx, Tel: 04-xxx,  are confirming… Continue reading Undertaking letter by Main contractor for structural safety /building safety as  required in application no:xxx.

Engineers are ready for training required for xxx Contracting L.L.C License no: xxx

shake-up-sales-meeting

Date: xxx Ref no: xxx To The Manager, DM Qualification Section (License) Dubai Municipality, Dubai UAE Sub:  Engineers are ready for training required for xxx Contracting L.L.C License no: xxx Dear Sir, With ref. to above and requirement our engineers are ready to take the training immediately with your appointment. So, kindly provide immediate appointment… Continue reading Engineers are ready for training required for xxx Contracting L.L.C License no: xxx

Request to arrange materials

structural-shop-drawing

Date: xxx Ref. xxx To       :              M/s xxx Gulf Project:              2B + G + 14 + Lower Roof Hotels Building, Plot No. xxx at Al Barsha 1st, Dubai Subject:             Request to arrange materials Dear Mr.Jaseem, With ref. to above, we would like to inform that the painting workers are suffering today at site because… Continue reading Request to arrange materials

Regarding discrepancies in number of bar per column cannot be accommodated and need to redesign

Date:               xxx Ref:                 xxx To:                     xxx Engineering Consultancies Kind Attn:       Dr. xxx Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha  1st, Dubai U.A.E Subject:     Regarding discrepancies in number of bar per column cannot be             accommodated and need to redesign Dear Mr. Abdur Rahman,… Continue reading Regarding discrepancies in number of bar per column cannot be accommodated and need to redesign

Regarding query for beam jacketing at site

Date:               xxx Ref:                 xxx To:                     xxx Engineering Consultancies Kind Attn:       Dr. xxx Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha  1st, Dubai U.A.E Subject:           Regarding query for beam jacketing at site   Dear Sir, With ref. to above kindly confirm, the 10mm anchor… Continue reading Regarding query for beam jacketing at site

Structural Guarantee of the beam jacketing

Date:               xxx Ref:                 xxx To:                     xxx Engineering Consultancies Kind Attn:       Dr. xxx Project:           2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha  1st, Dubai U.A.E Subject:           Structural Guarantee of the beam jacketing Dear Mr. Abdur Rahman, We are attaching the required concrete quantity and Beams… Continue reading Structural Guarantee of the beam jacketing

our continuous follow up for the nomination issued by the client for Electronic door lock and our concerned

awaiting-response

Date                : xxx Ref                   : xxx To                    : M/S xxx xxx Hospitality Project            : 2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai U.A.E Subject          : Regarding our continuous follow up for the nomination issued by the client for Electronic door lock and our concerned Dear… Continue reading our continuous follow up for the nomination issued by the client for Electronic door lock and our concerned