Reply - Notice of Delay

Response to Contractor’s allegations of delay

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Response to Contractor’s allegations of delay References: a) xxx dated 21 June xxx                       b) xxx dated 06 July xxx                     […]

Response to Contractor’s allegations of delay Read Post »

Materials at site

Notice of Delay in delivery of materials.

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Notice of Delay in delivery of materials. Dear Sir, We are writing to raise our deep concerns about the delivery of

Notice of Delay in delivery of materials. Read Post »

delivery-delay

Response to notice of delay in delivery and installation of pods

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Response to notice of delay in delivery and installation of pods References: a) xxx dated 21 June xxx                       b) xxx

Response to notice of delay in delivery and installation of pods Read Post »

Sanitary Accessories

Updates on the delivery of tiles sanitary wares & accessories

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Updates on the delivery of tiles, sanitary wares & accessories References: a) xxx dated 21 June xxx                       b) xxx dated

Updates on the delivery of tiles sanitary wares & accessories Read Post »

Compliance Visit Report

Response to Notice of QHSE Violation

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Response to Notice of QHSE Violation Dear Sir, We are in receipt of your letter ref: xxx dated 12 September xxx

Response to Notice of QHSE Violation Read Post »

Engineer's Instruction

Rejection to allegations of delay

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Rejection to allegations of delay References: a) xxx dated 21 June xxx                       b) xxx dated 06 July xxx                       Dear

Rejection to allegations of delay Read Post »

Notification of Variation

NOTIFICATION OF VARIATION CLAIM

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     NOTIFICATION OF VARIATION CLAIM Reference: a) xxx dated 18 August xxx                     b) Email for the Minutes of Meeting held on

NOTIFICATION OF VARIATION CLAIM Read Post »

Project Work Program

Program for the installation of pods in xxx 4

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Program for the installation of pods in xxx 4 References: a) xxx dated 21 June xxx                       b) xxx dated 07

Program for the installation of pods in xxx 4 Read Post »

Variation notification

Rejection to Notice of Delay

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Rejection to Notice of Delay References: a) xxx dated 21 June xxxx                       b) xxx dated 06 July xxxx                       c)

Rejection to Notice of Delay Read Post »

Shaver Sockets & Light Fittings

Light switch Access Panel CDP Electrical Junction Box and Manifold locations

Our Ref: xxx Date: xxx To                           : xxx Contracting Company LLC                                P. O. Box xxx, Dubai, U.A.E. Attention            : Mr. xxx, Senior Project Manager Project                 : xxx Tower, Dubai – U.A.E. Subject :     Light switch, Access Panel, CDP, Electrical Junction Box and Manifold locations Reference: a) xxx dated 18 August xxxx                     b) Email

Light switch Access Panel CDP Electrical Junction Box and Manifold locations Read Post »