Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Variation notification

Notification of Claims

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Notification of Claims Dear Sir, Further to our Subcontract Agreement reference xxx dated 11th November xxx and to the recently received […]

Notification of Claims Read Post »

Undertaking letter

Undertaking for NCN Nos. 197 and 203

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Undertaking for NCN Nos. 197 and 203 Dear Sir, Further to the NCN Nos. 197

Undertaking for NCN Nos. 197 and 203 Read Post »

Contract Documents

Contract No. to be followed

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Contract No. to be followed Dear Sir, We are in receipt of ASCON’s letter reference

Contract No. to be followed Read Post »

Engineer's Instruction

Release of Outstanding Payments

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Release of Outstanding Payments Dear Sir, With reference to the subject and our Final Account

Release of Outstanding Payments Read Post »

Engineer's Instruction

Final Accounts for Original Contract Works

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Final Accounts for Original Contract Works Dear Sir, We refer to the exchanges of emails

Final Accounts for Original Contract Works Read Post »

Notice of Delay in Payments

Delay Notice for Project Completion

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Delay Notice for Project Completion Dear Sir, We acknowledge receipt of your letter reference xxx

Delay Notice for Project Completion Read Post »

False Ceiling

Additional Works – 50mm x 50mm Bulkhead

M/s xxx Construction & Investment Co. L.L.C. P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Mr. xxx                             Operations – Operations                            Project            :  (G+7F) xxx Apartment Consultant    :  xxx Engineering Consultants Subject:           Additional Works – 50mm x 50mm Bulkhead Dear Sir, We refer to the payment application