Author name: Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

advance payment

Payment Status

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Payment Status Dear Sir, We refer to your letter reference xxx dated 10th August xxx regarding the pending Engineer’s Instruction for […]

Payment Status Read Post »

Marble Vanity Top

Variation in Granite Top

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Variation in Granite Top Dear Sir, We refer to our letter reference xxx site dated 13th August xxx and to your

Variation in Granite Top Read Post »

METHOD STATEMENT WATER SUPPLY WORK

Damage of Pex Pipes in Cluster G-12

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Damage of Pex Pipes in Cluster G-12 Dear Sir, We are in receipt of your letter reference xxx dated 13th August

Damage of Pex Pipes in Cluster G-12 Read Post »

fixing doors

Damages to Joinery Works

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Damages to Joinery Works Dear Sir, We are in receipt of your letter reference xxx dated 18th August xxx in response

Damages to Joinery Works Read Post »

Door Frame installation

Damages to Joinery Works

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Damages to Joinery Works Dear Sir, We would like to draw your attention to the continuous damages being done on the

Damages to Joinery Works Read Post »

Slow Progress of Subcontract Works – Carpentry & Joinery

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Slow Progress of Subcontract Works – Carpentry & Joinery Dear Sir, Further to our letter reference xxx dated 28th July xxx

Slow Progress of Subcontract Works – Carpentry & Joinery Read Post »

Engineer's Instruction

Delay Notice: Slow Progress of Kitchen Cabinets and Wardrobes Subcontract

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Delay Notice: Slow Progress of Kitchen Cabinets and WardrobesSubcontract Dear Sir, We acknowledge receipt of your letter reference xxx dated 3rd

Delay Notice: Slow Progress of Kitchen Cabinets and Wardrobes Subcontract Read Post »

Slow Progress of Subcontract Works – Carpentry & Joinery

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Slow Progress of Subcontract Works – Carpentry & Joinery Dear Sir, We are in receipt of your letter reference xxx dated

Slow Progress of Subcontract Works – Carpentry & Joinery Read Post »

Kitchen Cabinet

Delay Notice: Slow Progress of Kitchen Cabinets and Wardrobes Subcontract

M/s xxx Building Contracting LLC        PO Box xxx, Dubai, U.A.E T: xxx | F: xxx Email: xxx Attention        :   MR. xxx     Project Manager  Project         :   xxx Sky Tower – Umm Ramool Subject        :   Delay Notice: Slow Progress of Kitchen Cabinets and WardrobesSubcontract Dear Sir, We are in receipt of your letter reference xxx dated

Delay Notice: Slow Progress of Kitchen Cabinets and Wardrobes Subcontract Read Post »