Notification of Variation

Variations for Reception Counter – Additional Costs

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Variations for Reception Counter – Additional Costs Dear Sir, We refer to the recent requirements by the Client to change the […]

Variations for Reception Counter – Additional Costs Read Post »

Variation Order Request

Variations – Additional Costs

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Variations – Additional Costs References:        Dear Sir, We refer to the above-mentioned letters regarding our submitted Variations, please be informed that

Variations – Additional Costs Read Post »

Payment Terms

Payment Status

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject            :  Payment Status Dear Sir, We refer to our submitted Payment Application No. 1 & Payment Application No. 2 for Clusters G-11,

Payment Status Read Post »

Undertaking Letter

Notice of Claim for Extension of Time

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject:         Notice of Claim for Extension of Time Dear Sir, Further to our Work Order reference xxx dated 23rd June xxx regarding

Notice of Claim for Extension of Time Read Post »

advance payment

Payment Status

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Payment Status References:        Dear Sir, We refer to our submitted Payment Application No. 1 & Payment Application No. 2 for Clusters

Payment Status Read Post »

Running Cost

Variation Approval for Additional Costs

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Variation Approval for Additional Costs References:   Dear Sir, We refer to our submitted variation costs for the above referred project references

Variation Approval for Additional Costs Read Post »

Wild Air for the Building

Absence of Wild Air

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Absence of Wild Air Dear Sir, We refer to our Work Order reference xxx dated 23rd June xxx regarding the above

Absence of Wild Air Read Post »

Notification of Variation

Additional Costs – Joinery Works – VO #3

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Additional Costs – Joinery Works – VO #3 Dear Sir, We refer to our letter reference xxx dated 20th August xxx

Additional Costs – Joinery Works – VO #3 Read Post »

Variation notification

Notice of Claim – Joinery Works – VO #3

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Notice of Claim – Joinery Works – VO #3 Dear Sir, We refer to the comments made on our submitted shop

Notice of Claim – Joinery Works – VO #3 Read Post »

fixing the floor tile

Additional Costs – Marble Cream Crystal

M/s xxx Properties LLC P.O. Box xxx, Dubai, U.A.E.                                 Tel: xxx Fax: xxx Attention        :   Engr. xxx                             Project Manager                              Project            :  (G+7F) xxx Apartment – Civil Works Subject           :  Additional Costs – Marble Cream Crystal Dear Sir, We refer to our letter reference xxx dated 17th August xxx regarding our

Additional Costs – Marble Cream Crystal Read Post »