This package includes following:
- Construction Programme or Baseline Programme in xer file format.
Project Duration: 18 Months including one Month Mobilization.
Detailed L4 construction with Cost, Manpower, and plant & equipment loaded for a GF + 4 Floors + Lower Roof Residential Building. Sequence follow for the Programme. Following are the high level WBS details. It’s very details Programme.
- LOA, Contract agreement, NOC, concerned authorities approved Drawing and Consultant letter to commence work at site prior to commencement of the Project.
- Engineering Submission and Approval.
- Internal Subcontractor Pre-qualification Submission and approval
- Provisional Sum (PS) items Subcontractor and Supplier nomination and issuance of Subcontract agreement and LPO
- Prime Cost (PC) items Subcontractor and Supplier nomination and issuance of Subcontract agreement and LPO
- Substructure, super Structure and finishes items Materials, Technical data Sheet and Sample Tag submission and Approval.
- Provisional Sum items Materials, Technical data Sheet and Sample Tag submission and Approval.
- Prime Cost items Materials, Technical data Sheet and Sample Tag submission and Approval.
- Shop Drawing Submission and Approval.
- General Shop drawing
- Architectural Shop drawing
- Structural Shop drawing
- Finishes Shop drawing
- Builders works Shop drawing
- Power and Lighting Shop drawing (wall , Floor and High level)
- Water Supply Shop drawing
- Drainage Shop drawing
- HVAC Drawing Shop drawing
- ELV and Home Automation Shop drawing
- Fire Fighting Shop drawing
- Fire Alarm Shop drawing
- Coordination Shop drawing Shop drawing
- RCP Shop drawing
- Provisional Sum items Shop drawing
- Engineering Procurements
- Civil Long lead items
- MEP Long lead items
- Provisional Sum Long lead items
- Prime Cost Long lead items
- Construction works.
- Civil Works
- Sub Structure
- Super Structure
- Finishes
- Internal Finishes
- External Finishes
- MEP Works
- MEP internal Works
- Electrical Power and Lighting
- Home Automation and ELV works
- Water Supply and Drainage works
- HVAC Works
- Fire Fighting and Fire Alarm works
- MEP External Works
- MEP internal Works
- Substantial Completion
- Authority Approval
- Snagging and De Snagging
- Testing and Commissioning
- Civil Works
Handover project to the Client
Reviews
There are no reviews yet.