RE- Compliance to NCR & site instructions
Our Ref: xxx Date: xxx To : xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : RE- Compliance to NCR & site instructions References : a) xxx dated 11 March xxxx b) xxx dated 15 December xxxx Dear Sir, We are […]
RE- Compliance to Consultant issued snagging comments for first floor
Our Ref: xxx Date: xxx To xxx Contracting Company LLC P. O. Box xxx, Dubai, U.A.E. Attention : Mr. xxx, Senior Project Manager Project : xxx Tower, Dubai – U.A.E. Subject : RE- Compliance to Consultant issued snagging comments for first floor References : a) UP-1763/LET-1373-21/LS-at dated 29 September xxx b) xxxdated 11 March xxx Dear Sir, We are […]