Warranties and Operating & Maintenance Manuals

The Engineer’s comments on draft warranty

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Project                 : MH-0080 Port de la Mer Phase 1 (plot 2), Dubai Subject :     The Engineer’s comments on draft warranty Dear Sir, We are […]

The Engineer’s comments on draft warranty Read Post »

Warranties and Operating & Maintenance Manuals

Response to Notice of Delay – Submission to Operation & Maintenance Manual

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Project                 : MH-0080 Port de la Mer Phase 1 (plot 2), Dubai Subject :     Response to Notice of Delay – Submission to Operation &

Response to Notice of Delay – Submission to Operation & Maintenance Manual Read Post »

report

Rejection of “DB live test” Testing & Commissioning at B5 level 5 – Incomplete installation of bathrooms pods.

                     installation of bathrooms pods. Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Project                 : MH-0080 Port de la Mer Phase 1 (plot 2), Dubai Subject :     Rejection of “DB live test”

Rejection of “DB live test” Testing & Commissioning at B5 level 5 – Incomplete installation of bathrooms pods. Read Post »

report

Snagging Report for Flat 110

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Project                 : MH-0080 Port de la Mer Phase 1 (plot 2), Dubai Subject                 : Snagging Report for Flat 110,201,202,203,204,205,206,207,208,209,210,211,212,213, 214,215,310,312,407,413,414,502,503,504,508,509,511,512,513,514,515,601,602,603,604,605,606,607 AND 609 in Building-1

Snagging Report for Flat 110 Read Post »

Snagging and De-snagging

Snagging Report for Flat 406 and 408 in Building-1

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Snagging Report for Flat 401,402,403,404,405,406 and 408 in Building-1 Dear Mr. Bahaa, Further to your letter Ref: xxx dated 04th May xxx

Snagging Report for Flat 406 and 408 in Building-1 Read Post »

delivery-delay

Response to Notice of Delay – Poor attendance for comments

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Response to Notice of Delay – Poor attendance for comments Dear Sir, We reject the content of your letter reference: xxx dated

Response to Notice of Delay – Poor attendance for comments Read Post »

COMMMMISSIONING CERTIFICATE

Notice of default in progress payment and short certification

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Notice of default in progress payment and short certification Dear Mr. Bahaa, We are writing to put on record that BHC has been

Notice of default in progress payment and short certification Read Post »

Claim rejected

Rejections of the Nominated Materials Supplier

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Rejections of the Nominated Materials Supplier Dear Sir, In response to your letter ref: xxx dated 2nd May xxx received on 4th

Rejections of the Nominated Materials Supplier Read Post »

Claim rejected

Rejections of the Nominated Supplier Materials

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Rejections of the Nominated Supplier Materials Dear Sir, We are writing you concerning the rejections of marble from the Nominated Supplier M/s

Rejections of the Nominated Supplier Materials Read Post »

delivery-delay

Response to Notice of Delay – POD Delivery

Our Ref:  xxx Date: xxx To                           : xxx Contracting LLC                                   P.O. Box xxx   Dubai, U. A. E. Attention            : Mr. xxx Project                 : xxx at Jumeirah First, Dubai Subject                 : Response to Notice of Delay – POD Delivery Dear Sir, In response to your letter reference: xxx dated 31st March xxx, we

Response to Notice of Delay – POD Delivery Read Post »