Notice of Delay – Pod marble works

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of Delay – Pod marble works Dear Sir, We refer to your letter reference xxx dated 11 May xxxx and respond as follows. We categorically reject […]

Notice of Delay – Pod marble works Read Post »

Engineer's Instruction

Notice of Delay in release of L/C Documents

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of Delay in release of L/C Documents References         : a) xxx dated 5th January xxxx                                b) xxx dated 27th January xxxx                                c) xxx dated

Notice of Delay in release of L/C Documents Read Post »

Notice of Delay in Payments

Notice of illegal use of Company stamp, logo & identity.

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of illegal use of Company stamp, logo & identity. Dear Sir, It has come to our attention that the Electronic stamp of M/s xxx (Contractor Name)

Notice of illegal use of Company stamp, logo & identity. Read Post »

Letter of Credit

Notice of Delay in release of L/C Documents

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Notice of Delay in release of L/C Documents References         : a) xxx dated 5th January xxxx                                b) xxx dated 27th January xxxx                                c) xxx dated

Notice of Delay in release of L/C Documents Read Post »

Project Work Program

Schedule for closing MIR comments

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Schedule for closing MIR comments References: a) BGC letter ref: xxx dated 08th February xxxx                       b) M/s xxx (Contractor Name) letter ref: xxx dated 21st December

Schedule for closing MIR comments Read Post »

Discrepancy

Discrepancy in Payment Certificates and Notice of Delay in release of LC Documents

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Discrepancy in Payment Certificates and Notice of Delay in release of LC Documents References         : a) xxx dated 5th January xxxx                                b) xxx dated 27th January

Discrepancy in Payment Certificates and Notice of Delay in release of LC Documents Read Post »

Tower Crane

Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B Dear Sir, We acknowledge the receipt of your letters xxx dated 31 January xxx &

Demobilization of Tower Crane TC-01 & TC-02 at Blocks A & B Read Post »

Marble Vanity Top

Pods Vanity Counter top & Cistern Top deviation against approved top material

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Pods Vanity Counter top & Cistern Top deviation against approved top material References         : Dear Sir, We refer to your letter ref: xxx dated 23 January xxxx

Pods Vanity Counter top & Cistern Top deviation against approved top material Read Post »

Approval and Finalization

Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : xxx Phase 2 Subject                 : Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals References         : Dear Sir, We refer to your letter ref: xxx dated 31 January

Response to allegations of delay in Delivery of PODs, MIR & WIR Approvals Read Post »