Pods Damaged by other at site

Damage Pod Type 1M

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Damage Pod Type 1M, BC# xxx, Building 3, level3, apartment 306. References:    a) xxx dated & issued on 6 July xxxx                           […]

Damage Pod Type 1M Read Post »

uploading bathroom Pod

Successful Completion of Pods Delivery

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Completion of Pods Delivery Dear Sir, We are writing to inform you that we have successfully completed on 28 August xxx the

Successful Completion of Pods Delivery Read Post »

Tiles and other Prime Cost items

Client’s directive to supply tiles for Phase 4 pods

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Client’s directive to supply tiles for Phase 4 pods Dear Sir, With reference to the attached Email received from M/s xxx Sahel

Client’s directive to supply tiles for Phase 4 pods Read Post »

Pod Delivery Schedule

Notice of pod damage (Pod Type 1M

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject                 : Notice of pod damage (Pod Type 1M, BC# xxx, Building 3, level3, apartment 316) References         : a) xxx dated 6 July xxx

Notice of pod damage (Pod Type 1M Read Post »

Pods Damaged by other at site

Notice of Misuse of Pods

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject                 : Notice of Misuse of Pods Dear Sir, We are writing to raise our deep concern to the misusage of pods from your

Notice of Misuse of Pods Read Post »

Response to Delay in Delivery of PODs

Response to Notice of Delay- Delivery of Bathrooms Pods.

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject                 : Response to Notice of Delay- Delivery of Bathrooms Pods. Dear Sir, We are extremely surprised to receive your notice of delay letter

Response to Notice of Delay- Delivery of Bathrooms Pods. Read Post »

Marble Vanity Top

Bianco Carrara Marble Inspection Request

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject                 : Bianco Carrara Marble Inspection Request Dear Sir, I’m writing to request for a slab inspection at M/s xxx AL Rokham located in

Bianco Carrara Marble Inspection Request Read Post »

Engineer's Instruction

Notice of Delay in the release of the retention (1st part)

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Notice of Delay in the release of the retention (1st part) Dear Sir, We refer to M/s xxx (Contractor Name) letter xxx

Notice of Delay in the release of the retention (1st part) Read Post »

Claim rejected

Rejection to the allegations of incomplete insulation works

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Rejection to the allegations of incomplete insulation works Dear Sir, We fundamentally object to the content of your letter reference xxx dated

Rejection to the allegations of incomplete insulation works Read Post »

advance payment

Notice of Delay in the release of the retention (1st part)

Our Ref: xxx Date: To xxx Contracting LLC P. O. Box xxx Dubai, U.A.E. Attention            : Mr. xxx, Group Procurement Manager Project                 : Design and Build of Coastal Village Residential Building. Subject :     Notice of Delay in the release of the retention (1st part) Dear Sir, In accordance with our Subcontract agreement ref: xxx, Appendix

Notice of Delay in the release of the retention (1st part) Read Post »