ACTIVITY HAZARD ANALYSIS Casting Blinding Concrete for Foundation Building Structures

ACTIVITY HAZARD ANALYSIS Casting Blinding Concrete for Foundation Building Structures

HAZARD / WORK: Casting Blinding Concrete for Foundation Building      Structures. LOCATION: ______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X […]

ACTIVITY HAZARD ANALYSIS Casting Blinding Concrete for Foundation Building Structures Read Post »

Building Footing

JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS Excavation and Foundation Preparation for Building Structures

Toolbox talks:-Manual HandlingCOSHHExcavationsNOISE Manual Handling We lift, manoeuvre and handle goods every day of our lives in one way or another, not just whilst at work but also during social activities such as gardening, DIY, shopping and sport. A bad back or injury today, could, and regularly does, turn into a painful back problem for

JOB HAZARD ANALYSIS TOOLBOX TALKS ATTACHMENTS Excavation and Foundation Preparation for Building Structures Read Post »

Building Footing

Method Statement for Excavation and Foundation Preparation for Building Structures

Table of Contents Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments   1.0       Purpose To ensure that all excavation and foundation preparation of building activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a

Method Statement for Excavation and Foundation Preparation for Building Structures Read Post »

Hazard Meaning and Definition

JOB HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures

  TASK: ­­­­­­­­Excavation and foundation preparation for Building Structures     Date:31st October 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Service location survey Manual handling operations (MHO’s) Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries Maximum use of equipment to reduce need

JOB HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures Read Post »

Risk Assessment Procedure Step wise Guide

ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures

HAZARD / WORK: Excavation and Foundation preparation For Building     Structures    LOCATION: ______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke    

ACTIVITY HAZARD ANALYSIS Excavation and Foundation preparation For Building Structures Read Post »

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

Method Statement for Backfilling of Box Culverts and Associated Structures

CONTENTS Purpose Scope of Work Definitions References Materials Plant  & Equipment Safety Prior Activities Procedure Responsibilities Attachments Purpose 1.1       To ensure that the backfilling of box culverts and associated structures (catch pits, access chambers, culvert outflow structures, transition manholes, etc.) is executed safely and in accordance with the contract requirements and that all quality assurance/

Method Statement for Backfilling of Box Culverts and Associated Structures Read Post »

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

JOB HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

The responsible person is to ensure the control measures below are in place before the activity is carried out   TASK: Backfilling of Box Culverts and Associated Structures     Date:14 October 2006 No ACTIVITY HAZARD RISK CONTROL MEASURES TO MINIMISE / ELIMINATE RISK RESPONSIBLE PERSON 1 Backfilling & Compaction Equipment falling into work area

JOB HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures Read Post »

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures

HAZARD / WORK: Backfilling of Box Culverts and Associated Structures LOCATION:______________________________________________ H=High                        M=Medium                   L=Low                                Significant Risks H M L   Who May Be Harmed 1 Work related upper limb disorders. Musculoskeletal injuries. Cuts, abrasions. Foot / toe injuries     X       2 Dehydration, heat exhaustion. Heat stroke     X   Employees……………………

ACTIVITY HAZARD ANALYSIS Backfilling of Box Culverts and Associated Structures Read Post »

Shop Drawing

Method Statement for Production of As-Built Drawings

As-built drawings are the most important documents in the construction process.  As-built drawings are usually the original design drawings revised to reflect any changes made in the field (e.g., design changes issued by change order and/or RFI, component relocations required for coordination, and rerouting of distribution systems).  All of these revisions will need prior approval

Method Statement for Production of As-Built Drawings Read Post »