This delay analysis documents were prepared to claim 216 calendar days extension of time to complete the project. Following Delay Events were impacted planned project completion.
SECTION 4 – LIST OF DELAY ANALYSIS WINDOWS
Window 1 – 16th November 2019 to 10th February 2020
- Delay in 1st Floor Slab Casting
Window 2 – 11Tth February 2020 to 9th March 2020
- Delay in issuance of HVAC design Drawing
Window 3 – 10th March 2020 to 18th May 2020
- Delay in issuance of revise ID Drawing
- Delay in issuance of Tiles supplier nomination
Window 4 – 19th May 2020 to 18th June 2020
- Delay in nomination of Swimming pool
- Delay due to newly issued IFC drawing
- Delay in nomination of wooden wardrobes
Window 5 – 19th June 2020 to 6th July 2020
- Delay in nomination of Sanitary ware supplier
- Delay in nomination of Kitchen Cabinet works subcontractor
- Delay in nomination of light fittings supplier
- Delay in nomination of custom-made wall featured works subcontractor
- Delay due to newly issued IFC Drawing
Window 6 – 7th July 2020 to 13th September 2020
- Delay due suspension notice for internal and external plaster
This delay analysis documents package includes following
- Narration of delay analysis technique and delay events
- Condition of Contract
- Substantiation of delay events
- Approved Baseline Programme
- Impacted Programme
Delay analysis technique and Metrology
The technique for delay analysis utilized in this claim is “Time Impacted Analysis” and “Window analysis” in order to measure the impact of all delay events accurately. Time Impact Analysis Technique is Actual Based Approach Which depends on the actual consequence and dates happened in the site during the execution not only the planning schedule. TIA is widely recognized by the construction industry as the most accepted method to quantify schedule delay. In this method the analyst develops and adds a model of the change to an approved schedule to quantify the delay to project completion.
Window analysis is a time impact technique which focus on the impact of delays in specific periods of time identifying gains or losses delays and recovery to the actual critical and sub critical paths as they occur with each period of time of the project life cycle is divided into a series of consecutive time Windows.
For Each window
- Each window is analyzed to identify the activities that were impacted delay or recovery and the results are investigated to identify the events that caused the deviation in progress
- Analysis steps
Step 1: Incorporate delay events that have been occurred in the period
Step 2: Establish the impact on time for Completion.
Step 3: Update the impacted programme with progress within the window period.
Step 4: Establish the impact on the Time for Completion.
D1: Impact delay period due to “Employer Delay Events”
D2: Impact delay period due to “Contactor Delays” from the update.
DELAY ANALYSIS METHODOLOGIES
- Impacted As Planned
- Time Impacted Analysis (Time Impacted window Analysis)
- Collapsed as Built
- As-Planned Vs. As-Built





Reviews
There are no reviews yet.