Sale!

Time Impacted delay Analysis methodology to claim 48 calendar days extension of time to complete a Construction project. Editable MS Word, Excel and .xer files

Original price was: 45,00 $.Current price is: 18,00 $.

Guaranteed Safe Checkout

This delay analysis documents were prepared to claim 48 calendar days extension of time to complete the project. Following Delay Events were impacted planned project completion.

  1. INCLEMENT WEATHER CONDITION
  2. Delay due to change in footing design type from individual to combined footing and approval of same from Dubai Municipality
  3. Pandemic COVID-19

 

This delay analysis documents package includes following

  1. Narration of delay analysis technique and delay events
  2. Condition of Contract
  3. Substantiation of delay events
  4. Approved Baseline Programme
  5. Impacted Programme

 

Delay Analysis methodology

  1. In TIA method, to find out impact of a particular delay event, an updated programme is used (instead of the baseline programme) which should be updated just before the delay event had its effect on the project. A delay fragnet, consisting of activities related to the delay events, is introduce into the updated program and all the necessary links are made. The programme is then re-run again on the data date of the updated programme. If the delay event affects the critical path of the updated programme, the project completion date will be extended by showing a new project completion date. The difference in number of days between the new project completion date and the one before the delay event is inserted (i.e. at the data date of the updated programme) gives the delay impact of the delay event on the project.

 

DELAY ANALYSIS METHODOLOGIES
  1. Impacted As Planned
  2. Time Impacted Analysis (Time Impacted window Analysis)
  3. Collapsed as Built
  4. As-Planned Vs. As-Built

Reviews

There are no reviews yet.

Be the first to review “Time Impacted delay Analysis methodology to claim 48 calendar days extension of time to complete a Construction project. Editable MS Word, Excel and .xer files”

Your email address will not be published. Required fields are marked *

Time Impacted delay Analysis methodology to claim 48 calendar days extension of time to complete a Construction project.Time Impacted delay Analysis methodology to claim 48 calendar days extension of time to complete a Construction project. Editable MS Word, Excel and .xer files
Original price was: 45,00 $.Current price is: 18,00 $.
Scroll to Top