Sale!

Construction Programme or Baseline Programme (.xer file) for a 2B + GF + 14 Floors + Lower Roof Hotel Building.

Original price was: 40,00 $.Current price is: 16,00 $.

Guaranteed Safe Checkout

This package includes following:

  1. Construction Programme or Baseline Programme in xer and PDF file format.
  2. WBS

Project Duration: 18 Months including one Month Mobilization.

Detailed L4 construction with Cost, Manpower, and plant & equipment loaded for a 2B + GF + 14 Floors + Lower Roof Hotel Building. Sequence follow for the Programme. Following are the high level WBS details. It’s very details Programme.

  1. LOA, Contract agreement, NOC, concerned authorities approved Drawing and Consultant letter to commence work at site prior to commencement of the Project.
  2. Engineering Submission and Approval.
    1. Internal Subcontractor Pre-qualification Submission and approval
    2. Provisional Sum (PS) items Subcontractor and Supplier nomination and issuance of Subcontract agreement and LPO
    3. Prime Cost (PC) items Subcontractor and Supplier nomination and issuance of Subcontract agreement and LPO
    4. Substructure, super Structure and finishes items Materials, Technical data Sheet and Sample Tag submission and Approval.
    5. Provisional Sum items Materials, Technical data Sheet and Sample Tag submission and Approval.
    6. Prime Cost items Materials, Technical data Sheet and Sample Tag submission and Approval.
    7. Shop Drawing Submission and Approval.
      1. General Shop drawing
      2. Architectural Shop drawing
  • Structural Shop drawing
  1. Finishes Shop drawing
  2. Builders works Shop drawing
  3. Power and Lighting Shop drawing (wall , Floor and High level)
  • Water Supply Shop drawing
  • Drainage Shop drawing
  1. HVAC Drawing Shop drawing
  2. ELV and Home Automation Shop drawing
  3. Fire Fighting Shop drawing
  • Fire Alarm Shop drawing
  • Coordination Shop drawing Shop drawing
  • RCP Shop drawing
  1. Provisional Sum items Shop drawing
  1. Engineering Procurements
    1. Civil Long lead items
    2. MEP Long lead items
  • Provisional Sum Long lead items
  1. Prime Cost Long lead items
  1. Construction works.
    1. Civil Works
      1. Sub Structure
      2. Super Structure
      3. Finishes
        1. Internal Finishes
        2. External Finishes
      4. MEP Works
        1. MEP internal Works
          1. Electrical Power and Lighting
          2. Home Automation and ELV works
          3. Water Supply and Drainage works
          4. HVAC Works
          5. Fire Fighting and Fire Alarm works
        2. MEP External Works
      5. Substantial Completion
      6. Authority Approval
      7. Snagging and De Snagging
      8. Testing and Commissioning
      9. Handover project to the Client
2B + GF + 14 Floors + Lower Roof Hotel BuildingConstruction Programme or Baseline Programme (.xer file) for a 2B + GF + 14 Floors + Lower Roof Hotel Building.
Original price was: 40,00 $.Current price is: 16,00 $.