Methodology or technique use to determine or prepare the Extension of time claim.

Methodology or technique use to determine or prepare the Extension of time claim.
Methodology or technique use to determine or prepare the Extension of time claim.

The methodology or technique used to determine and prepare an Extension of Time (EOT) claim in construction requires a systematic approach. The goal is to demonstrate that a delay has affected the project’s critical path and that the delay event qualifies under the contract provisions for an extension. The methodology typically involves delay analysis techniques, which are used to establish the cause, impact, and duration of the delay.

Below are some common methodologies and techniques used to prepare an EOT claim:

1. Critical Path Method (CPM)

The Critical Path Method (CPM) is one of the most important techniques for analyzing delays and determining the validity of an EOT claim. This method focuses on identifying the critical path, which is the sequence of activities that determines the minimum time needed to complete the project. Any delay in activities on the critical path directly impacts the project completion date.

Steps:

  • Create a Baseline Program: Develop a detailed project schedule using CPM, with all project activities and their dependencies clearly outlined.
  • Identify the Critical Path: Determine the sequence of activities that are critical for project completion (those that cannot be delayed without affecting the completion date).
  • Impact of Delay on Critical Path: Analyze how the delay event affects the activities on the critical path. If a delay occurs in a non-critical activity, it may not justify an EOT.

Example:

If excavation (a critical activity) is delayed due to unforeseen underground utilities, the entire project will be delayed. This delay justifies an EOT since it affects the critical path.

2. Delay Analysis Techniques

Several delay analysis techniques are commonly used to evaluate the impact of delays on the project schedule and justify the EOT claim. The choice of technique depends on the complexity of the project, the type of delay, and the data available.

a. As-Planned vs. As-Built Analysis:

This method compares the as-planned schedule (the original schedule at the start of the project) with the as-built schedule (the actual progress and dates when activities were completed).

  • As-Planned: The contractor’s baseline schedule of how the project was intended to be completed.
  • As-Built: The actual completion dates for each activity after the delay occurred.
  • Comparison: By comparing both schedules, it can be determined how the delays impacted the project. Delays on the critical path activities will show the need for an extension of time.

b. Impact as Planned:

In this technique, the delays are inserted into the as-planned schedule to assess their impact. This is done by introducing the delay event into the schedule at the point where it occurred and then recalculating the completion date.

  • The delay event is introduced, and its impact on critical and non-critical activities is assessed.
  • If the completion date shifts due to the inserted delay, an EOT may be justified.

c. Collapsed As-Built (or “But For” Analysis):

The collapsed as-built method removes the delay events from the as-built schedule to determine the project completion date without delays. This helps in understanding the impact of the delays. The key question is: “But for the delays, when would the project have finished?”

  • By removing delays that are beyond the contractor’s control, the analysis shows what the completion date would have been, thus supporting an EOT claim.

d. Window Analysis (Time Impact Analysis – TIA):

This is a dynamic approach where the project schedule is divided into windows or periods (e.g., monthly). The schedule is updated periodically, and each window is analyzed to determine the impact of delays on the critical path.

  • Time Windows: The project is divided into smaller periods, and delays in each window are analyzed.
  • Impact Assessment: The impact of the delay is assessed in real-time (e.g., every month) rather than waiting until the end of the project.
  • Real-Time Documentation: This method allows for proactive delay management and documentation during the project.

e. Time-Impact Analysis (Prospective Analysis):

Time-Impact Analysis is used for prospective claims, where delays are analyzed while the project is ongoing. In this technique, a delay event is added to the project schedule to assess how it will affect future progress.

  • Delay Introduction: Delays are introduced into the project schedule at the time they occur, and their impact on the critical path is calculated.
  • Updated Completion Date: This updated completion date is then used to assess whether an EOT is required.

3. Categorizing Delays:

When preparing an EOT claim, it is crucial to categorize the delays into different types because not all delays justify an extension. The delays need to be assessed according to their origin and impact.

a. Excusable vs. Non-Excusable Delays:

  • Excusable Delays: Delays that are beyond the contractor’s control (e.g., force majeure, design changes, client-related delays).
  • Non-Excusable Delays: Delays caused by the contractor’s failure, such as poor site management or lack of resources.

b. Compensable vs. Non-Compensable Delays:

  • Compensable Delays: Delays for which the contractor is entitled to both time extension and monetary compensation (e.g., client-driven delays).
  • Non-Compensable Delays: Delays where only time is granted, with no monetary compensation (e.g., force majeure events like natural disasters).

c. Concurrent Delays:

  • Concurrent Delays: If both the contractor and the client are responsible for delays that happen at the same time, the contract will need to specify how to handle these. Often, an extension of time may be granted without compensation.

4. Documentation and Record Keeping

Accurate and timely documentation is crucial for a successful EOT claim. The following documents and records should be prepared to support the claim:

  • Project Baseline Schedule: The original schedule that shows how the project was planned to be executed.
  • Daily Site Logs: Record of daily progress on-site, weather conditions, delays, and any disruptions.
  • Correspondence and Communications: Emails, letters, and meeting minutes that highlight discussions on delays or changes in the project.
  • Change Orders: Any official changes in scope or design that caused the delay.
  • Subcontractor Reports: Reports from subcontractors that provide evidence of delays due to procurement, material availability, or labor shortages.
  • Photos and Videos: Visual evidence of site conditions that contributed to delays (e.g., flooding, underground obstacles).
  • Expert Reports: Assessments from geotechnical engineers, consultants, or surveyors when delays are related to unforeseen site conditions.

5. Claim Preparation and Submission

Once the delay is analyzed and the impact on the project is determined, the contractor prepares the EOT claim for submission. Key elements to include in the claim are:

  • Cause of Delay: Clear identification of the event that caused the delay, whether it is excusable, compensable, or concurrent.
  • Impact on the Critical Path: Explanation of how the delay event affected the critical path and led to a need for time extension.
  • Duration of Delay: Calculation of the number of days the project was delayed as a result of the event.
  • Request for Time Extension: Formal request for a specific number of days of extension based on the delay analysis.
  • Supporting Documentation: All the relevant schedules, logs, reports, and communications to substantiate the claim.

6. Dispute Resolution for EOT Claims

In cases where the EOT claim is contested by the client, disputes may arise. Common dispute resolution methods include:

  • Negotiation: The contractor and client may attempt to reach a mutually acceptable agreement on the extension.
  • Mediation or Arbitration: A third-party mediator or arbitrator may help resolve the dispute without going to court.
  • Litigation: As a last resort, the dispute may proceed to court for legal resolution, though this is typically more time-consuming and costly.

Example of EOT Claim Preparation:

Scenario: A contractor is building a hospital, and midway through construction, there is a significant change in the design requested by the client. The contractor identifies that this design change will impact the critical path and delay project completion by 45 days.

  1. Critical Path Analysis: The contractor uses the Critical Path Method (CPM) to show that the design change delays critical path activities such as steel framing and MEP (Mechanical, Electrical, and Plumbing) installations.
  2. Delay Categorization: The delay is categorized as an excusable and compensable delay because it was caused by a client-requested design change.
  3. Time Impact Analysis (TIA): The contractor performs a Time Impact Analysis, inserting the design change delay into the schedule and recalculating the new project completion date.
  4. Documentation: The contractor prepares all relevant correspondence, revised drawings, daily logs, and updated schedules showing the impact of the delay.
  5. Submission: The contractor submits a formal EOT claim to the client, requesting a 45-day extension along with compensation for the additional costs incurred due to the delay.

Conclusion:

Determining and preparing an Extension of Time (EOT) claim in construction requires a detailed and methodical approach. The use of delay analysis techniques, such as the Critical Path Method, As-Planned vs. As-Built, or Time Impact Analysis, helps contractors demonstrate how a delay impacts the project schedule and justifies an extension. Proper documentation, timely submission, and an understanding of contract provisions are

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version