Site icon The Engineers Blog

As-Planned vs. As-Built Delay Analysis in Construction.

As-Planned vs. As-Built Delay Analysis in Construction.

As-Planned vs. As-Built Delay Analysis in Construction.

Introduction

The As-Planned vs. As-Built Analysis is one of the simplest and most commonly used techniques to evaluate the impact of delays in a construction project. It involves comparing the as-planned schedule (the schedule agreed upon at the beginning of the project) with the as-built schedule (the actual schedule showing how the project progressed and was completed). The goal is to identify any variances between the planned and actual execution of activities, which helps in determining the impact of delays and justifying an Extension of Time (EOT) claim.

This analysis is particularly useful in retrospective delay analysis, where the contractor or client seeks to understand how delays affected the project completion date after the fact.

Key Components of As-Planned vs. As-Built Analysis

  1. As-Planned Schedule:
  1. As-Built Schedule:
  1. Comparison Process:
  1. Identification of Delays:
  1. Critical Path Impact:

Steps in As-Planned vs. As-Built Analysis

1. Prepare the As-Planned Schedule:

The contractor develops a detailed as-planned schedule at the start of the project. This schedule should include:

2. Record the As-Built Schedule:

During or after construction, the as-built schedule is prepared to show the actual dates when activities started and finished. This schedule is based on site logs, progress reports, and daily records.

3. Compare the Two Schedules:

The as-planned and as-built schedules are compared activity by activity to identify variances. The comparison highlights:

4. Identify Delay Events:

For each variance, the analysis must determine the cause of the delay and whether the delay was excusable (beyond the contractor’s control) or non-excusable (the contractor’s responsibility).

5. Assess Impact on Critical Path:

Delays that occur on the critical path are particularly important because they directly affect the project completion date. The analysis checks whether the delayed activities were on the critical path and recalculates the project’s overall completion date.

6. Prepare EOT Claim:

Based on the analysis, the contractor prepares an Extension of Time (EOT) claim if delays were excusable and affected the critical path. The EOT claim includes the revised completion date and supporting evidence of delays.

Example of As-Planned vs. As-Built Analysis

Project Scenario:
A contractor is building a shopping mall, and the project has a planned completion date of December 31. The baseline schedule includes critical activities such as excavation, foundation work, steel framing, and roofing.

As-Planned Schedule (Baseline):

As-Built Schedule:

Comparison:

  1. Excavation: Completed as planned, no delay.
  2. Foundation Work: Delayed by 20 days due to unforeseen underground utilities (an excusable delay event).
  3. Steel Framing: Start delayed by 24 days due to the delayed foundation work (critical path delay).
  4. Roofing: Delayed by 25 days because the steel framing was late (critical path delay).

Analysis:

Conclusion of the Analysis:

Advantages of As-Planned vs. As-Built Analysis

  1. Simplicity: It’s a straightforward method for comparing what was planned with what actually occurred, making it easy to identify delays and disruptions.
  2. Clarity: Provides a clear, visual comparison between planned and actual progress, making it easy for both parties (contractor and client) to understand where the delays occurred.
  3. Effective for Retrospective Analysis: This method is particularly useful for evaluating delays after the project is completed or during a later phase.

Disadvantages of As-Planned vs. As-Built Analysis

  1. Limited to Retrospective Analysis: This method is best suited for analyzing delays after they occur, making it less effective for managing delays in real-time.
  2. No Dynamic Updates: Since the comparison is usually done after the fact, it does not provide a dynamic, ongoing assessment of the project, unlike other techniques such as Window Analysis.
  3. May Not Consider Complex Interactions: It might not fully account for complex delay interactions, such as concurrent delays or acceleration efforts.

Conclusion:

The As-Planned vs. As-Built Analysis is a fundamental delay analysis technique in construction projects. By comparing the baseline schedule to the actual progress, it helps identify delays, assess their causes, and determine whether an Extension of Time (EOT) is justified. The analysis focuses heavily on the critical path, as delays to critical activities will directly affect the overall project completion date. This method is particularly useful for retrospective claims, where the impact of delays needs to be assessed after they have occurred.

Exit mobile version