Method Statement Title: Testing and Commissioning of LV Switch boards / Panels.

METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
METHOD STATEMENT FOR LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION

Method Statement Title: Testing and Commissioning of LV Switch boards / Panels.

1.0       Scope

1.1       This method statement details the Testing and Commissioning of LV Switch boards / Panels  according to the specification section 16402.

            Note :  A separate method statement is submitted for installation of L.V. Switch

                        boards / Panels. ( Ref. ETA /MS/E-009 )

2.0       Material

  • All the materials shall be as per approved material submittals.
  • Size and number of LV Switch boards / Panels shall be as per approved shop drawing and  load schedule.
  • Identifications and labels.

3.0       Applicable Location

  • L.V. rooms for E1,E2,E3 & W1,W2,W3 Towers Located in Podium areas.

4.0       Instruments.

4.1       Insulation Resistance tester ( Megger ) with Variable Voltage selections.

  • Phase Sequence meter.

4.3       Multimeter.

Note : The caliberation certificates of testing instruments shall be verified prior to usage and copies shall be included in the test reports.

  • Inspection Procedure :
  • Visual, Mechanical and Operational checks as per the format enclosed.
  • Test Procedure :
  • Insulation Resistance Test  using 500V Megger:
  • Check the tightness of connections.
    • Clean all the supporting insulators.
    • Isolate the cables on incoming and outgoing side.
    • Apply a megger voltage of 500Volts DC between Phase ‘R’ to earth for 1 min with Phase ‘Y’,’B’ & ‘N’ shorted and earthed and record the values.
    • Similarly continue the test and record the values for the other phases.
  • Operational Checks:
  • Connect the required control supply as per the schematic.
    • Check the operation of the switchgear i.e. closing / tripping of switchgear from local and control points.
    • Check the operation of protective relays.
    • Check the operation of interlocks, alarms and indications circuits as per the approved schematic
  • Safety :
  • Only experienced and skilled personnel shall be engaged for testing.
  • Safety guards shall be in place and secured prior to start-up.
  • Warning signs and tapes shall be placed during start-up and commissioning as required.
  • All safety procedures shall be followed in accordance with the project health and safety plan.
  • Safety officer shall check and ensure all safety precautions as followed.
  • Records:
  • Site Test Reports.
  • Caliberation certificates of testing instruments.

9.0       Reference :

  • Specification Section 16402.
  • Approved Drawings.

10.0     Enclosures : Test Report for LV Switch board.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version