Method Statement Title: Testing and Commissioning of Light fixtures.

METHOD STATEMENT FOR LIGHTING FIXTURES INSTALLATION
METHOD STATEMENT FOR LIGHTING FIXTURES INSTALLATION

Method Statement Title: Testing and Commissioning of Light fixtures.

1.0       Scope

1.1       This method statement details the Testing and Commissioning of Light fixtures  according to the specification section 16505.

            Note:   A separate method statement is submitted for installation of Light fixture.

                        (Ref. ETA /MS/E-023)

2.0       Material

  • All the materials shall be as per approved material submittals.
  • Sizes of PVC wires shall be as per approved shop drawings / system manufacturers recommendation.
  • Type of Luminaire shall be as per approved shop drawings.

3.0       Applicable Location

  • Tower E1, E2, E3 & W1, W2, W3, Podium areas and Villas.

4.0       Instruments.

4.1       Insulation Resistance tester (Megger) with Variable Voltage selections.

4.3       Multimeter.

  • Test Procedure :
  • Physical check :
  • Check the electrical components such as Light fixtures are connected to the final circuit of the distribution board.
    • Check the installation of Light fixture.
  • Insulation Resistance Test using 500V Megger:
  • Check the tightness of connections.
    • Apply a megger voltage of 500Volts DC between  Phase ‘R’ to earth for 1 min with Phase ‘Y’,’B’ & ‘N’ shorted and earthed and record the values.
    • Similarly continue the test and record the values for the other phases.

5.3       Lux level checked by lux meter.

  • Safety :
  • Only experienced and skilled personnel shall be engaged for testing.
  • Safety guards shall be in place and secured prior to start-up.
  • Warning signs and tapes shall be placed during start-up and commissioning as required.
  • All safety procedures shall be followed in accordance with the project health and safety plan.
  • Safety officer shall check and ensure all safety precautions as followed.
  • Records:
  • Site Test Reports.
  • Calibration certificates of testing instruments.

9.0       Reference :

  • Specification Section 16505.
  • Approved Drawings.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version