Method Statement for Protection of Existing Gas Pipelines Using Precast Concrete Slabs

HDPE PIPE BUTT WELDING PROCEDURES

HDPE PIPE BUTT WELDING PROCEDURES

CONTENTS

  1. Purpose
  1. Responsibilities
  1. Attachments

1.0      Purpose

  1. To ensure that the protection of existing gas pipelines using precast concrete slabs, and related activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

2.0      Scope of Work

3.0      Definitions

3.1     CM               Construction Manager

3.2     PE/SE           Project Engineer/Site Engineer

          3.3     CS                Chief Surveyor

          3.4     ME               Material Engineer

          3.5     ESHO           Environmental, Safety, and Heath Officer        

4.1     Specifications:         Volume 3 – Section 9 – Part A

          4.2     Drawings:               Volume 2 – Section 8 – Part B – Civil, Mechanical and

                                                  Navaids, Drawing No. PGAD 745/1008/C/187, Rev. A                                

          4.3     B.O.Q                     Bill No. 18

          4.4     Method Statements: 1008-OAJ-MS-1002-R2 Method Statement for General

                                                  Excavation and Filling

                                                  1008-OAJ-MS-1012 Method Statement for Excavation

                                                  to Locate Existing Services

 

7.0      Tools, Plant and Equipment

8.0      Prior Activities

10.0  Responsibilities

  1. The CM will coordinate with SE and ensure that the necessary resources to implement the approved method statement have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved method statement.
  1. The ME will ensure that the materials being used are in accordance to the project specifications and the approved method statement.

The ESHO, along with his team, will ensure implementation of all ES&H procedures related to the nature of the works being carried out and is in accordance with ES&H Plan.