Site icon The Engineers Blog

Method Statement for Excavation and Foundation Preparation of Box Culvert

Method Statement for Sub base and Gravel Base

Method Statement for Sub base and Gravel Base

Table of Contents

  1. Purpose
  1. Responsibilities
  1. Attachments

 

1.0       Purpose

  1. To ensure that all excavation and foundation preparation of Box Culvert activities are executed safely and in accordance with the contract requirements and that all quality assurance / control activities are conducted in a systematic manner, works are inspected and conformance is verified and documented.

2.0       Scope Of  Work

3.0       Definitions

         ME                   Material Engineer

                                                                                          Infrastructure.

4.2    Drawings                     Vol 2- Section 8 – Part B – Civil ,Mechanical and Navaids

 

7.0       Safety

8.0       Prior Activities

   9.1  Trenches for Box Culvert shall be excavated to the lines and grades indicated on the 

   approved shop drawings by using Excavator as per clause 201.2.1

   9.2 Excavations dimensions will allow for the necessary working distance around the structure to permit the erection and removal of scaffolding and formwork (approx. 2m from concrete edge).

   9.3 The excavated materials shall be removed by dumper trucks as per clause 201.2.5 

9.4 The bottom of excavation shall be watered, leveled and compacted.

9.5 Bottom level of excavation and compaction will then be checked for approval by the Engineer’s Inspectors before any further activities are carried out as per clause 201.2.8

10.0   Responsibilities

  1. The CM will coordinate with SE to ensure that the necessary resources to implement the approved Method Statement and the JHA have been allocated to the task.
  1. The SE will ensure that the site preparation activities are conducted according to the approved Method Statement and the related JHA.
  1. The ME will ensure that the materials being used are in accordance to the Project Specifications, the approved Method Statement and the related inspection and testing plan.
  1. The ESHO officer, along with his team, will ensure implementation of all ES&H procedures related to the nature of the works being carried out for compliance with the Project Safety Plan and JHA.
Exit mobile version