Intimation for the work under hold

Reply - Notice of Delay

Reply - Notice of Delay

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. 373-1297 at Al Barsha 1st, Dubai U.A.E

Sub                : Intimation for the work under hold/ unable to revise the shop drawing since long time and request to release the confirmation

Dear Sir,

With reference to the above, we would like to inform you that, kindly issuethe Engineer’s instruction or drawings for the following which are under consideration since long time;

  1. The variation for waterproofing/ MEP on floor of the future cafeteria is under hold at basement .

So, this is for your kind intimation that Main Contractor is not responsible for the delay of the work and extension of time to be granted for the delay in approval or instruction. Because our work is under hold and we are unable to prepare the shop drawing and variation work  for your approval prior to execute the work and release the queries.

So, kindly do needful for all pending issues as well as Contractor have reserve the right to calim on impact on project constraints, the scope,time and cost accordingly.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager