Cost over run for preliminaries for document

Running Cost

Running Cost

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject         : Cost over run for preliminaries for document

Dear Sir,

With reference to the above, regarding submission of R7, R9  & R10 program in A1 size and kindly the following:

  1. Multiple scanning and uploading in box and its cost is already a serious over burden for the contractor because the comments by many terminal as well as repeated submissions/ comments and changes (cost over run).

            a)Firstly,  it is not a drawing, why it should be submitted in A1 size?

            b)Secondly, R7 & R9 are the intermediate program ,which are not being followed or not  valid now , which can be used only for the reference. So we can provide the soft copy for client’s  reference ,not in A1 size, if required by them they can print the same.

Furthermore, we are providing the soft copies of R7, R9 & R10 for the reference and to fulfill requirement.

So, this is for your kind intimation that we are facing a tough time with over run for printing and re printing.

Kindly support, coordinate and request to demand which is reasonable and required, because the program copy in A1 we consider as unreasonable and not required.

This is for your kind information.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager