Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject           : Regarding your comment for the SS spout and LED light for submitted swimming pool drawings

Dear Sir,

With reference to the above, kindly note the following with respect to the comments which is mentioned in the drawing no.U-1621-C-01 (copy attached):

  1. Your comment that MEP subcontractor to coordinate with ID and Architecture to fix the water spout .Please note that, this is not Main Contarctor’s scope, the client should decide the same.

So, Kindly review our concern, advice and do the needful accordingly.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager