Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor

PT WORKS
PT WORKS

Date: xxx

Ref no: CC/DT/DM/12

To,

Dubai Municipality

Building Control section

Dubai, UAE

Project        : 2B + G + 14+ Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai

Sub                : Submission of the proposal to close the distribution pump opening in PT slab from 4th floor to roof located in corridor

Dear Sir,

With reference to the above, we are hereby submitting the proposal and approval by the consultant and design confirmation by the PT subcontractor and attaching herewith the following for your reference and review.

  1. Consultant approval
  2. Method of statement
  3. VLM Emirates (PT subcontractor design confirmation
  4. DM approved drawing for temporary opening
  5. Design proposal for closeout with “L” angle and rebar

So, kindly review and request to close the violation

Regards,
For xxx Contracting L.L.C

xxx

General Manager

By Md Abu Zaed Khan