Resubmission of Variation for the LPG Placement over the Ramp Area

Central Gas System
Central Gas System

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project:            2B + G + 14+ Lower Roof Hotel Building on Plot No. xxx at Al Barsha 1st, Dubai

Subject         :  Resubmission of Variation for the LPG Placement over the Ramp Area

                         (Only for Structure and Civil Works) new building permit no xxx

                        transmittal ref no  AP/269/CC/62.

SRNO  ITEM DESCRIPTION IN NOMINATIONCONTRACT BOQ ITEM REF  QTY  UNIT  RATE  AED
        1  Covering of Cut out for LPG placement over the ramp area between Grid 1-2/A-B with steel structure and other required work ( Only for steel structure and Civil Work)   Other variation will be submitted  separately    NEW SCOPE Not available in Contract Bldg. Permit No. 3731297 241570-26-1  dated 29/10/17          135,602.17        135,602.17
                                                                                                                                                 TOTAL AED  135,602.17

( Dirham:  One Hundred Thirty Five Thousand  six hundred two and seventeen fills only)

Attached are herewith

  1. Variation at first floor ( revised).
  2. Proof for dimensions for various activities.
  3. AL KARAM  METAL WORKS LLC( Supply and Installation Quotation with break down of total cost).
  4. M/s NASCO  STEEL CONTRUCTION LLC ( Supply and Installation Quotation break down of total cost).
  5. AL BALAD METALS CONTRACTING LLC( Supply and Installation).
  6. HILTI quotation ( for chemical tubes)

NOTE   : Two sub contractors have submitted macro level break up for their total cost whereas the third one has not yet submitted.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment