Site Meeting

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Required Engr.  Instruction for the AC Opening in Lift Wall

Dear Sir,

With reference to above mentioned subject, we are awaiting your formal instruction to provide the opening of AC ( 8”X 8”) size pipe sleeve  as discussed in meeting held to your office last Jan. 21, 2017 ( Saturday) for  Lift Shaft.  Kindly issue the formal Engineer’s Instruction on approved Lift Shop Drawing and this proposed opening should not be an obstruction for the Lift Sub-Contractor  equipment shifting or installation.

This is only for your kind information and record.

NOTE: If no further Engineer’s Instruction received we will close all the sides of Lift Shaft.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager

By Md Abu Zaed Khan