Reply to your letter Ref: xxx Dated xxx

Letter Sample
Letter Sample

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Dear Sir,

With reference to your letter Ref: AP/269/CC/246 Dated 19.02.2017, kindly note that the Contractor Claim as per FIDIC 4th Edition reprinted in 1992, “Clause 44.(c)”, Contractor is entitled to have claim for adverse climatic conditions as per agreed Terms and Conditions in FIDIC.

Kindly review accordingly as per our Contract.

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager