Delay in supply of WC tank, approval of tile corner

delivery-delay

delivery-delay

Date:               xxx

Ref:                  xxx

Kind Attn         :Mr. xxx

Project             :2B + G + 14 + Lower Roof Hotel Building on Plot No. xxx at Al Barsha

1st, Dubai U.A.E.

Subject            : Delay in supply of WC tank, approval of tile corner or decision as well as ELV/ GRMS issue under clause 44.1(d)

Dear Sir,

With reference to the above, we are facing the severe delay in the extension due to pending issues with you and kindly note the following:

  1. As per our letter ref no:CC/AP/198/16 DT.01.12.16, item no.1 and 2 which are self-explanatory,that work under delay since 16.12.16 till date due to non-availability of WC tank to be supplied by the employer (delay in supply after intimation –65 days)

So, kindly find our intimation under clause 53.1

Regards,

For xxx Contracting L.L.C.

xxx

Project Manager