Regarding Non submission of technical details and samples of materials and accessories

shake-up-sales-meeting
shake-up-sales-meeting

Date                : xxx

Ref                   : CC/DESTEC/004

To                    : M/s. xxx GROUP, PO Box 47395, Sharjah UAE.

Project             : 2B + G + 14 + Lower Roof Hotels Building on Plot No. 373-1297 at Barsha, Dubai

Subject            : Regarding Non submission of technical details and samples of materials and accessories

Dear Mr. xxx,

With reference to the above mentioned subject, we would like to intimate you again the submission of technical details and sample board/samples for materials and accessories are still awaited from your side.

As you intimated consultant will take 14 days for reviewing any submittal and revised submittal also same. Without approval of materials you can’t start work at site

So, this is for your kind intimation to submit pending submittal as an earliest possible.

Regards,
For xxx Contracting L.L.C                       

xxx

Project Manager

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version