Request to add the Contractor’s point/concern in Minutes of Meeting

Minutes of Meeting

Date: xxx

Ref.: xxx

Total Pages: 1

To,

xxx

Attention:      xxx

Project:          xxx.

Subject:           Request to add the Contractor’s point/concern in Minutes of Meeting

Reference:       MCM/AAZ/OCAC/04/2019 dated 26th November 2019

                        MCM/AAZ/OCAC/05/2019 Reminder -1 dated 8th December 2019

MCM/AAZ/OCAC/05/2019 dated 24th December 2019

MCM/AAZ/OCAC/07/2019 dated 6th January 2020

MCM/AAZ/OCAC/12/2019 dated 19th January 2020

Dear Sir,

With reference to Progress Minutes of Meeting – 15, we would like to add following point in the status column of respective items. Also note that MCM still waiting for Provisional Sum and Prime Cost items Subcontractor/Supplier.

ItemsDecision & InstructionStatusPints to be added
1.1.1Program of Works25 Days DelayMCM submitted EOT Claim and the same under review with OC
1.3.5Swimming pool contractor to be nominatedSubcontractor nominated by client- MCM to Sign Contract – Sub Contractor Visited site today- Balancing tank Below Ground -beside Pump Room and heater/Cooling Machine above Garage Level Slab.Nomination documents yet to receive by MCM. Upon received of approved quotation from Client/Consultant MCM will facilitate Sub-Contract Agreement.

This is for your kind action and record.

Yours Sincerely

XXX

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.