Site icon The Engineers Blog

Method Statement Title: Welding Procedure

METHOD STATEMENT FOR BRAZING & JOINTING OF COPPER PIPES

METHOD STATEMENT FOR BRAZING & JOINTING OF COPPER PIPES

Method Statement Title: Welding Procedure

1.0       Purpose

To define the Method of Welding Pipe Lines.

2.0       Scope

The Method is applicable to all Chilled Water Pipe work using mild steel and carbon steel pipes and fittings, for pipe sizes 65mm dia and above in accordance with Specification Section 15050, Clause 3.04, Clause 3.07 and our material submittals reference M:002 & M:30

3.0       Method

Before commencement of any welding the following works are required to be carried out.

                        3.1.1    Check materials to be used have approved material submittals.

3.1.2    Check work areas are clean and safe ensuring that the area is free of all flammable or volatile material.

                        3.1.3    All welding work shall be carried out in open or ventilated areas.

                        3.1.4    Welders qualification will be verified as per requirement.

            3.2       Welding Procedure

3.2.1    Measure length of pipe required, making due all allowance for any pipe fittings to be used and cut the pipe to the measured length.

3.2.2    Prepare the end of the pipe to be welded to the right angle of level and the size of the root face in accordance with procedure Specification (copy attached).  The surfaces to be welded shall be smooth, uniform and free from tears, scale, slag, grease, paint and other materials that might affect the quality of welding.  Power tools or hand tools will be used for cleaning, grinding or both.

3.2.3    The two prepared ends to be welded, pipe to pipe or pipe to fitting, shall be aligned as accurately as is practical and ensuring that the spacing between the abutting ends is in accordance with the procedure specification used.  The alignment of the abutting ends shall minimize any offset between the surfaces caused by dimensional variations and will equally distribute around the circumference of the pipe any such offset.  Hammering of the pipe to obtain proper lineup will be kept to a minimum.

3.2.4    The two prepared ends shall be tack welded together in four positions at ninety degrees.  After tacking, the alignment shall be checked to confirm the integrity of the alignment has been preserved.  During the welding process the tacks shall be removed by grinding.

3.2.5    The welding process will commence, ensuring that the correct filler metal, electrical current, polarity, voltage, amperage and number  of passes is in accordance with the welding procedure.  All slag or foreign matter shall be removed from each pass of welding, including the repair of any visible defects, such as crack, cavities, etc., prior to commencing the succeeding passes.  Any such impurities shall be removed using a grinder.

3.2.7    Clean the joint by wire brush prior to painting.

3.3       Welding Electrode Storage and Handling

4.0       Inspection & Testing

            5.2       Specification Section 15050, Clause 3.04, clause 3.07

            5.3       Welding Procedure Specification and PQR (Enclosed)

                        M&E / WPS / 1779

                        ETA-M&E/PQR/1698

            5.4       Welders Certificates

                        Welder’s Qualification Certificates Enclosed.

6.0       Safety

6.1       Safety items to be provided shall include fire extinguishers and welding screens.

6.2       Welding cables to be checked regularly for visual signs of damage.  Joints to be sheathed and taped.

6.3       Prior to commencement of work check welding M/C, current, voltage, earthing, etc., for safety.

6.4       Safety equipment (Example : Hardhats, Safety shoes, Overalls, Gloves, Goggles as necessary) to be worn at all times.  Standard welding Safety kit of shields, gloves, etc. to be provided for each welder.  Glasses to be checked for cracks / weld spatter.

6.5       Hot work permit to be obtained as per the site safety procedures prior to the commencement of work. 6.6       Site safety officer will check and ensure all safety precautions are taken prior to commencement of welding

Exit mobile version