Method Statement Title: Acoustic Insulation to Drainage Pipes

METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET
METHOD OF STATEMENT FOR DRAINAGE PIPE INSTALLATION INSIDE THE TOILET

Method Statement Title: Acoustic Insulation to Drainage Pipes

Scope

  1. This method statement applies to installation of acoustic insulation for drainage piping.
  • Purpose
  • Purpose of this method statement is to outline the method of storage, handling and installation of acoustic lining for drainage piping.
  • Materials
  • Revac SGQ 50-25FF Metallic foil faced flexible polymer sheet laminated to quilted glass wool approximately 24mm thick, tested to ISO 140-3/95.
  • Method
  • Receiving
  • When received at site, each pallet shall be checked for quantities, model numbers, physical damages, etc.
  • Receiving inspection shall be checked by Storekeeper, Engineer and QC Engineer, which shall be documented.
  • Storage
  • All Revac pallets are stored in a covered store.
  • Storekeeper will be responsible for proper storage and maintenance of records, as required.
  • Installation
  • The following areas of drainage pipes will be covered by acoustic lining.
  • High-level drain pipes in living areas/bed rooms, entrance foyers of apartments, lift lobbies, main lobby/reception areas, control room/offices, kitchens, bathrooms and any other occupied space.
  • Clean the drainage pipes prior to commencement of acoustic lining.
  • Wrap the pipes and fittings by Revac SGQ 50-25 FF sheets.
  • Revac SGQ 50-25 FF can cover either butt joint or overlap joint.
  • Aluminium foil tape should be used at maximum 250mm centers. All joints should also be covered with aluminium foil tape. Cut ends of glass fibre shall be enclosed by tape.
  • Vertical pipe lagging may require the acoustic barrier to be adhered to pipe to stop the material moving.

Note     Refer attached manufacturer’s instructions.

  • Inspection
  • Acoustic lining for drainage pipes shall be witnessed during false ceiling clearance inspections.
  • Safety
  • All safety precautions shall be followed as per established project safety plan and procedure.
  • Only experienced and skilled insulators shall be engaged for carrying out this work.
  • The people involved in the insulation shall have PPE safety helmets, safety shoes, gloves, etc., as required.
  • Safety officer shall check and ensure that all safety precautions are followed.
  • Safety officer shall check and ensure that all scaffolding and ladders used at site are having duly signed tags.
  • References
  • Manufacturer’s catalogue.
  • Approved submittal for acoustic lining for drainage piping. Ref. Submittal P-003.
  • Shop drawings.
  • Records
  • Work Inspection Request (WIR) duly signed by the Consultant.
  • Attachments

9.1       Manufacturer’s instructions.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.