Method Statement Title: Installation of Access Control System

ACCESS-CONTROL-SYSTEMS
ACCESS-CONTROL-SYSTEMS

1.0       Scope

This method statement details the method of installation of Access Control System.

            Note

            A separate Method Statement Ref. ETA/MS/E- 038   shall be submitted for testing and commissioning of the Door Entry System (CCTV System, Access Control System, Audio Intercom, Video Intercom)

2.0       Material

  • All materials shall be as per approved material submittals.
  • Type of cable shall be as per approved shop drawings / system manufacturers recommendation.

2.3       Type and location of Card readers, Door contacts, Magentic locks, Exit Push button shall be as per approved shop drawing.

3.0       Applicable Location

  • Tower E1, E2, E3, W1, W2, W3 (Entry to the Building from the Podium Areas upto Level 2)

4.0       Method

4.1       Storage  

4.1.1    All materials received at site shall be inspected and ensured against approved material submittal.  

4.1.2    Any discrepancies, damages etc. shall be notified immediately for further action. 

4.1.3    Material found not suitable for the project are to be removed from site immediately.  

  • Cables shall be stored with the factory packing on the flat surface.

4.1.5    Materials shall be stacked properly as per manufacturers recommendation and covered to prevent dust and water / moisture.

4.1.6    Access Control System Equipment to be stored as per manufactures recommendation mentioned / marked in the packing.

4.1.8    Ambient condition of the storage place to be as per manufacturer’s recommendation.

            4.2       Installation

                        4.2.1    Control  Cable

                                   4.2.1.1          Ensure the relevant current / approved shop drawings are available with installation team.    

                                   4.2.1.2          Transfer the cable to the work place with the help manpower..

                                   4.2.1.3          Check the cable drum for any external damage during transportation and ensure the type of cable against area of usage / application.

                                   4.2.1.4          Type and size of the cable is as per approved shop drawings.

                                   4.2.1.5          In concealed application pull cables manually through conduit installed as per approved shop drawings and approved method statements.

                                   4.2.1.6          Leave enough length of cable at both ends of panel and devices for termination.

                                   4.2.1.7              No through joints is allowed without the sanction of the

                        Consultants.

.

                        4.2.2   Access Control  Equipments.

                                   4.2.2.1             Ensure the relevant current / approved shop drawings are available with installation team.

  • Transfer the equipment to the work place with the help   

                        manpower.

                                   4.2.2.3              Location of the panel to be as per approved shop drawing after coordinating with other services.

                                   4.2.2.4             Fixing holes will be marked properly keeping back box of the panel in place.

                                   4.2.2.5             Fix back box properly and fix remaining panel accessories.

                        4.2.3   Card Readers

                                   4.2.3.1             Ensure the relevant current / approved shop drawings are available with installation team.

  •            Exact location of the Card Readers to be as per approved   

                       Shop drawing.

                                   4.2.3.3             For the Card readers, which needs to be fixed on the wall, fix appropriate G.I.back box.

                                   4.2.3.4             Install the Card readers and terminate the cable properly.       

                        4.2.4   Door Contacts

                                   4.2.4.1             Ensure the relevant current / approved shop drawings are available with installation team.

4.2.4.2           Exact location of the Door Contacts to be as per approved   

                       Shop drawing.

                                   4.2.4.4           Type of Door Contacts to be as per the location and type

                                                          of door i.e., either recessed or surface mounted

                                   4.2.4.5             For the Door Contacts, which needs to be fixed on the door, door supplier to provide appropriate provisions.

4.2.5.6           Install the Door Contacts and terminate the cable

                       Properly.

                        4.2.5   Locks

                                   4.2.5.1             Ensure the relevant current / approved shop drawings are available with installation team.

4.2.5.2           Exact location of the Locks to be as per approved   

                       Shop drawing.

                                   4.2.5.3           Type of Locks Contacts to be as per the location and type

                                                          of door i.e., either recessed or surface mounted

                                   4.2.5.4             For the Locks, which needs to be fixed on the door, door supplier to provide appropriate provisions.

4.2.5.5            Install the locks and terminate the cable Properly.

                        4.2.6   Exit Push Button

                                   4.2.6.1             Ensure the relevant current / approved shop drawings are available with installation team.

4.2.6.2           Exact location of the Push Button to be as per approved   

                       Shop drawing.

                                   4.2.6.3             For the Push Buttons, which needs to be fixed on the wall, fix appropriate G.I.back box.

                                   4.2.6.4             Install the Push Buttons and terminate the cable properly.

                        5.0      Records

            5.1       QC Installation Check List

            5.2       Inspection request duly signed-off by NMX and Consultant.

6.0       Attachment

6.1       QC installation checklist of Access Control System.

By Md Abu Zaed Khan

Hello, this is Engr. Zaed Khan Planning Engineer, Associate member of Society of Engineers UAE. Expert in construction project planning, FIDIC red book, computation of extension of time claim, Contract agreement and contractual letters.

Leave a comment

Your email address will not be published. Required fields are marked *

Exit mobile version